Joint Report of the Resources and Corporate Services Portfolio Holder and the Leisure and Partnerships Portfolio Holder - A.3 - Clacton Leisure Centre Ventilation System
DecidedExecutive1 paper
Cabinet decided this item on Friday 26 May 2017. Below is the council's own wording, with the papers it was decided on.
That an additional £56,640 be allocated to the capital programme budget for the replacement of the Pool Hall Ventilation System at Clacton Leisure Centre and that the Head of Finance, Revenues and Benefits be authorised to make the necessary reallocation of funding within the existing capital programme.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
Key Decision Required: YES In the Forward Plan: NO – GENERAL EXCEPTION PROCEDURE USED
CABINET
26 MAY 2017
JOINT REPORT OF THE RESOURCES & CORPORATE SERVICES PORTFOLIO HOLDER & THE LEISURE AND PARTNERSHIPS PORTFOLIO HOLDER
A.3 CLACTON LEISURE CENTRE VENTILATION SYSTEM (Report prepared by Michael Carran)
PART 1 – KEY INFORMATION
PURPOSE OF THE REPORT To request additional budgetary provision to ensure sufficient funding for the replacement of the Pool Hall Ventilation system at Clacton Leisure Centre (CLC).
EXECUTIVE SUMMARY The sum of £50,000 was originally included in the capital programme to replace the Pool Hall Ventilation System at CLC, which is now beyond its economic lifecycle. After further exploratory works by the mechanical consultant appointed to oversee the project on behalf of the Council, an additional £120,000 was allocated, as the original budget was deemed substantially insufficient.
A tender exercise was carried out in February 2017 with five contractors submitting quotations. An exercise in value engineering was subsequently undertaken by the consultant, with the cheapest quote being reduced to £199,539, from an original submission of £264,112. The reason for the variance from the original budget is an underestimation of the physical mechanical costs from the consultant’s projections and the added cost of keeping the facility open throughout the works.
After taking into account the remaining professional fees payable to the mechanical consultant of £9,518, there is currently a project shortfall of £56,636. This balance is required to allow a works order to be placed and commence this essential installation.
As the current system has deteriorated significantly, a temporary unit has been installed to ensure satisfactory environmental conditions are maintained in the pool hall until a new unit is installed. This temporary solution is not ideal and has been the subject of some complaints during cold weather.
RECOMMENDATION(S) That an additional £56,640 is allocated to the capital budget for the replacement of the Pool Hall Ventilation System at CLC, with delegation given to the Head of Finance, Revenues and Benefits to make the necessary reallocation of funding within the existing capital programme. PART 2 – IMPLICATIONS OF THE DECISION
DELIVERING PRIORITIES The installation of this ventilation system will assist the Council in its objective to enhance its Leisure Facilities and achieve affordable excellence throughout its services.
FINANCE, OTHER RESOURCES AND RISK Finance and other resources The following table sets out the lowest tender figure submitted, together with the amount deducted after the consultant’s value engineering exercise. This has resulted in the figure of £199,539.01.
Contractor’s Submission Tender Figure 264,111.61 After value engineering -64,572.60 Revised Figure 199,539.01
It was originally considered that works would be required to the pool hall roof in order to install the new unit, but after intrusive investigations, this is no longer considered necessary at this time. This accounts for the majority of the value engineering figure.
Further to the tender sum payable to the contractor, there will be a total of £9,518 in professional fees to the Mechanical Consultant who will oversee the works.
The additional budget required to complete the necessary works is £56,640. It is proposed to meet this cost by reallocating funding already within the capital programme which was originally set aside as a contingent sum for a capital project that was completed several years ago but where the final position has only just been concluded.
Risk If the ventilation system is not replaced, the environmental conditions in the pool hall will be unsuitable for customer access.
LEGAL The proposals are within the Council’s powers. The Request for allocation of additional budget is in accordance with the Budget and Policy Framework, as set out in Part 5 of the Council’s Constitution
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Joint Report of the Resources and Corporate Services Portfolio Holder and the Leisure and Partnerships Portfolio Holder: A.3: Clacton Leisure Centre Ventilation SystemReport
25Joint Report of the Resources and Corporate Services Portfolio Holder and the Leisure and Partnerships Portfolio Holder - A.3 - Clacton Leisure Centre Ventilation SystemThis decision
Joint Report of the Resources and Corporate Services Portfolio Holder and the Leisure and Partnerships Portfolio Holder - A.3 - Clacton Leisure Centre Ventilation SystemThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.