Resolved – 1. That the Swindon Better Care Fund Year End Review for 2023/24 was approved. 2. That the Swindon Better Care Fund Plan Update for 2024/25 was approved. 3. That the contribution of the Disabled Facilities Grant in enabling people to remain in their own homes was acknowledged. 4. Gordon Muvuti and Clare Deards to provide assurance to the Board regarding the 2023/24 year-end review challenges and successes identified in the Better Care Fund report.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Appendix 1 UEC Locality Highlight Report June 2024 Locality: Swindon Author: Charlotte Richards Current RAG Status
Key Workstreams • Demand and Capacity – ensuring the resource and capacity is available in the correct place and at the appropriate level to achieve and maintain NCTR reduction • Home First – Pathway Reset, including SwICC criteria and processes • Pathway 2 Capacity – convert from step down to full Discharge to Assess model
In month ❑ MADE Events at GWH continue and Measures Impacts Next Steps: Key Delivery ongoing actions being implemented Milestones ❑ Procurement for D2A beds completed – NCTR 30th May 2024 – From DUCTR • D2A beds in place – use of beds commenced with soft criteria Targets – 9% GWH beds : • GWH latest NCTR 14.95% occupancy recruitment to therapy pending therapy recruitment Swindon - 24 (improved position) posts to support full ❑ BCF year end return and 24/25 plan GWH - 47 • Swindon NCTR 25 function – running with submitted – good feedback received on Community Length of Stay • Average Los in SwICC beds for April was 23.5 soft acceptance first draft Targets: days. • Plans for IFD opening – SwICC – 28 days • Average LoS in D2A beds during May was 50 July 2024 In month ✓ Swindon NCTR 25 – 1 away from 9% D2A – less than 42 days days (Existing beds only, not including new • Discharge Grant Achievements/ target D2A beds) implementation plan Progress Made ✓ HomeLine review options appraisal underway Discharge Ready Date April 24 (latest data on DUCTR): ✓ Launch of D2A model underway (soft Target: TBC • 34% of eligible Admissions coded with DRD launch) • Average time between DRD and D – 2 days ✓ Discharge Grant SOP drafted – agreement of implementation required NHS@Home • Open beds 40 Targets: • Average occupancy rate was 74% for April Open Capacity – 40 In month ✓ GWH - Integrated Front Door work ongoing Occupancy – 80% Key Issues with reduction in capacity at front door and plans underway for transition in July 2024 UCR • May 24 - 82.1% ✓ High numbers of outliers in SwICC with Target: delays. Including out of area and 2-hour response rate – 70% inappropriate admissions ✓ Prospect financial position continues to be of concern ED four-hour Performance From DUCTR (National submission) – Last Target: 76% National Monthly Submission January 2024 • GWH 73.80%
Risks: Risk Number / Ref Risk Score • Current and new capacity schemes do not deliver the required NCTR reductions required – risk to be monitored through weekly planning group
• 24/25 schemes funded at risk pending ICB approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.