Non-key decision Following consideration of the report, appendices and debate, the Cabinet resolved : (1) That the Wichelstowe Joint Venture 5 Year Business Plan as set out in Exempt Appendix 1 be approved. (2) That the Wichelstowe Joint Venture Phase 2 Business Plan as set out in Exempt Appendix 2 be approved. (3) That the Head of Property Assets, in consultation with the Chief Legal Officer, be authorised to amend the JV agreement plan to include Parcel 10 and an infrastructure obligation to construct the car park to serve the district centre, as identified in the plan as attached (Appendix 3), on such detailed terms and conditions as are determined by the Head of Property Assets in consultation with the Chief Legal Officer and as are considered necessary in order to protect the Council’s interests. (4) That the Head of Property Assets, in consultation with the Chief Legal Officer, be authorised to complete the transfer of the land included in the Phase 2 Business Plan, and as identified in the plan as attached (Appendix 4), to the Wichelstowe LLP (the JV) on such detailed terms and conditions, to ensure best consideration, as are determined by the Head of Property Assets in consultation with the Chief Legal Officer and as are considered necessary in order to protect the Council’s interests The reasons for the decision and alternative options are as set out in the report to the meeting .
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
2.1Approve the Wichelstowe Joint Venture 5 Year Business Plan as set out in Exempt Appendix 1
2.2Approve the Wichelstowe Joint Venture Phase 2 Business Plan as set out in Exempt Appendix 2.
2.3Authorise the Head of Property Assets, in consultation with the Chief Legal Officer, to amend the JV agreement plan to include Parcel 10 and an infrastructure obligation to construct the car park to serve the district centre, as identified in the plan as attached (Appendix 3), on such detailed terms and conditions as are determined by the Head of Property Assets in consultation with the Chief Legal Officer and as are considered necessary in order to protect the Council’s interests.
2.4Authorise the Head of Property Assets, in consultation with the Chief Legal Officer, to complete the transfer of the land included in the Phase 2 Business Plan, and as identified in the plan as attached (Appendix 4), to the Wichelstowe LLP (the JV) on such detailed terms and conditions, to ensure best consideration, as are determined by the
Further information on the subject of this report can be obtained from Rob Richards, 077400 37316, [email protected]. Wichelstowe – Five Year and Phase 2 Business Plans Cabinet Date: 12th June 2024
Head of Property Assets in consultation with the Chief Legal Officer and as are considered necessary in order to protect the Council’s interests.
3. Detail
Background
3.1Cabinet on 18th October 2017 approved the Council entering into the Wichelstowe LLP Joint Venture Agreement (“the JV Agreement”) to deliver the development of the Wichelstowe site. Accordingly the Wichelstowe LLP was incorporated in early 2018 as a Joint Venture between the Council and BDW Trading Ltd/Barratt Developments PLC (Minute .54, 2017/18 refers).
3.2The JV Agreement sets out the requirement for the JV to produce 5 year business plans setting out the approach to delivering development over the plan period as well as more detailed plans on each phase of development. The phase business plans, once approved, are the trigger for the Council transferring land to the JV so development can commence.
3.3Overall, the Wichelstowe development has been structured into 6 residential phases, which comprise a mix of land parcels. It is anticipated that the development will take a further 15 years to fully build out from now.
3.4Phase 0 comprised the first area of land transferred by the Council to the JV in 2019 and provides 208 units across 3 parcels. This phase was originally excluded from the JV Agreement as it was intended that it would be delivered by the Council’s housing company. However, the costs of development proved to be unviable so by way of a further cabinet approval this phase was transferred to the JV.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.