RESOLVED – that delegated authority be granted to the Development Management Service Delivery Manager to grant planning permission subject to the following: a) the applicant/landowners entering into a Section 106 agreement with the Local Planning Authority (subject to indexation from the date of committee with terms to be agreed by the Development Management Service Delivery Manager) relating to: i ) Highway contribution of £12,638.30 towards the Telford Growth Point Package relating to the Naird , Randlay Interchange and / or the Brockton Loop, payable upon the commencement of development, indexed and any unspent monies after 5 years refunded to the applicant; b) the conditions contained within the report (with authority to finalise conditions and reasons for approval to be delegated to Development Management Service Delivery Manager).
Word for word from the decision Telford & Wrekin published for this meeting.Source: democracy.telford.gov.uk
TWC/2019/0216 Land rear of Merlin House, Halesfield 19, Halesfield, Telford, Shropshire Erection of 2no. industrial buildings with associated parking
APPLICANT RECEIVED Bespoke Construction Services Ltd 15/03/2019
PARISH WARD Madeley Madeley and Sutton Hill
THIS APPLICATION HAS BEEN REFERRED TO PLANNING COMMITTEE AS IT CONTAINS A S106 AGREEMENT RELATING TO FINANCIAL CONTRIBUTIONS
1.0SUMMARY RECOMMENDATION
1.1It is recommended that DELEGATED AUTHORITY be granted to the Development Management Service Delivery Manager to GRANT FULL PLANNING PERMISSION subject to a S106, conditions and informatives.
2.0SITE AND SURROUNDINGS
2.1The application site measures 0.5 hectares, comprising a fairly flat parcel of largely vacant undeveloped land sitting at the rear of an existing office and warehouse unit. A section of the site at the southern end is laid to tarmac utilised for car parking and container storage. The site is located in a central position off Halesfield 19 towards the north western edge of the Halesfield industrial estate, a Strategic Employment Area as set out in policy EC1 of the Telford & Wrekin Local Plan (TWLP) and Employment Area as designated by Policy E1 of the Madeley Neighbourhood Plan. Halesfield 19 is positioned approximately four miles from Telford Town Centre and one mile from Madeley High Street.
2.2The site is bordered along the western and southern boundaries by mature tree planting set behind palisade fencing, the former running to the A442 Brockton Way. The western planting area is designated as Green Network through the Local Plan. The northern and eastern boundaries are demarked by a mix of the neighbouring building, palisade and paladin fencing. A range of employment uses sit to the north, east and south of Halesfield 19, including solar PV, engineering, vehicle body manufacturing, flooring production, and printed label premises. The nearest residential development is set back from the western side of the A442 at approximately 160m from the edge of the site.
3.0APPLICATION DETAILS
3.1This application seeks full planning permission for the erection of two general industrial buildings (use class B2) collectively totalling 1,892sqm, fronted by parking and yard areas. An additional bank of parking is further proposed along the southern edge of the site. Each building (single storey) is proposed to be subdivided into four units sought for small to medium sized companies and start-up businesses. The existing access serving the neighbouring Bespoke Construction and Hartman (design and distribution of outdoor furniture) building is proposed to be utilised with a re- profiled entrance. Drainage is proposed to be conveyed to mains for foul, and a SuDS (sustainable urban drainage system) approach to surface water. A total of 48 car parking spaces (10 of which would be disability spaces), and 3 articulated vehicle parking spaces would be provided.
3.2The application is accompanied by the following supporting documents: - Design and Access Statement - Drainage Strategy - Geo-environmental Report - Transport Statement and Travel Plan - Arboricultural Report - Ecological Assessment
3.3Proposed materials comprise walls and roof (10% comprising flush rooflights) of profiled metal cladding, uPVC windows and doors, with metal shutter doors, existing palisade and paladin fencing arrangements would remain with existing gates to be relocated to suit, a tarmac finish is proposed to the parking and yard areas.
3.4The application is subject to a Section 106 agreement securing financial contributions towards the following:- - Highways £12,638.30 strategic highways contribution based upon additional PM peak trip generation onto the network, this would contribute towards the Telford Growth Point Package relating to the Naird, Randlay Interchange and / or the Brockton Loop.
4.0RELEVANT HISTORY
4.1W2002/0227 - Erection of 2.4 Metre High Steel Palisade Security Fencing and Gates. Full Granted 04/04/2002
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingRESOLVED – that the minutes of the meeting of the Planning Committee held on 18 March 2026 be confirmed and signed by...
Minutes of the Previous MeetingRESOLVED – that the minutes of the meeting of the Planning Committee held on 4 February 2026 be confirmed as a correc...
Minutes of the Previous MeetingRESOLVED – that the minutes of the meeting of the Planning Committee held on 10 December 2025 be confirmed and signed...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.