Resolved
RESOLVED that the comments and recommendations of the Resources and Services Overview and Scrutiny Committee be noted and the comments of the Leisure & Tourism Portfolio Holder, in response thereto, be endorsed.
Cabinet noted this item on Friday 18 December 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the comments and recommendations of the Resources and Services Overview and Scrutiny Committee be noted and the comments of the Leisure & Tourism Portfolio Holder, in response thereto, be endorsed.
CABINET
18 DECEMBER 2020
REFERENCE REPORT FROM THE RESOURCES AND SERVICES OVERVIEW & SCRUTINY COMMITTEE
A.3 SCRUTINY OF THE LEISURE PROVISION BY THE COUNCIL IN THE DISTRICT (Report prepared by Keith Durran and Ian Ford)
BACKGROUND At the meeting of the Resources and Services Overview and Scrutiny Committee held on 21 September 2020 (Minute 87 refers) the Committee was provided with an overview of the Leisure Provision by the Council in the District.
The Committee was updated on a number of items on the Sport and Leisure work programme. The Assistant Director for Economic Growth and Leisure (Mike Carran) provided this background report.
UPDATES ON THE WORK PROGRAMME FOR THE COMMITTEE
a) The emerging District-wide Leisure Strategy as previously reported to it – progress with the development of the Strategy
Members were informed that the Sports Facilities Strategy had been due to be presented for consideration by Cabinet earlier in the year. One of the key focusses of that plan was a wholesale review of pricing and recommendations for a change in direction, based on an external review of the local fitness market and an evaluation of the number of the volume and value of pre-paid members. Due to the pandemic, that strategy had been postponed and was likely to be brought forward for consideration early in 2021.
b) The refurbishment of the Clacton Leisure Centre – to review arrangements for the refurbishment since they were last presented to the Committee.
The Committee heard that in July 2019, Cabinet had committed a budget for the refurbishment of the swimming pool changing rooms and health suite areas at Clacton Leisure Centre.
A tender process for those works was postponed earlier in the year due to the forced closure of the Sports Facilities. A full specification had been prepared by a specialist organisation acting on behalf of the Council and was then in a position to be advertised to prospective contractors. This Architectural Design and Contract Administration company would also act on behalf of the Council during the evaluation of tenders and throughout the construction phase.
Followed by the receipt and evaluation of the subsequent submissions, it was anticipated that the work would be undertaken at the end of the year, which was historically the quietest period. c) The sale of land to Clacton County High School, community access to the pitches on that land, management of that community access and the conditional works on the existing 3G pitches at the Leisure Centre – progress/timescales.
The Committee was informed that the transfer of land to Clacton County High School (CCHS) had yet to be concluded and the final agreements were not at that time, in place.
In anticipation of its conclusion however, agreement had been reached with the school and Essex County Council (ECC) on arrangements for community use.
Grass Pitch The grass pitch which was marked out on the ‘new’ school land, would remain available for community use outside of school hours. That would be booked through the same process as all other grass sports pitches under the management of the Council.
Artificial Grass Pitch Officers had been working with the Essex Football Association and the Football Foundation (FF) to develop a 3G strategy for the District. Essentially, a 3G pitch was artificial grass suitable for football. A refurbishment of the current sand filled pitch into a 3G was part of the agreement with ECC/CCHS.
Working with the FF opened the door to the potential of external funding and a planning application for the refurbishment of the Clacton Leisure Centre pitch had been submitted. That was an essential requirement prior to a funding application being submitted.
d) The refurbishment of the Skate Park at the Leisure Centre – plans and timescales.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Matters Referred to the Cabinet by a Committee: A.3: Scrutiny of the Leisure Provision by the Council in the DistrictReport | 212 KB | DownloadRead as text |
Follow Cabinet at Tendring and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.