CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tendring District Council
Cabinet, Friday 26 May 2017 at 10.30am

Joint Report of the Resources and Corporate Services Portfolio Holder and the Leisure and Partnerships Portfolio Holder - A.3 - Clacton Leisure Centre Ventilation System

Decided Executive 1 paper

Cabinet decided this item on Friday 26 May 2017. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

That an additional £56,640 be allocated to the capital programme budget for the replacement of the Pool Hall Ventilation System at Clacton Leisure Centre and that the Head of Finance, Revenues and Benefits be authorised to make the necessary reallocation of funding within the existing capital programme.
Word for word from the decision Tendring published for this meeting. Source: tdcdemocracy.tendringdc.gov.uk

Follow this further

Built from Tendring's papers

What the report saysPro

Report to Cabinet

Key Decision Required: YES In the Forward Plan: NO – GENERAL EXCEPTION PROCEDURE USED

CABINET

26 MAY 2017

JOINT REPORT OF THE RESOURCES & CORPORATE SERVICES PORTFOLIO HOLDER & THE LEISURE AND PARTNERSHIPS PORTFOLIO HOLDER

A.3 CLACTON LEISURE CENTRE VENTILATION SYSTEM (Report prepared by Michael Carran)

PART 1 – KEY INFORMATION

PURPOSE OF THE REPORT To request additional budgetary provision to ensure sufficient funding for the replacement of the Pool Hall Ventilation system at Clacton Leisure Centre (CLC).

EXECUTIVE SUMMARY  The sum of £50,000 was originally included in the capital programme to replace the Pool Hall Ventilation System at CLC, which is now beyond its economic lifecycle. After further exploratory works by the mechanical consultant appointed to oversee the project on behalf of the Council, an additional £120,000 was allocated, as the original budget was deemed substantially insufficient.

 A tender exercise was carried out in February 2017 with five contractors submitting quotations. An exercise in value engineering was subsequently undertaken by the consultant, with the cheapest quote being reduced to £199,539, from an original submission of £264,112. The reason for the variance from the original budget is an underestimation of the physical mechanical costs from the consultant’s projections and the added cost of keeping the facility open throughout the works.

 After taking into account the remaining professional fees payable to the mechanical consultant of £9,518, there is currently a project shortfall of £56,636. This balance is required to allow a works order to be placed and commence this essential installation.

 As the current system has deteriorated significantly, a temporary unit has been installed to ensure satisfactory environmental conditions are maintained in the pool hall until a new unit is installed. This temporary solution is not ideal and has been the subject of some complaints during cold weather.

RECOMMENDATION(S) That an additional £56,640 is allocated to the capital budget for the replacement of the Pool Hall Ventilation System at CLC, with delegation given to the Head of Finance, Revenues and Benefits to make the necessary reallocation of funding within the existing capital programme. PART 2 – IMPLICATIONS OF THE DECISION

DELIVERING PRIORITIES The installation of this ventilation system will assist the Council in its objective to enhance its Leisure Facilities and achieve affordable excellence throughout its services.

FINANCE, OTHER RESOURCES AND RISK Finance and other resources The following table sets out the lowest tender figure submitted, together with the amount deducted after the consultant’s value engineering exercise. This has resulted in the figure of £199,539.01.

Contractor’s Submission Tender Figure 264,111.61 After value engineering -64,572.60 Revised Figure 199,539.01

It was originally considered that works would be required to the pool hall roof in order to install the new unit, but after intrusive investigations, this is no longer considered necessary at this time. This accounts for the majority of the value engineering figure.

Further to the tender sum payable to the contractor, there will be a total of £9,518 in professional fees to the Mechanical Consultant who will oversee the works.

The additional budget required to complete the necessary works is £56,640. It is proposed to meet this cost by reallocating funding already within the capital programme which was originally set aside as a contingent sum for a capital project that was completed several years ago but where the final position has only just been concluded.

Risk If the ventilation system is not replaced, the environmental conditions in the pool hall will be unsuitable for customer access.

LEGAL The proposals are within the Council’s powers. The Request for allocation of additional budget is in accordance with the Budget and Policy Framework, as set out in Part 5 of the Council’s Constitution

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Joint Report of the Resources and Corporate Services Portfolio Holder and the Leisure and Partnerships Portfolio Holder: A.3: Clacton Leisure Centre Ventilation SystemReport 158 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 24 attended
NS
Councillor Neil Stock OBEChairman, present
CG
Councillor Carlo GuglielmiCommittee Member, apologies (council duties)
TF
Councillor Tanya FergusonCommittee Member, present
PH
Councillor Paul HoneywoodCommittee Member, present
LM
Councillor Lynda McWilliamsCommittee Member, present
MT
Councillor Michael TalbotCommittee Member, present
NT
Councillor Nick TurnerCommittee Member, apologies (on leave)
GW
Councillor Giles WatlingCommittee Member, present
JB
Councillor Jeff BraySpokesperson, present
JB
Councillor Joy BroderickSpokesperson, present
RB
Councillor Robert BuckeSpokesperson, present as substitute
PC
Councillor Peter CawthronSpokesperson, absent (unspecified)

All 24 on the meeting page

On this subject at Tendring

Search all
  1. Joint Report of the Resources and Corporate Services Portfolio Holder and the Leisure and Partnerships Portfolio Holder - A.3 - Clacton Leisure Centre Ventilation SystemThis decision
  2. Joint Reference from the Cabinet and the Resources and Services Overview & Scrutiny Committee - A.5 - Annual Capital and Treasury Strategy for 2022/23 (including Prudential and Treasury Indicators)Agreed
  3. Matters Referred to the Cabinet by a Committee - Reference from the Resources and Services Overview & Scrutiny Committee - A.7 - Joint Use Sports Facilities UpdateNoted
  4. Cabinet Members' Items - Joint Report of the Housing Portfolio Holder and the Finance and Corporate Resources Portfolio Holder - A.3 - Housing Revenue Account Budget Proposals 2019/2020Approved
  5. Cabinet Members' Items - Joint Report of the Finance & Corporate Resources Portfolio Holder and the Corporate Enforcement Portfolio Holder - A.4 - Utilisation of 20% Increase in Planning FeesApproved
  6. Cabinet Members' Items - Joint Report of the Finance and Corporate Resources Portfolio Holder, the Investment and Growth Portfolio Holder and the Leisure and Tourism Portfolio Holder - A.8 - Mayflower 400: An Opportunity for TendringApproved

More from Tendring Cabinet

All decisions
MeetingDecisionOutcome
13 Nov 2026 Minutes of the Last MeetingRESOLVED that the minutes of the meeting of the Cabinet, held on Friday 23 October 2026, be approved as a correct rec... Approved Open
13 Nov 2026 Cabinet Members' Items - Report of the Portfolio Holder for Corporate Finance & Governance - A.1 - Financial Performance Report 2026/27 - General Update at the end of September 2026RESOLVED that Cabinet – (a) notes the Council’s in-year financial position as at the end of September 2026; (b) appro... Approved Open
13 Nov 2026 Cabinet Members' Items - Report of the Corporate Finance & Governance Portfolio Holder - A.2 - The Local Council Tax Support Scheme, Discretionary Council Tax Exemptions / Discounts / Premiums for 2027/28 and Annual Minimum Revenue Provision Policy Statement 2027/28RESOLVED that Cabinet – a) agrees that the underlying LCTS scheme for 2027/28 remains the same as the current year, a... Agreed Open
13 Nov 2026 Cabinet Members' Items - Report of the Housing & Planning Portfolio Holder - A.3 - Annual Housing Improvement, Performance & Assurance Report 2025/26RESOLVED that Cabinet – (a) notes the contents of the Annual Housing Improvement, Performance & Assurance Report 2025... Decided Open
13 Nov 2026 Cabinet Members' Items - Report of the Housing & Planning Portfolio Holder - A.4 - Adoption of the Conservation Area Character Appraisals and Management Plans for St Osyth and Manningtree & MistleyRESOLVED that – (a) the outcome of the public consultation exercises summarised in this report (A.4) be noted; and (b... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies