RESOLVED that – a) the Resources and Services Overview and Scrutiny Committee is thanked for the work it has done to date in reviewing the forecast as it has developed; b) the comments of the Finance and Corporate Resources Portfolio Holder in response to issues raised by the Resources and Services Overview and Scrutiny Committee be endorsed; c) the updated Financial Forecast 2019/20, as set out in item A.6 of the Report of the Finance and Corporate Resources Portfolio Holder and its accompanying Appendices, be approved and; d) the Resources and Services Overview and Scrutiny Committee’s comments on this latest financial forecast for 2019/20 be requested.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
Key Decision Required: Yes In the Forward Plan: Yes
CABINET
14 DECEMBER 2018
REPORT OF FINANCE AND CORPORATE RESOURCE PORTFOLIO HOLDER
A.6 UPDATED FINANCIAL FORECAST / BUDGET 2019/20 (Report prepared by Richard Barrett)
PART 1 – KEY INFORMATION
PURPOSE OF THE REPORT To enable Cabinet to consider the updated financial forecast for 2019/20 for consultation with the Resources and Services Overview and Scrutiny Committee.
EXECUTIVE SUMMARY As part of maintaining a ‘live’ forecast, further updates to the position for 2019/20 have been made since the financial forecast was last considered by Cabinet on 9 November 2018.
Changes to the in-year budget (2018/19) are not included within this report as they are now reported via the quarterly financial performance reports presented during the year.
At this stage of the budget process, there is a net surplus of £0.002m forecast in 2019/20, an overall change of £0.511m compared with the £0.509m deficit reported to Cabinet on 9 November 2018. The long term forecast therefore remains on target.
It is important to highlight that the 2019/20 budget includes an estimated collection fund surplus of £0.710m. Although this is an on-going item in the budget it is reviewed each year based on in-year collection performance and can therefore only be deemed a one- off ‘saving’ in 2019/20. Although the amount is available to support the 2019/20 budget, if this was excluded from the forecast, there would be a budget deficit of £0.708m for 2019/20.
Although subject to potential changes to the forecast over the remaining budget setting period, the current forecasted surplus of £0.002m will be paid into the Forecast Risk Fund.
Any necessary changes emerging from the detailed Local Government Finance Settlement will be reported directly at the meeting if received in-time, otherwise they will be included in the figures that will be presented to Cabinet in January 2019 when it considers the final budget proposals after consultation with the Resources and Services Overview and Scrutiny Committee.
Once the final position for 2019/20 is determined, the remaining years of the 10 year forecast will be revised, set against the revised 2019/20 position and will be reported to members later in the budget setting process. RECOMMENDATION(S) It is recommended that Cabinet:
a) Thanks the Resources and Services Overview and Scrutiny Committee for the work they have done to date in reviewing the forecast as it has developed and agrees the comments of the Finance and Corporate Resources Portfolio Holder in response to issues raised by the Committee as set out in this report;
b) agrees the updated Financial Forecast 2019/20 as set out in this report and Appendices and;
c) requests the Resources and Services Overview and Scrutiny Committee’s comments on this latest financial forecast for 2019/20.
PART 2 – IMPLICATIONS OF THE DECISION
DELIVERING PRIORITIES The forecasting and budget setting process will have direct implications for the Council's ability to deliver on its objectives and priorities. At its heart, the 10 year approach to the forecast seeks to establish a sound and sustainable budget year on year through maximising income whilst limiting reductions in services provided to residents, business and visitors.
FINANCE, OTHER RESOURCES AND RISK Finance and other resources The financial implications are set out in the body of the report.
Although the availability of financial resources is a key component in the delivery of services there will also need to be appropriate input of other resources such as staffing, assets and IT.
Risk There are significant risks associated with forecasting such as cost pressures, inflation and changes to other assumptions that form part of the financial planning process. There are a number of areas that could lead to additional expenditure being incurred, such as: -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.