1. PURPOSE
1.1To inform Members of the number of times the Financial Instructions and Contract Procedure Rules have been waived and the reasons for this.
2.1The Financial Instructions and Contract Procedure Rules provide the framework for managing the Council’s financial affairs. They apply to every member and officer of the Council and anyone acting on its behalf.
2.2Sometimes there are instances where the rules cannot be followed and requests are made to waive them. One of the following criteria must be met:
1 LIFE OR DEATH There is significant chance that the life or health of officers, members, or the public will be put at real risk.
2 INCREASED COST / LOSS OF INCOME The Council will incur significant avoidable costs or lose significant income.
3 LIMITED MARKETS The Council would be wasting its time tendering as supply of the product or service is demonstrably restricted to one or few businesses.
4 URGENT ACTION REQUIRED The Council would be criticised for failing to act promptly. TEIGNBRIDGE DISTRICT COUNCIL
3. WAIVERS
3.1The following waivers have been processed since the December 2018 monitoring report:
Proposing Proposal / Reason Approval Officer Richard Rainbow Temporary Project Management Support Tony Watson To extend the current temporary project Drainage and management being provided for the South Interim Head of Coastal Manager West Coastal Monitoring Programme at 2 days Commercial Services per week.
Value: £4,900 (fully recoverable from Environment Agency grant)
Reason: Limited Markets
Neil Blaney Greater Exeter cluster economy Tony Watson Purchase of a report and one year access to Economy data to bring the Shared (East Devon, Exeter, Interim Head of Manager Mid Devon and TDC) Economic Strategy in Commercial Services line with national and local productivity focus. It will provide new evidence to better understand the economic sectors at the Greater Exeter geography level.
Value: £3,750 paid by each of the four Councils (total £15,000)
Reason: Limited Markets
Daron Hand Photo-voltaic Panels Tony Watson Installation of phot-voltaic panels for the Group Building Teignbridge Business Centre, Heathfield. Interim Head of Surveyor Commercial Services Value: £25,384
Reason: Increased Cost / Loss of Income and Urgent Action Required
Richard Rainbow South West Strategic Coastal Monitoring Tony Watson Programme Drainage and Purchase of replacement of Datawell Interim Head of Coastal Manager Waverider buoy to replace the damaged and Commercial Services uneconomic to repair Minehead Waverider buoy.
Value: £43,000 (fully recoverable from Environment Agency funding)
Reason: Limited Markets TEIGNBRIDGE DISTRICT COUNCIL
Alison Dolley Local House Condition Stock Modelling Amanda Pujol To meet Housing Act requirements to review Private Sector housing conditions to identify actions needed Interim Head of Service Housing Team and enable resources and works to be Delivery and Leader targeted. Improvement
Value: £39,950 (over three years)
Reason: Limited Markets
Richard Rainbow South West Strategic Coastal Monitoring Tony Watson Programme Drainage and Purchase of spares for hydrodynamic buoys to Interim Head of Coastal Manager enable regular maintenance works to be Commercial Services carried out.
Value: £46,186.15 (fully recoverable from Environment Agency funding)
Reason: Limited Markets
That the report be noted.
Sue Heath Audit Manager Wards affected - Contact for any more information Sue Heath – Audit Manager – 01626 215258 Background Papers (For Part I reports only) Financial Instructions Waivers File – Internal Audit Key Decision - In Forward Plan - In O & S Work Programme -
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Instructions and Contract Rules Waivers ReportReport | 3 pages | DownloadRead as text |
Follow Audit Committee at Teignbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Minutes of the previous meetingRESOLVED That the minutes of the previous meeting be agreed as a correct record and signed by the Chair. | Agreed | Open |
| 29 Jun 2026 | Draft Annual Governance StatementRESOLVED That the is approved by the Committee for inclusion in the Annual Statement of Accounts. | Approved | Open |
| 25 Mar 2026 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting on Monday 10 th February 2026 be agreed as a correct record and sig... | Agreed | Open |
| 25 Mar 2026 | Strategic & Corporate Risk ReportRESOLVED To note the actions being taken to reduce risks to the achievement of the Council’s objectives. | Noted | Open |
| 25 Mar 2026 | Audit Committee Annual ReportRESOLVED The Committee approved the report and recommended to Full Council its adoption. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.