Resolved
Resolved To note the report.
Overview & Scrutiny Committee noted this item on Monday 11 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved To note the report.
Progress with implementation of the Infrastructure Delivery Plan is noted
1. PURPOSE
To consider progress with implementation of the Infrastructure Delivery Plan.
Teignbridge’s Infrastructure Delivery Plan (Appendix A) was updated in September 2016 to reflect projects that had been completed or had come forward during the Local Plan period between 2013 and 2033. It also outlined the most up to date position relating to identified future infrastructure requirements.
An up to date IDP is integral to informing the Council’s Capital Programme and providing the evidence needed to secure investment from external partners. The 2016 version will therefore need to be reviewed again in the next couple of years. This should either be through a stand-alone review related to the existing Teignbridge Local Plan or as part of a suite of infrastructure work for the Greater Exeter Strategic Plan (GESP). In either case, precise arrangements will need to unfold as the GESP moves forward.
This report is focussed on progress made since the Infrastructure Delivery Plan was endorsed by O&S in 2016. It summarises:
- Projects completed since September 2016; and - Notable progress and updates on outstanding projects. TEIGNBRIDGE DISTRICT COUNCIL
3. PROJECTS DELIVERED
Since September 2016 a number of infrastructure projects have been delivered, either by Teignbridge or other infrastructure providers. Each of these is summarised at Table 1 below.
Table 1: Projects delivered Sep 16 to Sep 17
Ref Project Cost Delivery Body
Buckland multi wheeled sports 1 £130,000 TDC facility Wray valley trail sections 2 between Steward’s Wood and £575,000 DCC Wray Barton Completion of Exe Estuary Trail 3 £1,000,000 DCC into Dawlish Town Centre Kingskerswell / Newton Road 4 £450,000 DCC cycle improvements Dawlish Countryside Park 5 £2,900,000 TDC SANGS 6 Cirl Bunting nature reserve land Part II RSPB Newcross, Kingsteignton school 7 £185,000 DCC land acquisition Houghton Barton Main Road 8 third party land acquisition. £344,000 TDC Unlocks 1,150 homes. Bridge Road widening, Exeter 9 £13,500,000 DCC (opening September 2017) Barton Surgery Expansion, Surgery / NHS / 10 £1,000,000 Dawlish TDC Highweek experimental traffic 11 £5,000 DCC order 12 Newton Abbot Station Car Club £25,000 Co-cars/TDC/DCC Newton Abbot community space 13 £185,000 NA Town Council building acquisition Total £20,300,000 TEIGNBRIDGE DISTRICT COUNCIL
4. NOTABLE PROGRESS AND UPDATES WITH OTHER PROJECTS
Table 2 summarises projects where a notable update to the 2016 Infrastructure Delivery plan is available or progress towards project completion has been made.
Table 2: Progress made with other projects
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Infrastructure Delivery PlanReport | 90 KB | DownloadRead as text |
PDF |
Item 11 Appendix A 2016 IDPAppendix | 193 KB | Download |
Follow Overview & Scrutiny Committee at Teignbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2020 | Election of Chair and Vice ChairRESOLVED That Councillor Bullivant be elected Chair. It was proposed by Councillor Bullivant and seconded by Councill... | Decided | Open |
| 14 Jul 2020 | Impact of Covid 19 on Council ServicesRESOLVED 1. That members note and endorse the council’s response to the Coronavirus (COVID-19) pandemic to date. 2. T... | Decided | Open |
| 14 Jul 2020 | Report of the Performance Task and Finish GroupRESOLVED 1. The performance report template as set out in Appendix 1 be used for future Overview and Scrutiny perform... | Agreed | Open |
| 14 Jul 2020 | Proposed Task and Finish Groups - Employment sites and Cultural QuarterRESOLVED Two Task and Finish groups: Making Employment Sites Work , and Delivering a Shared Vision for New Strategic ... | Decided | Open |
| 17 Sep 2019 | Election of Vice ChairmanRESOLVED - Councillor D Cox is elected Vice-Chairman of the Council for the remainder of the current municipal year. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.