RESOLVED that the Acting Assistant Director (Planning) (or equivalent authorised officer) be authorised to grant planning permission for the development, subject to: Conditions and Reasons: 1) The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason - To comply with the requirements of Section 91 of the Town and Country Planning Act 1990, as amended by the Planning and Compulsory Purchase Act 2004. 2) The development hereby permitted shall be carried out in accordance with the following approved plans:- 3447-PA-10, 3447-PA-11 and 3447-PA-12; received 5th February 2020. Reason - For the avoidance of doubt and in the interests of proper planning. 3) Notwithstanding the requirement that the development hereby permitted shall be begun before the expiration of three years from the date of this permission; no obstruction of the current Public Footpath (Footpath No. 23) can take place unless/until the diversion under Section 257 of the Town & Country Planning Act 1990 (the authorising of the diversion of any footpath) is successful. Reason - To ensure the continued safe passage of the public on the definitive right of way is maintained free and unobstructed at all times.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
1.1This application is referred to the Planning Committee as the applicant is Tendring District Council.
1.2The application involves a proposed single storey extension to the existing storage building, extended compound and relocation of footpath.
1.3The site is not allocated as Employment Land nor safeguarded for employment use in the Employment Land Review. Policy ER3 of the Tendring District Local Plan (2007) seeks to ensure that land in or allocated for employment use will normally be retained for that purpose. The use of the site will be retained for employment purposes. The principle of development is acceptable subject to the detailed consideration below.
1.4The proposal will not result in any material harm to residential amenity or highway safety and will result in a slight visual improvement.
Recommendation
That the Head of Planning be authorised to grant planning permission for the development subject to:-
Subject to the conditions stated in section 8.2
2. Planning Policy
2.1The following Local and National Planning Policies are relevant to this planning application.
National Policy:
NPPF National Planning Policy Framework February 2019
National Planning Practice Guidance
Local Policy:
Tendring District Local Plan 2007
QL9 Design of New Development
QL10 Designing New Development to Meet Functional Needs
QL11 Environmental Impacts and Compatibility of Uses TR4 Safeguarding and Improving Public Rights of Way
Tendring District Local Plan 2013-2033 and Beyond Publication Draft (June 2017)
SPL3 Sustainable Design
PP6 Employment Sites
Local Planning Guidance:
Essex Design Guide
Essex County Council Car Parking Standards - Design and Good Practice
Status of the Local Plan
2.2The ‘development plan’ for Tendring is the 2007 ‘adopted’ Local Plan. Paragraph 213 of the NPPF (2019) allows local planning authorities to give due weight to adopted albeit outdated policies according to their degree of consistency with the policies in the NPPF. Paragraph 48 of the NPPF also allows weight to be given to policies in emerging plans according to their stage of preparation, the extent to which there are unresolved objections to relevant policies and the degree of consistency with national policy. As of 16th June 2017, the emerging Local Plan for Tendring is the Tendring District Local Plan 2013-2033 and Beyond Publication Draft.
2.3Section 1 of the Local Plan (which sets out the strategy for growth across North Essex including Tendring, Colchester and Braintree) was examined in January and May 2018 and the Inspector’s initial findings were published in June 2018. They raise concerns, very specifically, about the three ‘Garden Communities’ proposed in north Essex along the A120 designed to deliver longer-term sustainable growth in the latter half of the plan period and beyond 2033. Further work is required to address the Inspector’s concerns and the North Essex Authorities are considering how best to proceed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.