Resolved
Resolved To note the actions being taken as set out in the agenda report.
Overview & Scrutiny Committee noted this item on Monday 5 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved To note the actions being taken as set out in the agenda report.
That Members note this report and the actions taken as contained in section 3.
1. PURPOSE
To provide Members with an update on progress with the Energy Services Company (Dextco) and linked Exeter Energy Network Project.
Members will recall approving support for the formation of an Energy Services Company at Full Council in September 2016. Its main purpose being to help deliver more efficient heat and power in Devon, through sustainable energy projects which provide environmentally friendly energy to homes and businesses.
The company, Dextco, was established in December 2016 and founding members and shareholders comprise Devon County Council (DCC), Exeter City Council (ECC), Royal Devon and Exeter NHS Foundation Trust (RD&E), University of Exeter (UoE) and Teignbridge District Council (TDC).
The first project the company is backing is the Exeter Energy Network scheme which will refurbish the energy centre at the RD&E Wonford site and deliver a network to take heat from the hospital to the city centre. The core heat network itself is 6.5 km long and provides a total of 21 GWh through low temperature hot water to commercial heat users along the Heavitree corridor into the city centre. It will serve the Civic Centre and other public and private sector DH ready buildings here.
Heat networks (also called district heating or DH) and combined heat and power (CHP) enable heat generated at a central point to be distributed to a number of buildings. Co-generation uses the heat produced as a by-product of electricity generation; this heat is usually lost at large power stations. TEIGNBRIDGE DISTRICT COUNCIL
3. MAIN IMPLICATIONS
Procurement
Progress with the project has been steady on all fronts. Preparation for the procurement process is well advanced and has included comprehensive market assessment that has helped to define the broad specification, among other tasks a Market Engagement Day (including a site tour) was held at the University on 5th July 2017.
Much was learnt from the feedback from industry representatives, including valuable knowledge gained on the structure of the joint venture, the technical solution and pointers on the procurement process from an industry standpoint. There has been further soft market testing since the market engagement day and two market questionnaires have been sent out to a range of participants in the energy industry.
The project specification is designed to be outcome – driven, with the key outcomes being delivery of heat at a competitive price, resilience, return on investment to the joint venture company shareholders and potential for expansion / development.
On-going preparation of a suite of contract documents has been a major priority of the group since last autumn. These include network easements, gas purchase, electricity supply, heat connection and heat supply agreements, amongst others, which will be provided to potential bidders at the procurement launch. Dextco is also planning to undertake a route condition survey to check on utilities alignment in order to help reduce the risks in the heat network installation.
Management
Management of the project is undertaken by the Dextco Board which provides governance and direction for the project. It normally meets every four weeks, regular agenda items include a project manager’s report and review of key risks on the risk register. Teignbridge along with other partner authorities is represented at director level. A Project Group provides support to the Board and meets fortnightly, with input from procured technical, financial and legal advisors when required.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Energy CompanyReport | 68 KB | DownloadRead as text |
Follow Overview & Scrutiny Committee at Teignbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2020 | Election of Chair and Vice ChairRESOLVED That Councillor Bullivant be elected Chair. It was proposed by Councillor Bullivant and seconded by Councill... | Decided | Open |
| 14 Jul 2020 | Impact of Covid 19 on Council ServicesRESOLVED 1. That members note and endorse the council’s response to the Coronavirus (COVID-19) pandemic to date. 2. T... | Decided | Open |
| 14 Jul 2020 | Report of the Performance Task and Finish GroupRESOLVED 1. The performance report template as set out in Appendix 1 be used for future Overview and Scrutiny perform... | Agreed | Open |
| 14 Jul 2020 | Proposed Task and Finish Groups - Employment sites and Cultural QuarterRESOLVED Two Task and Finish groups: Making Employment Sites Work , and Delivering a Shared Vision for New Strategic ... | Decided | Open |
| 17 Sep 2019 | Election of Vice ChairmanRESOLVED - Councillor D Cox is elected Vice-Chairman of the Council for the remainder of the current municipal year. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.