Resolved
Resolved – The report and circulated appendices be noted.
Devon Building Control Partnership Committee noted this item on Friday 27 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – The report and circulated appendices be noted.
The Devon Building Control Partnership Committee is asked to note the report and the attached Appendices
1. PURPOSE
To provide an update on the financial performance of the Devon Building Control Partnership.
The Partnership operates under the Devon Building Control Partnership Agreement 2017.
The Agreement states that the Committee shall meet a minimum of three times a year and that one of those meetings shall be the Annual General Meeting, at which the Chair and Vice Chair will be determined for the forthcoming year.
3. MAIN IMPLICATIONS
The Partnership has completed fourteen years in operation and has been hosted by Teignbridge District Council since April 2011 and who has employed all staff in the Partnership since April 2017.
The Partnership continues to successfully deliver the building control service across the three Authorities, maintaining high standards, meeting PIs and continues to operate within agreed annual budgets.
2017/18 was the first year under the new agreement, under which Teignbridge council became the full host to the partnership, employing all staff and supplying all support services. The main objectives of the agreement were achieved which included the TUPE transfer of staff, elimination of duplicated support services and resulting reduced costs to all partners. Simplification and efficiency of financial information was also achieved.
Staff
During the year three surveyors all reduced their hours, resulting in a saving in costs and a better work/life balance for those involved. The workload has been managed by sharing across the teams efficiently with no reduction in overall service levels.
The Committee agreed to fund an Apprentice surveyor from Partnership reserves. A successful appointment was made in September 2017 and the person involved has made excellent progress and confidence is high that he has the potential to continue and develop into a very good surveyor.
The Committee also recommended funding for a temporary post in the Technical Support team to enable it to continue managing high demands whilst focussing on marketing, online applications and inspection requests via the new website. There is currently someone fulfilling this post on a part time basis, without which the team would not have achieved all of this.
Following the ‘One Teignbridge’ project, in which the partnership is reviewed early in 2019 it is hoped some of the demands on the team can be reduced.
Expansion
It was reported earlier this year that an SLA with Torbay council was unable to be agreed.
Legal
The 2017 Partnership Agreement requires that the Partnership Committee will meet for a minimum of 3 times a year:
At the Annual General Meeting the Partnership Committee shall; agree the Partnership’s draft final accounts, and agree the balance to be held in the Trading Account. reassess the values and objectives of the Partnership and monitor service delivery and financial performance. from among their members elect a Chairman and Vice-Chairman
Risk Analysis
Risks to the Partnership’s business are documented and reviewed annually.
4. GROUPS CONSULTED
South Hams District Council, Teignbridge District Council and West Devon Borough Council. 5. TIME-SCALE
The information covers the period from 1 April 2017 to 31 March 2018.
6. JUSTIFICATION
The meeting is required in accordance with the Partnership Agreement. Building Control Partnership
Andrew Carpenter Head of Devon Building Control Partnership
Wards affected All Contact for any more information Andrew Carpenter 01626 215721
Background Papers (For Part I reports only) Key Decision In Forward Plan In O&S Work Programme Community Impact Assessment attached: Appendices attached:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual ReportReport | 3 pages | DownloadRead as text |
Follow Devon Building Control Partnership Committee at Teignbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2024 | Appointment of representativesIt was agreed that the standing orders would be circulated to committee members in order to consider additional amend... | Agreed | Open |
| 25 Mar 2024 | Administration of the PartnershipIt was agreed that a working group would be created comprising one member and one officer from each council in the pa... | Agreed | Open |
| 25 Mar 2024 | Part 1 Operational Report Q2 and Q3 2023-24Resolved That that Part 1 Operational Report be noted by the Committee. | Noted | Open |
| 22 Sep 2023 | Election of ChairResolved That Councillor Southcott be appointed Chair of Devon Building Control Partnership Committee 2023-2024. | Decided | Open |
| 22 Sep 2023 | Election of Vice-ChairResolved That Councillor Taylor be appointed Vice-Chair of Devon Building Control Partnership Committee 2023-2024. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.