AI summaryTeignbridge Full Council approved the budget and delegated authority to refurbish Dawlish Leisure Centre, with up to £3 million of CIL funding and £1.223 million of borrowing. Construction is forecast to take 10 months.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedBudget approved, authority delegated to Director of Customer and Transformation
MoneyUp to £3 million CIL, £1.223 million borrowingCIL allocation plus internal borrowing for refurbishment
What happens nextRIBA stages 3 and 4, then procurementDesign, then approximately 8 month procurement, then 10 month build
Who it affectsNot stated
What was decided
Full Council approved the project budget and enabled the programme of works to deliver the refurbishment of Dawlish Leisure Centre.
Authority was delegated to the Director of Customer and Transformation to ensure delivery in line with the report, Council policy and approved budget.
Why
The refurbishment fulfils the One Teignbridge strategy priority IN.8 to improve leisure centres and is intended to raise participation and reduce operating costs. Report P21, P42, P66
The current facility is dated, has limited offer, no exercise studios, and a pool that opened in 1974. Local health data shows Teignbridge adults are more inactive than regional and national averages. Report P29, P37, P23
Allocating up to £3 million of CIL is considered financially prudent, leaving an estimated £6.51 million of CIL available after existing planned commitments. Report P44, P45
What happens next
The project will move through RIBA stages 3 and 4, followed by procurement and main contractor award over about 8 months, with construction forecast to take 10 months. Report P41
A pre-planning application will be submitted and the dual-use partner, Dawlish Community College, will be formally notified of the works programme. Report P59, 2.5
During construction the pool and all-weather pitch will be kept operating, while sports hall users are offered Broadmeadow and Newton Abbot alternatives. Report P41
The money
£23.49 million Current CIL cash balance held by the Council Report P44
£11.58 million Forecast CIL income over the next five years Report P44
£35.07 million Anticipated total CIL resource Report P44
£28.56 million Existing planned infrastructure CIL commitments Report P44
£6.51 million Estimated CIL balance remaining available Report P44
£3 million Maximum CIL funding allocated to the Dawlish refurbishment Report P45
£1.223 million Borrowing required for the project, initially met by internal borrowing
£1.2 million Original 2018 refurbishment cost estimate Report P49
£1 million Planned maintenance spend over the next five years Report P50
Options considered
Chosen: Refurbish the leisure centre as proposed. Fulfils strategy priority IN.8, forecast to improve revenue position, meet return on investment, and serve growing population Report P42, P66
Rejected: Continue as is. Facility remains dated, operates at a deficit, with around £1 million of repairs and maintenance likely needed, and works would only become more expensive
Rejected: Close the site. Leisure is non-statutory so closure is possible, but the council plays a critical role in providing this community facility and the private sector is not meeting demand Report 4.2
Implications
Financial: Project is affordable within the capital financing framework and forecast to improve the centre's revenue position under all three membership growth scenarios, with yields of 31.04%, 42.87% and 50.76%. Report P47
Legal: The Council has power to act under the Localism Act 2011, including the General Power of Competence, and the Local Government Act 1972, with possible Planning Act 1990 and Procurement Act 2023 duties. Report 3.2, P55
Climate: Refurbishment will replace ventilation, install LED sports hall lighting, refurbish the existing solar PV system, and add air-to-air heat pumps, reducing energy use and lifecycle carbon. Report 3.4, P61, P62
Risk: A principal risk is that the project is lost during pending local government reorganisation, with rising costs if delayed. Some revenue loss is expected during construction. Report 3.3, P57, P46
Equalities: Public sector leisure supports concessionary rates, inclusive programmes, and targeted interventions for vulnerable and disabled residents, helping to address health inequalities. Report P20, P58
Who and where
Existing users of Dawlish Leisure Centre, including pool, gym, sports hall and all-weather pitch users Report P37
Dawlish Community College, the dual-use partner for the sports hall Report P37, 2.5
Local schools and swimming clubs needing pool access for the curriculum Report P20
Future residents of planned housing including the North-West Urban Extensions (DA2) of 860 homes Report P48
Teignbridge residents as a whole, particularly the inactive adult and child populations Report P23, P29, P34
Timeline
1974: Dawlish swimming pool opened Report P37
1994: Sports hall added to the site Report P37
2012: Fitness gym added, replacing the former cafe Report P37
2015: Solar PV system installed Report P40
2018: Original refurbishment proposals drawn up, with cost estimated at £1.2 million Report P49
July 2025: Broadmeadow sports centre refurbishment reopened as a comparable completed scheme Report P19, P42
January 2026: Dawlish Community College informed of potential works programme Report 2.5
2026-07-28: Full Council decision to approve the project budget and delegate authority
Approximately 8 months after RIBA 3 and 4: Procurement process and main contractor award Report P41
10 month construction period: Forecast build programme following contractor appointment Report P41
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge developers pay to local councils to fund infrastructure
RIBA stages: Stages of the Royal Institute of British Architects' plan of work covering design, development and construction
Dual-use agreement: Arrangement where a school and the public share use of the same sports facilities
Feed in Tariff: A government scheme paying owners of solar or other low carbon generation for the electricity they produce
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26
Resolved
RESOLVED That Full Council: 1. Approve the project budget and enable the programme of works to progress and deliver the refurbishment of Dawlish Leisure Centre. 2. Delegate authority to the Director of Customer and Transformation to ensure delivery of the project in accordance with this report, Council policy and approved budget.
Word for word from the decision Teignbridge published for this meeting.Source: democracy.teignbridge.gov.uk
Title of person giving advice: Head of Financial Services and Audit Email: [email protected]
Legal implications
Legal services will continue to support the project to ensure that all necessary statutory powers, approvals, contractual arrangements, and governance requirements are appropriately addressed prior to commencement of works.
Further comments in section 3.2
Title of person giving advice: Interim Head of Legal Email: [email protected]
Risk Assessment
Risks are noted in section 3.3 of the report.
Title of person giving advice: Head of Leisure Email: [email protected]
Environmental / Climate Change Implications Environmental implications are discussed in Section 3.4 and outline the project benefits in terms of operational energy use and how the specification and efficient use of materials will act to reduce lifecycle carbon emissions.
Title of person giving advice: Climate Projects Officer Email: [email protected]
Cllr John Nutley Executive Member for Leisure, Recreation, Resorts and Tourism.
Cllr David Palethorpe Deputy Leader & Executive Member for Economy, Estates and Major Projects.
Appendices / Background Papers
Appendix 1 – Outline of the current layout. Appendix 2 – Outline proposal for the refurbishment. Appendix 3 – Leisure Needs Assessment (2024), attached as a separate document. Appendix 4 – Equality Impact Assessment.
1. Introduction
The refurbishment of Dawlish leisure centre featured in the previous Council Strategy (Teignbridge Ten) when the original refurbishment proposals for Broadmeadow sports centre and Dawlish centre were brought forward in 2018. Both projects were delayed through the covid period. Following a return to business post- covid, the leisure services were focused on recovering the level of business activity. Subsequently, as that was achieved, the Broadmeadow refurbishment project was brought forward and successfully completed, reopening in July 2025. The Dawlish refurbishment proposal is now presented for the Council’s consideration.
Unlike private commercial gyms, public sector leisure facilities exist for civic benefit rather than pure profit, offering concessionary rates, inclusive programs, and targeted interventions for vulnerable or disabled individuals. Providing accessible, affordable physical activity options contributes to the reduction of chronic health conditions and combats social isolation. Local schools depend heavily on public sector pools to meet statutory curriculum requirements for swimming, which is especially critical in areas surrounded by the sea and local rivers.
The ‘One Teignbridge’ council strategy community consultation evidenced strong support for leisure. Accordingly, the strategy confirmed the Council’s intention to provide the leisure facility infrastructure to support community health and wellbeing across the district. A priority project was agreed (IN.8) to facilitate improvements to our leisure centres, and a key action was confirmed as the refurbishment of Dawlish leisure centre, presenting the opportunity to improve participation levels and reduce operating costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.