RESOLVED that the Head of Planning (or equivalent authorised officer) be authorised to grant outline planning permission for the development, subject to: a) Within six months of the date of the Committee’s resolution to approve, the completion of a legal agreement under the provisions of Section 106 of the Town and Country Planning Act 1990 dealing with the following matters (where relevant): · On-site Council Housing/Affordable Housing; · On-site or off-site open space/play equipment. b) Planning conditions in accordance with those set out in ( i ) below (but with such amendments and additions, if any, to the detailed wording thereof as the Head of Planning (or the equivalent authorised officer) in their discretion considers appropriate). ( i ) Conditions: 1. Standard 3 year time limit for commencement; 2. Accordance with approved plans; 3. Highways conditions (as recommended by the Highway Authority); 4. Ecological mitigation/enhancement plan; 5. Surface water drainage/foul drainage scheme; 6. SuDS maintenance/monitoring plan; 7. Hard and soft landscaping plan/implementation; 8. Details of lighting, materials and refuse storage/collection points; 9. Broadband connection; and 10. Contaminated land. c) That the Head of Planning (or the equivalent authorised officer) be authorised to refuse planning permission in the event that such legal agreement has not been completed within the period of six months, as the requirements necessary to make the development acceptable in planning terms had not been secured through a Section 106 planning obligation.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
1.1This is a full planning application for 16 new bungalows on an existing agricultural field adjoining the existing development boundary for Thorrington. The site is predominantly square shaped in nature and partially enclosed by mature trees to the west boundary. The site measures some 1.10 hectares in area. The site is accessed via an existing layby which will be permanently closed. As a full application, the Planning Committee is being asked to approve a detailed scheme including 16 detached and semi-detached bungalows, containing 11 three bed bungalows and 5 two bed bungalows. The properties are designed in traditional style and are considered appropriate in this location.
1.2As noted the site adjoins but is outside of the settlement development boundary in the adopted Local Plan and the new preferred options draft. Because the Council does not have an up to date Local Plan and is currently unable to identify a five-year supply of deliverable housing sites as required by government planning policy, this application has been considered in line with the government’s ‘presumption in favour of sustainable development’. Officers have needed to approach the application with a view to positively addressing, as far as possible, technical issues and other matters raised by consultees and residents.
1.3Thorrington is identified as a ‘smaller rural settlement’ in the emerging Local Plan where only small scale developments of upto 10 dwellings would normally be supported. However taking into account that the scheme is supported by the Parish Council and the need for additional housing Officers consider that approval is justified in this case.
1.4The development has attracted very little public interest with only two letters of objection to the principle of development being received. There are no objections from any statutory agencies and no financial contributions have been requested by Essex County Council or the NHS towards education or health provision. The highways arrangements have been approved by the Highway Authority who support the scheme subject to conditions.
1.5The development is considered to have limited impacts on the existing landscape or ecology. The existing trees located on the west boundary of the site will be retained.
1.6Officers consider that this development complies with the requirements of the National Planning Policy Framework and the recommendation is approval subject to a section 106 agreement to secure affordable housing and open space/play facilities.
Recommendation: Approval
That the Head of Planning be authorised to grant planning permission for the development subject to:-
a) Within 6 (six) months of the date of the Committee’s resolution to approve, the completion of a legal agreement under the provisions of section 106 of the Town and Country Planning Act 1990 dealing with the following matters (where relevant):
On-site Council Housing/Affordable Housing; On site or off-site open space/play equipment.
b) Planning conditions in accordance with those set out in (i) below (but with such amendments and additions, if any, to the detailed wording thereof as the Head of Planning (or the equivalent authorised officer) in their discretion considers appropriate).
(i) Conditions:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.