(a) Cabinet agrees the updated Financial Baseline 2017/18 and the detailed budget proposals (including fees and charges and special expenses), as set out in the Appendices to item A.7 of the Report of the Finance, Revenues and Benefits Portfolio Holder; (b) Cabinet requests the Corporate Management Committee’s comments on the Updated Financial Baseline 2017/18 and detailed budget proposals (including special expenses); and (c) all future expenditure in 2016/17 be in line with the proposed revised budget 2016/17 set out in the aforementioned Appendices, subject to final approval by Council at its meeting to be held on 7 February 2017, and that the corporate financial system be amended accordingly to reflect those changes along with any amendments arising from revisions to the code of practice relating to the presentation of the Council’s annual Statement of Accounts
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
Key Decision Required: Yes In the Forward Plan: Yes
CABINET 16 DECEMBER 2016
REPORT OF FINANCE, REVENUES AND BENEFITS PORTFOLIO HOLDER
A.7 UPDATED FINANCIAL BASELINE 2017/18 AND DETAILED BUDGET PROPOSALS FOR A REVISED BUDGET 2016/17 AND ORIGINAL BUDGET FOR 2017/18 (Report prepared by Richard Barrett)
PART 1 – KEY INFORMATION
PURPOSE OF THE REPORT To enable Cabinet to: Consider the updated financial baseline for 2017/18 To consider for approval the detailed budget proposals for a revised budget 2016/17 and original budget for 2017/18, including special expenses.
EXECUTIVE SUMMARY The updated financial baseline sets out how the financial and budget position of the Council for 2017/18 has progressed since Cabinet considered the Initial Financial Baseline for 2017/18 at its meeting on 5 August 2016.
During the year the Council accepted the Government’s minimum Revenue Support Grant (RSG) offer which means that unless the Government make any further changes, the minimum level of funding receivable over the next three years is as follows:
1) 2017/18 - £1.650m (reduction over prior year – 36%) 2) 2018/19 - £1.070m (reduction over prior year – 36%) 3) 2019/20 - £0.422m (reduction over prior year – 60%)
Since 2011/12 the Council has found savings totalling £12.000m. However, given the significant reductions in RSG set out, further savings of potentially £5.000m are required over the next three years, with £1.565m required in 2017/18 alone.
The detailed Local Government Finance Settlement figures were not available at the time this report was printed. If they do become available in time then they will be reported directly at the meeting, otherwise they will be included in the figures that will be presented to Cabinet in January 2017 when it considers the final budget proposals after consultation with the Corporate Management Committee.
A number of actions have been taken with the aim of delivering a balanced budget for 2017/18. To date a budget ‘gap’ of £0.603m remains. Work remains on-going to minimise this ‘gap’ before final recommendations are made to Full Council in February 2017.
A summary of the budget adjustments made along with other changes that have emerged during the budget setting process are set out later on in this report. Although additional costs and other adjustments have emerged, net savings / budget reductions totalling £0.962m have been identified to date.
1 It is important to note that the savings identified to date represent only the initial steps to close the forecasted funding gap in the longer term. Further uncertainties also remain against this overall backdrop which may not yet have been reflected in the forecasted budget ‘gaps’ in future years that may require additional savings to be identified to deliver a balanced and sustainable budget in the future.
The medium term forecast covering the period 2018/19 and 2019/20 is in the process of being updated with the outcome planned to be presented to Cabinet in January when the final budget position will be presented. It is difficult to forecast any further ahead at this stage given the huge level of uncertainty that the 100% retention of business rate model will introduce from 2020. The longer term forecast will remain a ‘live’ activity and updates will be provided to members as the forecast evolves over 2017/18.
RECOMMENDATION(S) It is recommended that:
a) Cabinet agrees the updated Financial Baseline 2017/18 and the detailed budget proposals (including fees and charges and special expenses) set out in the Appendices, which include the use of £2.646m from reserves to meet the cost of paying the three year pension deficit amount in one payment in early 2017/18;
b) Cabinet requests the Corporate Management Committee’s comments on the Updated Financial Baseline 2017/18 and detailed budget proposals (including special expenses); and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.