Telford & Wrekin Council
Cabinet, Thursday 16 July 2026 at 10.00am

Better Buses in Telford & Wrekin - Update

Noted Executive 1 paper

AI summaryTelford & Wrekin Cabinet notes six new bus routes have passed one million trips, with £2 fares and new infrastructure, and delegates authority to keep evolving the network.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted bus improvements and delegated further decisions
Money£5,047,995 revenue and £6,784,510 capitalMulti-year Department for Transport funding for buses
What happens nextContinue evolving the bus networkDirector to act on resident feedback
Who it affectsAll wards in the boroughEvery ward benefits from bus services

What was decided

Cabinet noted ongoing improvements including six new bus routes, a £2 adult fare cap, the On Demand service, and two electric buses being commissioned. Report 3.10, 3.13, 3.17

Cabinet noted that continued investment is funded by government grants, council funds and developer contributions.

Cabinet delegated authority to the Director of Neighbourhood and Enforcement Services, in consultation with the relevant cabinet member, to evolve the network, and to the Director of Policy and Governance to sign legal documents.

Why

The council wants an affordable, reliable and well connected bus network that links homes, jobs, education and health sites and helps cut carbon. Report 3.1, 3.5

If the council had not stepped in in 2022, large parts of the borough would have lost bus services, as the market alone would not cover them. Report 3.9

Resident surveys in 2021, 2022 and November 2024 shaped the new routes and re-tendered services that started in July 2025. Report 3.7, 3.11

What happens next

The six retendered services will keep running, with the On Demand service planned to expand further across the borough. Report 3.11, 3.17

A summer park and ride trial will run weekends and Bank Holiday Mondays from July to September, linking Ironbridge Gorge, Wellington and The Wrekin. Report 3.18

The council is exploring options for evening and night time services and a potential travel support scheme for care leavers. Report 3.14, 3.19

The money

  • £5,047,995 Local Authority Bus Grant revenue funding for 2026 to 2029
  • £6,784,510 Capital funding for 2026 to 2030 for bus infrastructure and low emission vehicles

Options considered

  • Chosen: Continue supporting and developing new bus routes in the borough. Resident feedback and risk that commercial market would not cover many areas Report 3.9
  • Rejected: Stop supporting new bus services and rely on commercial provision. Would leave large parts of the borough without any bus services

Implications

  • Financial: Multi-year funding gives certainty to 2029 for revenue and 2030 for capital, but no confirmed revenue funding beyond 2029.
  • Legal: The Bus Services Act 2025 changed the law so the council can now establish its own bus company if needed.
  • Equalities: The £2 fare cap, English National Concessionary Fare Scheme and wide coverage support access for all groups.
  • Climate: Bus travel cuts carbon per passenger; two electric buses are being commissioned and shelters use solar or wind power.
  • Risk: Government funding structures could change, so the council will seek external sources including Section 106 contributions.
  • Staffing: The report says there are no HR implications.

Who and where

  • All borough residents and visitors using bus services Report 3.10
  • Workers travelling to employment sites such as Hortonwood, Halesfield and Stafford Park Report 3.8
  • Patients and visitors needing links to the Princess Royal Hospital
  • Rural communities in the north of the borough including Newport and Wellington links Report 3.8
  • Users of the On Demand service in the Gorge, Horsehay, Lightmoor and Telford College areas Report 3.17
  • Eligible older and disabled passengers using the English National Concessionary Fare Scheme

Timeline

  • April 2022: Enhanced Partnership between the council, bus operators and user groups began Report 3.3
  • December 2022: First of six new bus routes launched Report 3.8
  • January 2025: Cabinet approved securing new services from July 2025 Report 3.11, P31
  • Early 2025: On Demand bus service pilot launched in the Gorge Parish area Report 3.17
  • July 2025: Six bus services were re-tendered and reconfigured Report 3.11
  • October 2025: Bus Services Act 2025 received Royal Assent, allowing councils to run their own bus companies
  • December 2025: Multi-year Local Authority Bus Grant allocation announced
  • May 2026: £2 fare cap extended to all bus routes that start and end in the borough Report 3.13
  • July 2026: Cabinet considered this update report
  • July to September: Summer park and ride trial linking Ironbridge Gorge, Wellington and The Wrekin Report 3.18
  • 2026 to 2029: Period covered by £5,047,995 of revenue bus funding
  • 2026 to 2030: Period covered by £6,784,510 of capital bus funding

Plain English for the jargon

  • Enhanced Partnership: A formal agreement between the council, bus operators and user groups to improve bus services together.
  • Bus Service Improvement Plan (BSIP): A council plan, required by the National Bus Strategy, setting out how local bus services will be improved.
  • Section 106: Planning obligations where developers contribute money towards local infrastructure, used here to help fund bus services.
  • On Demand bus: A flexible minibus service where passengers book journeys rather than following a fixed route.
  • Citymapper: A mobile app that gives real time journey planning and bus information.
  • Local Authority Bus Grant: Government funding given to councils to support local bus services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB-13

Resolved

RESOLVED – that: a) the continued improvements in bus travel and connectivity across Telford and Wrekin over the last two years be noted as follows: · The provision of six new bus routes, that have now completed 1million passenger trips; · £2 fare cap across the borough (£1 for under 19’s) as part of the Council’s wider commitment to provide cost of living support to our residents; · Infrastructure improvements including new bus shelters; · Improved journey experience through development of the ‘ Citymapper ’ app; · Introduction and expansion of the Travel Telford ‘On Demand’ bus network; and · The delivery of two electric buses. b) the continued investment in our bus network made possible by recent government funding, Council investment and user of developer funding to bring forward improvements be noted; c) delegated authority be granted to the Director: Neighbourhood & Enforcement Services, in consultation with the Cabinet Member for Jobs, Transport & Digital Connectivity to take necessary steps to continue to evolve the bus network in Telford and Wrekin. In doing so, ensure the evolution continues to be founded on resident and user feedback to ensure affordable, reliable and well connected bus services are bought forward; and d) delegated authority be granted to the Director: Policy & Governance to execute any legal documentation required to facilitate and implement the recommendations within this report.
Word for word from the decision Telford & Wrekin published for this meeting. Source: democracy.telford.gov.uk

Follow this further

Built from Telford & Wrekin's papers

What the report saysPro

Report to Cabinet

Background

3.1Telford & Wrekin Council is committed to providing a better-connected and affordable bus network, linking residential, leisure and employment sites in line with the Councils Vision for 2032. Well-connected transport links borough towns with key education, employment and shopping destinations while helping to ease congestion and reduce carbon emissions.

3.2In 2021, The National Bus Strategy for England was published and sought to transform the quality of bus services across the country. In 2024 government committed to providing greater powers locally for bus services; as transport authority, the council has a pivotal role in bringing forward positive change to the bus network. This change is underpinned through the council's commitment to partnership working.

3.3Cabinet at their October 2021 meeting approved the creation of an Enhanced Partnership; at the same meeting, Cabinet received an update on the development of a Bus Service Improvement Plan (BSIP) as required by the National Bus Strategy. Telford and Wrekin entered into an Enhanced Partnership on 1st April 2022 that seeks to bring together the council, bus operators and user groups with a focus on increasing patronage, improving services and delivering transformation.

2 Better Buses in Telford & Wrekin - Update

3.4The Bus Service Improvement Plan sets the vision for the bus network in the borough, it is updated in line with the Department for Transport (DfT) guidelines and timescales and published on the council's website.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Better Buses in Telford & Wrekin: UpdateReport 339 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
LC
Councillor Lee CarterChair, present
RO
Councillor Richard OvertonVice-Chair, present
PD
Councillor Paul DavisCommittee Member, present
ZH
Councillor Zona HanningtonCommittee Member, present
CH
Councillor Carolyn HealyCommittee Member, present
AM
Councillor Angela McClementsCommittee Member, present
KM
Councillor Kelly MiddletonCommittee Member, present
SR
Councillor Shirley ReynoldsCommittee Member, present
PW
Councillor Paul WatlingCommittee Member, present
OV
Councillor Ollie VickersCommittee Member, present
AL
Anthea LoweOfficer, in attendance
PS
Paige StarkeyOfficer, in attendance

More from Telford & Wrekin Cabinet

All decisions
MeetingDecisionOutcome
12 Nov 2026 Minutes of the Previous MeetingRESOLVED – that the minutes of the meeting held on 15 October 2026 be confirmed as a correct record and signed by the... Decided Open
12 Nov 2026 Cost of Living Strategy 2026 - 2029RESOLVED – that: a) progress and impact of the previous Cost of Living Strategy 2022-2025, through which the Council ... Noted Open
12 Nov 2026 Better Homes for All UpdateRESOLVED – that: a) the continued impact of the Better Homes For All Programme supporting tenants, landlords and comm... Approved Open
12 Nov 2026 Council House Building ProgrammeRESOLVED – that: a) the delivery of 300 new Council owned homes over the next 3 years, as set out in the report, sign... Approved Open
12 Nov 2026 Adoption of Telford & Wrekin Local PlanRESOLVED – that: a) the Inspectors have, subject to approval of recommended modifications found the Local ... view th... Approved Open