CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Teignbridge District Council
Overview and Scrutiny Committee, Tuesday 15 September 2026 at 10.00am

Budget Monitoring 2026/27 Q1

Decided Scrutiny 1 paper

AI summaryTeignbridge Overview and Scrutiny Committee received the Q1 2026/27 budget monitoring report, which forecasts a £0.275m revenue surplus and £33.1m capital outturn. The capital programme was reprofiled to £33.6m after adding the Dawlish Leisure Centre scheme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee noted Q1 financial position
Money£0.275m revenue surplusForecast against approved base budget at Q1
What happens nextQ2 monitoring reportMaterial changes to be reported at Q2
Who it affectsAll wardsCouncil-wide revenue and capital budgets

What was decided

The committee resolved that the Q1 2026/27 budget monitoring report be received. Report P3

Members were asked to review performance against the revenue and capital budgets at the end of the first quarter. Report P3

Why

The report sets out the council's financial performance against the approved 2026/27 budget, highlights emerging budget pressures, and supports financial oversight and decision-making. Report P5, P62

Regular monitoring by members helps ensure the council meets its statutory obligation to secure a balanced budget. Report P63, P64

What happens next

Any material changes to the Q1 forecasts, or further variances identified, will be reported through the Q2 budget monitoring process. Report P4

The forecast Q1 underspend of £0.275m is credited to the General Fund Reserve, pending consideration by members as part of the council's future financial planning and reserves strategy. Report P25

The money

  • £0.275m Forecast revenue surplus against approved base budget at Q1 Report P9, P20
  • £23.5m Original approved capital programme for 2026/27 Report P28
  • £33.6m Reprofiled capital budget after Dawlish Leisure Centre addition Report P28, P29
  • £2.8m Capital expenditure to end of Q1, 12.1% of original budget Report P28, P29
  • £33.1m Forecast capital outturn for 2026/27 Report P28, P29
  • £1.47m Forecast total investment income for 2026/27, £0.275m above budget Report P38
  • £0.793m Crisis and Resilience Fund received after budget approval Report P19
  • £56.537m Usable reserves brought forward at 1 April 2026 Report P25

Options considered

  • Chosen: Receive the Q1 budget monitoring report. Report is for noting rather than formal resolution Report P58

Implications

  • Financial: Waste, Recycling and Cleansing is forecasting a £0.111m overspend because a £0.195m food waste grant is no longer expected. Report P17
  • Financial: Financing items show a £0.344m overspend, mainly because £0.581m of vacancy savings sit within individual service budgets rather than centrally. Report P17
  • Financial: Investment income is forecast to be £0.275m above budget due to higher-than-expected interest rates. Report P38
  • Risk: Coastal resilience pressures are flagged, with continued close observation of the Coastal Resilience Reserve during the long hot summer. Report P46
  • Risk: The budget assumes a 3% pay award; no national agreement is in place and any rise above 3% would add pressure. Report P49
  • Legal: Regular monitoring helps the council meet its statutory duty to secure a balanced budget and provide certain services. Report P63
  • Equalities: No service delivery changes are proposed, so no Equalities Impact Assessment is required. Report P65
  • Climate: The budget contains sufficient resource to fund the Climate Change Officer, with many projects supporting the transition to net zero. Report P66

Who and where

  • All wards across Teignbridge Report P2
  • Council services with material Q1 variances, including Development Management, Economy and Assets, Parking, Leisure, and Waste, Recycling and Cleansing Report P16, P17
  • Residents receiving services funded from the revenue and capital budgets Report P60
  • Eligible residents supported by the Crisis and Resilience Fund Report P19

Timeline

  • 26 February 2026: Original capital programme of £23.5m approved by Full Council Report P28
  • 1 April 2026: Start of 2026/27 financial year Report P25
  • 30 June 2026: End of Q1; position reported Report P4, P35, P38
  • 28 July 2026: Dawlish Leisure Centre improvement scheme approved by Full Council Report P28
  • 17 September 2026: Next Bank of England base rate decision Report P35
  • 31 March 2027: Forecast year end and forecast closing reserves balance of £43.301m Report P25

Plain English for the jargon

  • CIPFA: Chartered Institute of Public Finance and Accountancy
  • CIL: Community Infrastructure Levy
  • MRP: Minimum Revenue Provision
  • DBCP: Devon Building Control Partnership, hosted by Teignbridge
  • LGR: Local Government Reorganisation
  • CFR: Capital Financing Requirement
  • DMO: Debt Management Office Deposit Facility
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

RESOLVED The report be received.
Word for word from the decision Teignbridge published for this meeting. Source: democracy.teignbridge.gov.uk

Follow this further

Built from Teignbridge's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Teignbridge District Council Overview and Scrutiny Committee 15th September 2026

Budget Monitoring Report – Quarter 1 Executive Cllr John Parrott Member(s): Service Area: Financial Services and Audit Report author(s) Gordon Bryant and contact details: Head of Financial Services and Audit Ward(s) affected: All Wards Access to Part I (public) information and confidentiality: For Executive only Key decision? N/A

Included in Forward N/A Plan? Recommendations The Committee: (1) Review the performance against the revenue and capital budgets as at the end of the first quarter of the financial year.

1. Executive Summary This report provides a summary of Teignbridge District Council’s forecast revenue and capital year-end financial positions as at the end of June 2026, representing Quarter 1 of the financial year. Forecasts to year end have been prepared using the latest information available at this stage. Any material changes to these forecasts, or further budget variances identified, will be reported through the Quarter 2 budget monitoring process.

2. Purpose of Report and key information This report sets out Teignbridge District Council’s financial performance against the approved budget for the first quarter of the 2026/27 financial year. It provides Members with an overview of the Council’s current revenue and capital position, highlights any emerging budget pressures or variances, and supports effective financial oversight and decision-making. 2.1 Revenue Forecast At the end of Quarter 1, as shown in table 1, the 2026/27 revenue outturn is forecast to be a £0.275m surplus against the approved base budget split between a

Overview and Scrutiny 15th September 2026 favourable expenditure variance of £0.303m offset by an adverse funding variance of £0.028m.

Table 1 - Revenue Budget Monitoring 2026/27 Summary – Quarter 1 Forecast Variance Variance Services* Budget £m £m £m (%) Corporate Services 6.095 6.076 (0.019) 0% Strategic Place 2.602 1.958 (0.644) -25% Environment, Health & Wellbeing 11.575 11.591 0.016 0% Total all services 20.272 19.625 (0.647) -3% Financing Items 0.256 0.600 0.344 135% Total Revenue Expenditure 20.528 20.225 (0.303) -1%

Revenue Funding & Reserves** Reserves 0.451 0.451 0.000 0% Funding (20.979) (20.951) 0.028 0% Total Funding & Reserves (20.528) (20.500) 0.028 0%

Forecast Outturn 0.000 (0.275) (0.275) * See table 2 ** See table 3

Tables 2 & 3 below expand on the financial position across all services, the use of reserves, and funding, with commentary provided for material budget variances.

Overview and Scrutiny Committee 15th September 2026 Table 2 - Service Budget Monitoring 2026/27 – Quarter 1 Forecast Variance Variance Corporate Services Budget £m £m £m (%) Business Transformation Team 0.753 0.753 0.000 0% Communications 0.445 0.446 0.001 0% Democratic Services 0.915 0.920 0.005 1% Electoral Services 0.229 0.230 0.001 0% Finance 1.387 1.345 (0.042) -3% Human Resources 0.749 0.760 0.011 1% Internal Audit & Information Governance 0.282 0.282 0.000 0% Legal 0.785 0.787 0.002 0% Procurement 0.044 0.046 0.002 4% Corporate Leadership Team 0.506 0.507 0.001 0% 6.095 6.076 (0.019) 0% Strategic Place Building Control (0.405) (0.405) 0.000 0% Customer Services 0.969 0.887 (0.082) -9% Development Management 0.941 0.825 (0.116) -12% Economy & Assets 0.619 0.429 (0.190) -31% Housing 2.177 2.097 (0.080) -4% Parking (4.066) (4.163) (0.097) 2% Revenues & Benefits 1.572 1.496 (0.076) -5% Spatial Planning 0.795 0.792 (0.003) 0% 2.602 1.958 (0.644) -25% Environment, Health & Wellbeing Community Safety 0.153 0.149 (0.004) -3% Environmental Health 1.464 1.455 (0.009) -1% Green Spaces & Active Leisure 1.274 1.278 0.004 0% Leisure 1.009 0.904 (0.105) -10% Licensing (0.064) (0.064) 0.000 0% Resorts 0.127 0.146 0.019 15% Waste, Recycling & Cleansing 7.612 7.723 0.111 1% 11.575 11.591 0.016 0% Total all services 20.272 19.625 (0.647) Financing Items 0.256 0.600 0.344 135%

Totals 20.528 20.225 (0.303)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Monitoring 2026/27 Q1Report 233 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 31 attended
LB
Louisa BrintonOfficer, in attendance
PB
Councillor Phil BullivantChair, present
RB
Councillor Richard BuscombeGuest, in attendance
TC
Trish CornsOfficer, in attendance
DE
David EatonOfficer, in attendance
KF
Kay FiceOfficer, in attendance
CF
Charlie FisherOfficer, in attendance
RH
Councillor Robert HayesCommittee Member, present
JH
Councillor Jackie HookGuest, in attendance
ML
Michelle LuscombeOfficer, in attendance
AM
Councillor Andrew MacGregorCommittee Member, present
JM
Councillor Jack MajorCommittee Member, present

All 31 on the meeting page

On this subject at Teignbridge

Search all
  1. Budget Monitoring 2026/27 Q1This decision
  2. Q1 2026/27 Budget MonitoringNoted
  3. Strata Budget Monitoring and Performance October 2024-25Noted
  4. 2023/24 Draft Final Accounts & Treasury Management, 2024/25 Budget Monitoring - Revenue & Capital, Treasury Management Lending ListNoted
  5. Financial - 24/25 - Budget MonitoringNoted
  6. Strata Budget Monitoring Outturn 2022-23Noted

More from Teignbridge Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 MinutesThe of the meeting held on 16 June 2026 were approved as a correct record and signed by the Chair. Approved Open
15 Sep 2026 Declarations of InterestsCouncillors Bullivant and C Parker declared a non-pecuniary interest in agenda item 13 voluntary sector funding annua... Decided Open
15 Sep 2026 Update on task and finish groupsRESOLVED a) The MTFP Review group update be received and endorsed. b) Consideration of the draft Terms of Reference f... Deferred Open
15 Sep 2026 2025/26 Q4 Performance Monitoring (January - March 2026)The Committee reviewed the agenda report. Each of the six One Teignbridge Strategy Themes; Community, Economy, Enviro... Agreed Open
15 Sep 2026 Voluntary Sector Service Level Agreement (SLA) Outputs and FundingRESOLVED The Council’s continued support for community and voluntary sector organisations through the ongoing funding... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies