Cabinet Members' Items - Report of the Corporate Finance and Governance Portfolio Holder - A.6 - Performance Report: July to September 2019 (Quarter 2)
ApprovedExecutive3 papers
Cabinet approved this item on Friday 8 November 2019. Below is the council's own wording, with the papers it was decided on.
RESOLVED that – (a) the deliverable and measurable outcomes that have been developed for the Priorities and Projects and incorporated into the Council’s Performance Report(s), be approved; and (b) the current position for each performance measure as at Quarter Two (July – September 2019) be noted.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
REPORT OF THE CORPORATE FINANCE & GOVERNANCE PORTFOLIO HOLDER
A.6 PERFORMANCE REPORT JULY – SEPTEMBER 2019 (QUARTER 2) (Report prepared by Anastasia Simpson & Katie Wilkins)
PART 1 – KEY INFORMATION
PURPOSE OF THE REPORT This report presents the deliverables and measurable outcomes for the Cabinet’s agreed Priorities and Projects 2019/20, as well as reporting the current position as at Quarter Two (July – September 2019).
EXECUTIVE SUMMARY The Performance Reports (Resources & Services & Community Leadership) set out the detailed actions and targets for the delivery of the Council’s priorities throughout the year.
Current Performance The Performance Report includes both the Council’s emerging Corporate Plan 2020/24 and Priorities and Projects 2019/20.
The Priorities and Projects for 2019/20 were approved by Cabinet at its meeting of the 19th July 2019. It was agreed that the next phase of this work would be to develop specific deliverables (for the priorities and projects) in consultation with the relevant Portfolio Holders and that these would be incorporated into the Performance Report(s) in line with the Quarter Two timetable and presented to Cabinet, so Cabinet can endorse the deliverables before they are subject to scrutiny.
Now the drafting process is complete, officers would like to submit the Performance Reporting Template(s), including the deliverables and measurable outcomes, to Cabinet for formal approval and adoption, as well as reporting the current position as at Quarter Two (July – September 2019).
The Quarter 2 position demonstrates that of the 22 indicators and projects where performance is measured, 19 (86%) are on, or above, their expected target, 1 (5%) is not currently in line with expected performance and 2 (9%) we currently have no data available. The indicators and projects highlighted in the Community Leadership report are deemed ‘non measurable’ as Tendring’s role is that of influence only.
The respective report/s will be presented to the Resources and Services Committee: 28 November 2019 and Community Leadership Committee: 2 December 2019.
TRANSFORMING TENDRING The transformation project continues to progress. Although there have been some areas of delay the new areas at Pier Avenue are occupied and the site draws nearer to completion. Initial cohorts of staff have been moving away from Weeley and the areas of the Town Hall that are nearing completion are significantly improved.
Pier Ave: Council Tax Building: Work on office elements, on the ground and first floors are complete. Work on the staircase and redecoration and carpeting on the second floor accommodation is being carried out in further stages but will not be completed until roofing work is finished. Nesting birds on the roof of the existing building and adverse weather delayed associated reroofing work of that building; full completion is now scheduled for October 2019.
Barnes House and Link: Construction work is now substantially complete and the areas are occupied. Some snagging and furnishing remains outstanding.
Northbourne Depot: Work to create offices is complete. Staff moved into the new offices on 25 March 19. Next stages are the provision of kennels and storage space for Environmental Services.
IT and Chanel Shift: Redesigning of the IT Network and move onto the cloud continues. Training on the new Firmsteps Interface and resolution of some teething issues is progressing well with the interface activated for two environmental functions and ready for activation once other service area applications are ready.
Westleigh House: On 31 July 19 the building and nearby public conveniences had been demolished. Existing car park areas and the site of the pubcons reverted to parking use in August 2019. Other surfacing work should be fully complete in November 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Cabinet Members' Items: Report of the Corporate Finance and Governance Portfolio Holder: A.6: Performance Report: July to September 2019 (Quarter 2)Report
71Cabinet Members' Items - Report of the Corporate Finance and Governance Portfolio Holder - A.6 - Performance Report: July to September 2019 (Quarter 2)This decision
Cabinet Members' Items - Report of the Corporate Finance and Governance Portfolio Holder - A.6 - Performance Report: July to September 2019 (Quarter 2)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.