Executive, Tuesday 5 December 2017 at 10.00am

Haldon Traveller Site Extension

Approved Executive 1 paper

Executive approved this item on Tuesday 5 December 2017. Below is the council's own wording, with the papers it was decided on.

Item239

Resolved

Resolved That forward funding of the three pitch extension of the Haldon Traveller site be approved in advance of receipt of the Section 106 offsite affordable housing contribution which will fund the development in full.
Word for word from the decision Teignbridge published for this meeting. Source: democracy.teignbridge.gov.uk

Follow this further

Built from Teignbridge's papers

What the report saysPro

Report to Executive

Recommendations

The Executive is recommended to approve the forward funding of the three pitch extension of the Haldon Traveller site in advance of receipt of the Section 106 offsite affordable housing contribution which will fund the development in full.

1. PURPOSE

To enable the development of three additional traveller pitches which received planning consent in April 2017. The development is to be funded by way of an offsite provision within the planning application number 13/02729/MAJ Matford Home Park, South of A379, Exeter.

Background

In December 2014 fifteen gypsy and traveller pitches where provided by Teignbridge District Council on land acquired from Devon County Council to meet an established need. The site was delivered using predominantly grant funding from the Homes and Communities Agency to meet an established need.

The site was developed using the majority but not all of the land ownership.

In October 2014 Planning Consent was granted at Matford Home Park, Matford, an element of the Local Plan allocation at South West Exeter (SWE1) The site has a planning condition to deliver three traveller pitches, either on or offsite. The Section 106 agreement was signed on 28th September 2017 with a requirement for the developer to make a contribution of £300k for the offsite delivery of the three pitches. The trigger date for this payment is commencement of the Matford Home Park development. It was considered by Officers that provision by way of an extension to the Haldon Ridge Site would TEIGNBRIDGE DISTRICT COUNCIL

the most sustainable solution bearing in mind that the current site has a growing waiting list for pitches.

Planning consent for the three pitches (17/00382/FUL) was granted in April 2017. Officers have tendered for a suitable developer and a contract is about to be issued.

Bearing in mind that works in a woodland landscape can only be conducted at restricted times of the year it is prudent for the works to commence early in the New Year, prior to the bird breeding season. This will result in the works commencing prior to the trigger date for the Section 106 planning agreement. Planning Services are of the opinion that the development is likely to commence during 2018.

3. MAIN IMPLICATIONS

The budget for this work is £300k. Expenditure so far for planning application, including ecological and geotechnical survey works total around £53,151 leaving £246,849 for the works. The lowest tender is £269,319 with work currently taking place to reduce the tender to within the budget. This work is being undertaken by Randall and Simmonds on our behalf.

Delaying the project would result in the likelihood of costs increasing and a pro rata gross rental income of £12,480 per year.

4. GROUPS CONSULTED

This matter has been discussed internally with Financial Services who are supportive of using internal funds to enable the works to be carried out and the budget subsequently refunded when the trigger date is reached.

The works would go through the Council’s capital programme. Should payment to the contractors be required before receipt of the Section 106 contribution, the scheme would be temporarily unfunded. However, as the Section 106 agreement for the funding contribution has been signed, there is reasonable assurance that it will be forthcoming. Once the funds are received, they would be applied in the usual way. In the interim, the scheme will be borrowing internally against the Council’s other balances.

If it does not prove possible to reduce the tender sum to within the contribution amount, the balance would be funded from existing housing capital receipts.

Should the s106 funds not be forthcoming the full cost of the development would be met by housing capital receipts, however this is considered very unlikely.

5. TIME-SCALE

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Haldon Traveller Site ExtensionReport 67 KB DownloadRead as text

At this meeting

Whole meeting

More from Teignbridge Executive

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesRESOLVED That the minutes of the previous meeting on Thursday 16 th July 2026 be agreed as a correct record and signe... Agreed Open
8 Sep 2026 Q1 2026/27 Budget MonitoringRESOLVED That the Executive: 1) Note the performance against the revenue and capital budgets as at the end of the fir... Noted Open
8 Sep 2026 Housing Delivery Action PlanRESOLVED That the Executive: 1) Support the appended Action Plan (Appendix 1). 2) Note the publication of the Governm... Noted Open
8 Sep 2026 Safeguarding Policy ReviewRESOLVED That the Executive: 1) Adopt the Revised Safeguarding Policy 2026 v2.0; and 2) Adopt the key performance ind... Approved Open
8 Sep 2026 Social Value PolicyRESOLVED That the Executive: 1) Adopt the at Appendix A (as amended to include the environmental measures); and 2) Au... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies