Resolved – (1) That the route map set out in paragraphs 3.8 - 3.30 of the report to unlock the restoration of the Mechanics Institute be noted. (2) That a budget of up to £110k, funded from the cashflowing reserve, in order to progress the development of options set out in the route map, be approved. (3) That the Director of Strategic Development be authorised to proceed with the development of the options set out in the route map. (4) That progress reports will be brought for consideration at key junctures identified within the report, and by no longer than 12 months from the date of this meeting. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM:JG)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
2.1.1 Note the route map set out in paragraphs 3.8 - 3.30 of the report to unlock the restoration of the Mechanics Institute;
2.1.2 Approve a budget of up to £110k, funded from the cashflowing reserve, in order to progress the development of options set out in the route map;
2.1.3 Authorise the Director of Strategic Development to proceed with the development of the options set out in the route map; and
2.1.4 Note that progress reports will be brought for its consideration at key junctures identified within the report, and by no longer than 12 months from the date of this meeting.
Further information on the subject of this report can be obtained from David Dewart, [phone removed], [email protected]. A Route Map for the Mechanics Institute Cabinet Date: 7th February 2024
3. Detail
Current Situation
3.1The Mechanics Institute occupies a prominent location at the heart of Swindon’s historic Railway Village. This area, which has Conservation Area status, is currently being regenerated through the Heritage Action Zone programme.
3.2The building has been empty since 1986, is in a poor state of repair and is defined as a Dangerous Structure under the Building Act. The building is also defined as At Risk by the Theatres Trust. The Council has erected hoarding around the perimeter of the site to discourage the public from entering the building. The cost of the hoarding installed in 2021 was £50k. The Council has been funding the upkeep of the hoarding since. The building, which has played an important historical role in the social and civic development of Swindon and the UK, is currently a blight on the townscape.
3.3The regeneration of the wider Railway Village and the Carriage Works, which is driving investment and increasing footfall to the area, has created more favourable preconditions for a potential restoration of the Mechanics Institute.
3.4However, significant challenges remain. These challenges relate to securing a viable re- use of the building; the high cost of restoring it to a viable use; and the aspirations of its current owner.
3.5A Mechanics Steering Group, Chaired by the Cabinet Member for Heritage, Art and Culture , with representation from the Council officers, Historic England, the Mechanics Institution Trust (MIT) and the Theatres Trust, has been considering options for securing the building’s future.
3.6The Group has re-examined the approach to securing the successful restoration of the Mechanics Institute. This review has informed a three step route map for delivering the restoration of the building. The route map addresses the following challenges:
3.6.1 Securing operationally viable and suitable new use(s) for the building;
3.6.2 The high cost of the restoration of the building; and
3.6.3 Ownership of the building.
3.7The Route Map tackles these challenges in three distinct areas as set out below. Whilst the Steps follow sequentially, it is anticipated that with appropriate resource in place these steps may be able to progress simultaneously.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.