RECOMMENDED TO COUNCIL that the final proposals for the Corporate Plan 2020/24, as set out in Appendix B to item A.1 of the Report of the Leader of the Council, be approved, subject to within the section headed “A Growing and Inclusive Economy” the aspiration “Maximise our seafront opportunities” being amended to read “Maximise our coastal and seafront opportunities”.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
A.1 A NEW CORPORATE PLAN 2020/24 (Report prepared by Martyn Knappett)
PART 1 – KEY INFORMATION
PURPOSE OF THE REPORT To seek Cabinet approval and recommendation to Full Council, the final proposals for the Corporate Plan 2020/24 following full consultation with key partners and stakeholders.
EXECUTIVE SUMMARY At its meeting on 13th September 2019, the Cabinet agreed the draft proposals for the Corporate Plan 2020/24 (as set out in Appendix A) as its initial proposals for consultation purposes.
The consultation process included; presentation to the two Overview and Scrutiny Committees (for consideration and comment back to Cabinet), and consultation with key partners (other Local Authorities, Parish and Town Councils) community representatives, local primary and secondary schools, members of the public and industry and business bodies. The feedback from the consultation process has been summarised within this report.
The Corporate Plan, final proposals continues to follow the principles which were previously agreed by the Cabinet, namely:-
A “Plan on a Page” With Community Leadership at its heart With other cross-cutting themes identified such as Tendring4Growth And with a clear statement of the Council’s overall vision and values.
However, following the consultation process and as part of working collaboratively, a number of consultees have requested that the *Future of Essex and the vision and ambitions this sets out, be included with Tendring’s final proposals. Therefore it is recommended within the Values section and working collaboratively that this section is expanded as follows:
Working collaboratively with partners, including supporting the Essex wide vision and ambitions.
The other key themes, remain as previously reported:
Delivering High Quality Services Community Leadership Through Partnerships Building Sustainable Communities for the Future Strong Finances and Governance A Growing and Inclusive Economy
There have also been some minor updates to the order of priorities within the Corporate Plan.
The Vision of the Council remains unchanged from the initial proposals. The previously agreed timetable for completion of the Corporate Plan still stands and seeks approval by Full Council in early 2020.
RECOMMENDATION(S)
It is recommended that Cabinet agree the final proposals for the Corporate Plan 2020/24 as set out in Appendix B and recommends them to Full Council for approval.
PART 2 – IMPLICATIONS OF THE DECISION
DELIVERING PRIORITIES The Corporate Plan sets out high level priorities for the Council 2020/24.
FINANCE, OTHER RESOURCES AND RISK There are no financial implications in setting out the Councils aspirations in a Corporate Plan. Individual projects still need to be fully and properly assessed and formally approved prior to commencing. One of the priorities from the LGA Peer Challenge carried out in 2018 was that an enhanced approach to project management, project delivery and performance reporting be brought into use. This will encompass a full assessment of resources and risk.
LEGAL The Corporate Plan forms part of the Council’s Policy Framework which means it must be approved by Full Council following a process involving both Cabinet and Overview and Scrutiny.
The legal implications of individual projects will be assessed when they are brought forward for formal decisions to be made.
OTHER IMPLICATIONS Consideration has been given to the implications of the proposed decision in respect of the following and any significant issues are set out below. Crime and Disorder / Equality and Diversity / Health Inequalities / Area or Ward affected / Consultation/Public Engagement. The implications of individual projects will need to be fully and properly assessed and approved prior to commencing. As with resources and risk assessment of other implications will be included as part of enhanced project delivery arrangements.
PART 3 – SUPPORTING INFORMATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.