Local Plan Timetable - Local Development Scheme

Agreed Executive 1 paper

AI summaryTeignbridge Executive agrees to start work on a new Local Plan for 2029 to 2044, approves a £105,000 budget for 2026/27, and sets a timetable with statutory milestones in June and October 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedStart work on Teignbridge Local Plan 2029 to 2044
Money£105,000Budget for year one, 2026/27, from reserves or in-year savings
What happens nextFormal notice by 30 June 2026Gateway 1 milestone due by 31 October 2026
Who it affectsTeignbridge districtExcludes areas within Dartmoor National Park

What was decided

The Executive approved the start of work on the Teignbridge Local Plan 2029 to 2044, with priority given to addressing the housing shortfall caused by the updated standard method. Report P6, 2.1

Members agreed the Local Development Scheme set out in Appendix 1, to take effect on 20 March 2026. Report P6, P47

The Executive approved £105,000 for 2026/27 and agreed to reconvene the Local Plan Working Group under the terms of reference in Appendix 2. Report P6, 2.9

Why

The adopted Local Plan 2020 to 2040 set a requirement of 720 homes per year, while the new standard method indicates 1,088 per year, meaning the Council is legally required to start a new plan and give formal notice by 30 June 2026. Report 2.1, 2.11

The Levelling-Up and Regeneration Act 2023 and updated standard method calculations created a housing shortfall that must be addressed under transitional arrangements. Report 2.1, 2.10

Failure to meet the statutory milestones risks Government intervention, loss of local control over plan-making, and a higher chance of examination failure. Report 2.11

What happens next

Prepare and publish the Local Plan timetable in March 2026, issue formal notice and run a scoping consultation by June 2026, and complete the Gateway 1 stage by 31 October 2026. Report P21, P55

Present a progress review to the Executive at the end of 2026, covering any extra budget needed for 2027/28.

Bring a Consultation and Engagement Strategy to the Executive alongside the scoping consultation in June 2026. Report 2.6

The money

  • £105,000 Indicative additional budget required for 2026/27 Report P57
  • £260,000 Indicative additional budget required for 2027/28 Report P57
  • £240,000 Indicative additional budget required for 2028/29 Report P57
  • £20,000 Economic Development Needs Assessment cost (2026/27) Report P57
  • £30,000 Playing Pitch Strategy cost (2026/27, underway) Report P57
  • £10,000 Environmental assessments cost (2026/27) Report P57
  • £30,000 Land Availability Assessment cost (2026/27) Report P57
  • £40,000 Housing Needs Assessment for housing requirements (2026/27) Report P57
  • £30,000 Housing Needs Assessment for housing types (2026/27) Report P57
  • £30,000 Review of landscape designations and sensitive landscapes (2026/27) Report P57
  • £35,000 Staff resource cost for each year 2026/27 to 2028/29 Report P57
  • £100,000 Examination cost Report P57
  • -£30,000 Base budget reduction in each year 2026/27 to 2028/29 Report P57
  • c. £35,000 per year Indicative cost of an additional Apprentice or Graduate Planner Report 2.5

Options considered

  • Chosen: Commence work on the Teignbridge Local Plan 2029 to 2044 now. Statutory deadlines require formal notice by 30 June 2026 and Gateway 1 by 31 October 2026 Report 2.1, 2.11
  • Rejected: Delay commencement of the new Local Plan. Not legally compliant; risks Government intervention and examination failure Report P41
  • Rejected: Prepare a more limited plan with reduced scope. Risks being found unsound or failing statutory Gateway 1 and Gateway 3 requirements Report P41
  • Rejected: Rely on neighbouring authorities or seek a joint plan. Neighbouring authorities have different timelines and limited appetite; joint governance would take too long Report P42
  • Rejected: Rely on future Local Government Reorganisation to produce a new plan. Would fail legal requirements for notice and Gateway 1 and could leave Teignbridge without an up-to-date strategy during transition Report P42

Implications

  • Legal: Preparing and updating local plans is a statutory requirement under the Levelling-Up and Regeneration Act 2023 and Section 15 of the Planning and Compulsory Purchase Act. Report 2.10
  • Financial: MHCLG invited bids for financial support; an application was submitted in January 2026 with an outcome expected by the end of March 2026. Some GESP funds remain for joint evidence work. Report 2.9
  • Risk: Failure to meet statutory milestones risks Government intervention, loss of local control over plan-making, and later examination failure. Report 2.11
  • Staffing: Current capacity is 2.8 FTE planning policy specialists and 0.6 FTE data and engagement support; an additional Apprentice or Graduate Planner is recommended to meet the demanding timetable. Report 2.5
  • Climate: No direct environmental or climate change impacts arise from this report, but the Local Plan itself will be assessed through Strategic Environmental Assessment and Habitats Regulations Assessment. Report 2.12

Who and where

  • Residents and communities across Teignbridge district (excluding Dartmoor National Park) Report 2.1
  • Neighbouring authorities, including Torbay, which has asked Teignbridge to consider accommodating unmet housing need Report 2.8
  • Developers and site promoters operating in the district Report 2.4
  • Planning policy team and wider Council officers Report 2.5
  • The Executive Member for Planning and other members of the reconvened Local Plan Working Group Report P13, P58

Timeline

  • March 2026: Prepare and publish Local Plan timetable (LDS) Report P21, P55
  • 20 March 2026: Local Development Scheme comes into force Report P47
  • May 2026: Full Council expected to adopt the Local Plan 2020 to 2040 Report 2.1
  • June 2026: Formal notice of preparation and scoping consultation Report P21, P55
  • October 2026: Gateway 1: completion of initial scoping consultation and baseline evidence Report P21, P55
  • November 2026: Gateway 2: completion of draft plan consultation Report P21, P55
  • October 2028: Gateway 3: completion of final plan consultation and submission Report P21, P55
  • November 2028: Examination starts Report P22, P56
  • November 2028 to April 2029: Examination period Report P22, P56
  • May to December 2029: Adoption, with timeframe for modifications consultation Report P23, P56
  • End of 2026 calendar year: Progress review report to Executive, including any 2027/28 budget needs

Plain English for the jargon

  • Local Development Scheme (LDS): A document required under Section 15 of the Planning and Compulsory Purchase Act that sets out which plans a local planning authority will prepare, their scope and timetable.
  • Gateway 1, 2, 3: Statutory milestone stages under the Levelling-Up and Regeneration Act 2023 that a new Local Plan must pass during preparation.
  • Standard method: The national formula for calculating a local planning authority's local housing need.
  • NPPF: National Planning Policy Framework, the Government's planning policy framework for England.
  • MHCLG: Ministry of Housing, Communities and Local Government.
  • LGR: Local Government Reorganisation, the planned restructuring of local authorities in England.
  • GESP: Greater Exeter Strategic Plan, a joint planning project between Exeter, East Devon, Teignbridge and other partners.
  • FTE: Full Time Equivalent, a unit measuring staff capacity.
  • Sounding board: An informal advisory group, in this case the Local Plan Working Group, that gives advice but has no decision-making power.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

RESOLVED That the Executive: 1. Commence preparation of the Teignbridge Local Plan 2029–2044, prioritising actions to address the shortfall in housing provision created by the updated standard method calculations. 2. Agree the Local Development Scheme as set out in Appendix 1 to come into effect on 20 March 2026. 3. Agree a budget of £105,000 for year one of the project (2026/27). 4. Reconvene the Local Plan Working Group as per the Terms of Reference set out in Appendix 2.
Word for word from the decision Teignbridge published for this meeting. Source: democracy.teignbridge.gov.uk

Follow this further

Built from Teignbridge's papers

What the report saysPro

Report to Executive

Teignbridge District Council Executive 10 March 2026 Part i

Teignbridge Local Plan 2029-2044

Purpose of Report To seek approval to commence work on a new Local Plan for Teignbridge and agree a timetable and budget for the project.

Recommendation(s)

The Committee RESOLVES to:

1. Commence preparation of the Teignbridge Local Plan 2029–2044, prioritising actions to address the shortfall in housing provision created by the updated standard method calculations. 2. Agree the Local Development Scheme as set out in Appendix 1 to come into effect on 20 March 2026. 3. Agree a budget of £105,000 for year one of the project (2026/27) 4. Reconvene the Local Plan Working Group as per the Terms of Reference set out in Appendix 2.

Financial Implications These are as set out in section 2.9. Gordon Bryant Head of Finance Email: [email protected]

Legal Implications These are as set out in section 2.10. Charlie Fisher, Democratic Services Manager Email: [email protected]

Risk Assessment These are as set out in section 2.11. Michelle Luscombe Head of Strategy and Partnerships Tel: 01626 215754 Email: [email protected]

Environmental/ Climate Change Implications These are as set out in section 2.12. Michelle Luscombe Head of Strategy and Partnerships

Executive 10 March 2026 Tel: 01626 215754 Email: [email protected]

Report Author Michelle Luscombe Head of Strategy and Partnerships Tel: 01626 215706 Email: [email protected]

Executive Member Executive Member for Planning (Cllr Gary Taylor)

Appendices 1. Local Development Scheme – March 2026 2. Local Plan Evidence Base 3. Local Plan Working Group Terms of Reference

Executive 10 March 2026 1. PURPOSE 1.1. The purpose of this report is to obtain approval to commence work on a new Local Plan for Teignbridge and agree a timetable and budget for the project.

2. REPORT DETAIL

2.1Overview 2.1.1 The Teignbridge Local Plan 2020–2040 is currently undergoing examination, and the Inspector’s Final Report is expected imminently. Upon receipt of the Report, the Plan will be presented to Full Council with a recommendation for adoption, which is anticipated to take place at the Full Council meeting in May 2026. Once adopted, the Plan will form the principal basis for determining development proposals within the district (excluding areas within the Dartmoor National Park). 2.1.2 During the latter stages of preparing the Local Plan 2020-2040, the Government introduced significant reforms to the planning system through the Levelling-Up and Regeneration Act 2023. Although we were able to progress the Plan under the transitional arrangements, these arrangements also require the Council to undertake an immediate review of the Plan following its adoption. 2.1.3 These arrangements apply to local planning authorities whose adopted housing requirement is less than 80% of the requirement calculated using the new national standard method. The Local Plan 2020–2040 includes a requirement of 720 homes per year, whereas the new standard method indicates a requirement of 1,088 homes per year. As a result, the Council is legally required to begin work on a new Local Plan, to give formal notice of this by 30 June 2026, and to pass the newly introduced ‘Gateway 1’ stage by 31 October 2026, notwithstanding that the current Plan has not yet been adopted. 2.1.4 This report provides a proposed approach and timetable to ensure compliance with these statutory milestones and with the requirements of the new planning system.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Plan Timetable: Local Development SchemeReport 280 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
RB
Councillor Richard BuscombeCommittee Member, present
JH
Councillor Jackie HookCommittee Member, present
RK
Councillor Richard KeelingChair, present
CN
Councillor Charles NuttallCommittee Member, present
JN
Councillor John NutleyCommittee Member, present
DP
Councillor David PalethorpeDeputy Leader, present
JP
Councillor John ParrottCommittee Member, present
GT
Councillor Gary TaylorCommittee Member, present
PW
Councillor Peter WilliamsCommittee Member, present
CF
Charlie FisherOfficer, expected
PS
Phil ShearsOfficer, expected
PB
Councillor Phil BullivantGuest, in attendance

All 15 on the meeting page

On this subject at Teignbridge

Search all
  1. Local Plan Timetable - Local Development SchemeThis decision
  2. Adoption of the Local Plan 2020-2040Noted
  3. Local Plan AddendumApproved
  4. Teignbridge Proposed Submission Local Plan 2020 to 2040Approved
  5. Local Plan Consultation – Renewable Energy Site options, Gypsy and Traveller site options and residential sites optionsDecided
  6. Notice of Motion - Giving the Community a stronger voice in local planningDecided

More from Teignbridge Executive

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesRESOLVED That the minutes of the previous meeting on Thursday 16 th July 2026 be agreed as a correct record and signe... Agreed Open
8 Sep 2026 Q1 2026/27 Budget MonitoringRESOLVED That the Executive: 1) Note the performance against the revenue and capital budgets as at the end of the fir... Noted Open
8 Sep 2026 Housing Delivery Action PlanRESOLVED That the Executive: 1) Support the appended Action Plan (Appendix 1). 2) Note the publication of the Governm... Noted Open
8 Sep 2026 Safeguarding Policy ReviewRESOLVED That the Executive: 1) Adopt the Revised Safeguarding Policy 2026 v2.0; and 2) Adopt the key performance ind... Approved Open
8 Sep 2026 Social Value PolicyRESOLVED That the Executive: 1) Adopt the at Appendix A (as amended to include the environmental measures); and 2) Au... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies