Internal Audit Activity & Update to Internal Audit Charter 2024/2025

Noted Finance 3 papers

Audit Committee noted this item on Wednesday 31 January 2024. Below is the council's own wording, with the papers it was decided on.

ItemAU34

Resolved

RESOLVED – that: a) the information contained in respect of the Internal Audit Planned Work undertaken between 1 November 2023 and 31 December 2023 and unplanned work to date be noted; and b) the revised Internal Audit Charter 2024/2025 be approved.
Word for word from the decision Telford & Wrekin published for this meeting. Source: democracy.telford.gov.uk

Follow this further

Built from Telford & Wrekin's papers

What the report saysPro

Report to Audit Committee

Purpose of report

2.1The purpose of this report is to update members on the progress made against the 2023/24 Internal Audit Plan and to provide information on the recent work of Internal Audit.

2.2To provide members with an update on the internal Audit Charter for 2024/25.

Background

3.1This report provides information on the work of Internal Audit from 1 November 2023 to 31 December 2023 and provides an update on the progress of previous audit reports issued.

3.2The key focus for the team during this period was the completion of audits on the annual audit plan and fulfilling commercial contracts.

3.3The information included in this progress report will feed into and inform our overall opinion in our Internal Audit Annual Report. All audit reports issued during the year are given an overall audit opinion based on the following criteria:

Level of Assurance/Audit Opinion & Definition

Good (Green) Reasonable (Yellow) There is a sound system of control There is a sound system of control but designed to address relevant risks there is evidence of non-compliance with with controls being consistently some of the controls. applied.

Limited (Amber) Poor (Red) Whilst there is a sound system of The system of control is weak and there is control, there are weaknesses in the evidence of non-compliance with the system that leaves some risks not controls that do exist. addressed and there is evidence of non-compliance with some key controls.

2 Internal Audit Activity & Update to Internal Audit Charter 2024/2025

3.4To determine the overall grading of the Internal Audit report each recommendation is risk rated (high, medium or low). The recommendation risk rating is based on the following criteria:

High risk = A fundamental weakness which presents material risk to the system objectives and requires immediate attention by management.

Medium risk = A recommendation to address a control weakness where there are some controls in place but there are issues with parts of the control that could have a significant impact.

Low risk = A recommendation aimed at improving the existing control environment or improving efficiency, these are normally best practice recommendations.

3.5The chart below shows the percentage of high (red segment), medium (yellow segment) and low (green segment) risk recommendations made for the reports issued during this period.

3.6The level of assurance (based on the table above) for audit reports issued in this period is detailed below.

3 Internal Audit Activity & Update to Internal Audit Charter 2024/2025

3.7The information in the above pie charts is broken down in the summary table below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2023 24 Internal Audit PlanAppendix A 453 KB Download
PDF
2024/25 Internal Audit CharterAppendix B 407 KB Download
PDF
Internal Audit Activity & Update to Internal Audit Charter 2024/2025Report 332 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
MB
Michelle BrockwayOfficer, in attendance
AL
Anthea LoweOfficer, in attendance
AM
Councillor Angela McClementsChair, present
GC
Councillor Graham CookVice-Chair, apologies
ED
Councillor Elise DaviesCommittee Member, present
SR
Councillor Stephen ReynoldsCommittee Member, present
PT
Councillor Paul ThomasCommittee Member, present
BT
Councillor Bill TomlinsonCommittee Member, present
CT
Councillor Chris TurleyCommittee Member, present
IW
Ian WykesOfficer, in attendance

On this subject at Telford & Wrekin

Search all
  1. Internal Audit Activity & Update to Internal Audit Charter 2024/2025This decision
  2. Internal Audit Activity & Internal Audit CharterNoted
  3. Internal Audit Annual Report 2024-25Noted
  4. Internal Audit Activity Report & Update to Internal Audit CharterNoted
  5. Internal Audit Activity ReportNoted
  6. Internal Audit Activity ReportNoted

More from Telford & Wrekin Audit Committee

All decisions
MeetingDecisionOutcome
27 May 2026 Minutes of the Previous MeetingRESOLVED – that the minutes of the meeting held on 28 January 2026 be confirmed and signed by the Chair. Decided Open
27 May 2026 Audit Committee Terms of ReferenceRESOLVED – that: a) the report be noted; and b) the for the 2026/2027 municipal year be adopted. Noted Open
27 May 2026 Information Governance & Caldicott Guardian Annual ReportRESOLVED – that: a) the ... view the full minutes text for item AU8 Decided Open
28 Jan 2026 Minutes of the Previous MeetingRESOLVED – that the minutes of the meeting held on 19 November 2025 be confirmed and signed by the Chair. Decided Open
28 Jan 2026 Becoming Carbon Neutral and Climate Change Adaptation UpdateRESOLVED – that the update on Telford and Wrekin Council becoming Carbon Neutral and the additional work the Council ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies