That: (a) the financial position as at the end of September 2016 was noted; (b) that in respect of the 2016/17 budget it was approved that: · planning expenditure budgets be increased to facilitate additional capacity to meet the current demand for the service with the associated income budget increased by £0.102m as set out in the report; · the General Fund Capital Programme be increased by £0.120m to accommodate the increased cost of the air handling units at Clacton Leisure Centre funded by the adjustments set out in the report and; (c) the Council’s Treasury Management Practices be amended to allow the aggregate amount that can be invested with any one Local Authority to be increased from £4.000million to £6.000million.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
Key Decision Required: Yes In the Forward Plan: Yes
CABINET
25 NOVEMBER 2016
REPORT OF FINANCE, REVENUES AND BENEFITS PORTFOLIO HOLDER
A.4 CORPORATE BUDGET MONITORING REPORT FOR THE SECOND QUARTER OF 2016/17 (Report prepared by Richard Barrett)
PART 1 – KEY INFORMATION
PURPOSE OF THE REPORT To provide an overview of the Council’s financial position against the budget as at the end of September 2016 and to set out a number of budget adjustments required in 2016/17.
EXECUTIVE SUMMARY • The Council’s financial position against the approved budget has been prepared for the period to the end of September 2016 and is the second such report for 2016/17.
• It is still relatively early in the financial year and therefore some expenditure or income trends may still be emerging / evolving. However any significant issues arising to date have been highlighted and comments provided as necessary.
• The position to the end of September 2016, as set out in more detail in the Executive Summary attached, shows that overall the General Fund Revenue position is behind the profiled budget by £5.807m. After allowing for significant one- off budgets such as the Fit for Purpose Budget where commitments or decisions are still to be made, the position is revised to £1.701m behind the profiled budget. A considerable element of this variance is due to the timing of expenditure and income although some emerging issues have been identified which have been set out below.
• In respect of other areas of the budget such as the Housing Revenue Account, Capital Programme, debt recovery, treasury activity and LCTSS / council tax and business rates there are no significant issues that have been identified to date.
• Any emerging issues will be monitored and updates provided in future budget monitoring reports along with their consideration as part of the Financial Strategy and budget setting framework for 2017/18 where a longer term response may be required.
• The budget monitoring process continues to form a fundamental element of supporting the forecast for future years through the identification of savings that can be ‘banked’ as the year progresses rather than just as part of the annual budget setting cycle. This enables the medium term forecast to be updated on an on-going basis with the savings identified being available to support the future year’s budget. No transfers to the Building for the Future Reserve are proposed within this report but further consideration of such changes will form part of the detailed estimates process that will be reported to Cabinet in December following the completion of the comprehensive processes behind the formulation of the revised budget for 2016/17.
• A number of emerging issues have arisen during the second quarter that require budget adjustments to be made and specific recommendations required with further details highlighted below.
• A half year treasury management review has been carried out with a summary set out later on in this report along with an associated recommendation to revise the Council’s Treasury Management Practices to provide additional flexibility around investments with other Local Authorities.
• As mentioned in the first quarter’s report, the appendices reflect both the revised organisational restructure and portfolio structure. Although budgets have been reallocated to a revised department / portfolio, there are a limited number of budgets that will need to be split out with the timeliest opportunity to do this being the revised budget process over the autumn. This does not have a direct impact on the budget monitoring process as emerging issues will be highlighted where necessary regardless of where they may appear in the structure.
RECOMMENDATION(S) It is recommended that:
(a) The financial position as at the end of September 2016 be noted;
(b) that in respect of 2016/17 budget it be agreed that:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.