That: a) Cabinet agrees to the proposal set out by Brightlingsea Town Council; b) Cabinet delegates authority to the Corporate Director (Operational Services) to manage the impact of the reduction in savings within existing budgets in consultation with the Head of Finance, Revenues and Benefits; and c) Cabinet agrees that, by the end of September 2017, arrangements be put in place to commence the transfer of the pool to Brightlingsea Town Council, the exact details of the transfer arrangements to be agreed by the Corporate Director (Corporate Services), or further agrees that the Pool be decommissioned and authorises the Corporate Directors (for both Corporate Services and Operational Services) to commence the decommissioning process.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
To advise Cabinet of the proposal submitted by Brightlingsea Town Council (BTC) in respect of the future of Brightlingsea Swimming Pool (BSP).
To consider the offer in light of the financial implications and to determine whether to accept the offer and the impact of such an acceptance.
Executive summary
Following the decision made by Cabinet in June 2016 to accept an offer from BTC to undertake capital repairs to BSP and for TDC to cover the running costs of the pool for the shortened 2016 season, communication and discussions have been ongoing between BTC and TDC about the future of the pool.
A deadline was originally set for the end of 2016 for a decision to be made as to whether BTC would take a long lease on the pool and maintain and operate the pool thereafter or for TDC to decommission the pool.
Following a meeting in early 2017, at which BTC set out the actions it had taken to evaluate the feasibility for them operating the pool, a proposal has been submitted by BTC to part meet the cost of operating the pool for the 2017 season to allow BTC more time to complete their feasibility work.
A provisional date has been set for a final decision on the future of the pool which will be shortly after the end of the 2017 season.
In essence BTC agrees to offset 50% of the operating deficit, up to a maximum of £30,000, for the 2017 season in order for BTC to complete its Business Plan with an end date of September 2017 for a final decision to be made. 1.3 RECOMMENDATION(S)
a) That Cabinet considers whether it wishes to agree to the proposal set out by BTC, as listed in section 3 of this report;
b) Subject to Cabinet agreeing to the proposal set out by BTC, Cabinet delegates authority to the Corporate Director (Operational Services) to manage the impact of the reduction in savings within existing budgets in consultation with the Head of Finance, Revenues and Benefits.
c) Subject to Cabinet agreeing to the proposal set out by BTC, agrees that by the end of September 2017 arrangements are put in place to commence the transfer of the pool to BTC, the exact details of the transfer arrangements to be agreed by the Corporate Director, Corporate Services, or agrees that the pool is decommissioned and authorises the Corporate Director’s, Corporate Services and Operational Services to commence the decommissioning process.
PART 2 – IMPLICATIONS OF THE DECISION
2.1DELIVERING PRIORITIES
Due to the requirement to make significant savings, this decision impacts on the Council’s key priority to balance the budget. The service provided by the sports facilities positively assists the Council to promote healthier lifestyles and wellbeing and the pool is a tourist destination contributing to the tourist economy.
2.2FINANCE, OTHER RESOURCES AND RISK
Finance The financial position in respect of the pool was set out in the June Cabinet report with the average running deficit being around £60,000 per annum. The deficit in 2016 was much lower (c£24,000) as it had a much compressed opening period.
On the basis of the average deficit a figure of £60,000 has been included within the budget savings total for 2017/18 on the basis that the pool with not operate during 2017.
If the decision is taken to accept the offer from BTC the saving arising from BSP will be reduced, the size of the reduction will be determined by the operating deficit but is unlikely to exceed a reduction of £30,000. If the operating deficit is similar to the 2016 season the savings figure will be reduced by £12,000, taking into account the offer made by BTC.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
166Joint Report of the Deputy Leader of the Council and the Leisure, Well-being and Partnerships Portfolio Holder - A.4 - Brightlingsea Swimming PoolThis decision
Who was there
8 of 16 attended
NS
Councillor Neil Stock OBEChairman, apologies (on leave)
CG
Councillor Carlo GuglielmiVice-Chairman, in the Chair, present
Joint Report of the Deputy Leader of the Council and the Leisure, Well-being and Partnerships Portfolio Holder - A.4 - Brightlingsea Swimming PoolThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.