RESOLVED that Cabinet – a) subject to Full Council agreeing to the allocation of funding, approves the project to stabilise the damaged cliff areas at Holland-on-Sea; b) subject to a) above, approves the inclusion of the cliff stabilisation scheme within the 2021/22 Capital Programme with a budget of £2.131m, to be funded by utilising £1.5m from the existing beach recharge reserve along with the £631k already set aside for this project; c) recommends to Full Council that it approves the use of the £1.5m beach recharge reserve to fully fund the proposed cliff stabilisation scheme; d) instructs officers to seek ways to generate external funding to offset cliff stabilisation costs; and e) approves on-going representations being made to Government in the light of recent experiences and the continuing, significant and financial challenges faced by the Council in this area.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
To seek Cabinet authority for a scheme of work to stabilise failed and failing cliffs at Holland on Sea.
To seek Cabinet’s recommendation to Council to use £1.5m currently held in reserves to support the overall funding of the proposed remedial works, which will stabilise approximately 200m of the cliff for the next 50 to 100 years and create new locations for approximately 30 new beach huts.
Separate decisions will be made in relation to the appointment of a contractor to carry out the work and seeking authority to appoint a specialist engineer to oversee the work.
Executive summary
Since February 2020, three areas of cliff in Holland-on-Sea have collapsed or been identified as likely to collapse. If the stability of these areas is not addressed the collapse will continue to progress putting at risk the public highway and infrastructure within it. Public services and amenity would be compromised.
The Council’s emerging Tourism Strategy sets out a 10 point plan, which includes development of the local seafront offer, with the coast being fundamental to the local visitor economy. Tourism is estimated to be worth more than £402 million to the District, and is responsible for over 8,980 jobs, equivalent to 17.9% of the District’s employment.
The securing of these cliff areas if in line with corporate priorities and criteria set out in the emerging Annual Capital and Treasury Strategy, specifically safeguarding assets reducing risks and seeking to limit future exposure to costs and liability.
Monitoring of the movement is continuing to take place. Design of remedial measures has been completed and tenders invited. At the time of writing tenders have been received within the allocated budget. Evaluation is ongoing and separate decisions will be made, subject to the funding decision of Full Council to appoint a contractor and an engineer to oversee the work. If no action is taken further collapse is likely which will expose the Council to significant reputational, financial and legal risk. The potential consequences of not addressing the matter are set out in the options appraisal and risk sections.
Tenders have been invited, received and assessed. The lowest tender is in the sum of £1,930,212.92. An allocation of funding in excess of this would be prudent to allow for contingencies and potentially increasing material costs, with a total budget of £2.131m therefore proposed.
That, subject to Cabinet’s approval of the proposed remedial works, that it is recommended to Full Council to utilise £1.5m from the existing beach recharge reserve to support the overall funding required to meet the cost set out above
The Council is responsible for around 16km of coastline including cliffs at Clacton, Holland, Frinton, Walton and Dovercourt. Although only three areas are subject to current slippage, all of the slopes are at relatively steep angles. Any future need to carry out structural repairs of these areas would be financially very challenging.
RECOMMENDATION(S)
That the Cabinet:
a) subject to Full Council agreeing to the allocation of funding, approves the project to stabilise the damaged cliff areas at Holland-on-Sea;
b) subject to a) above, approves the inclusion of the cliff stabilisation scheme within the 2021/22 Capital Programme with a budget of £2.131m, to be funded by utilising £1.5m from the existing beach recharge reserve along with the £631k already set aside for this project;
c) that subject to a) and b) above, recommends to Full Council to approve the use of the £1.5m beach recharge reserve to fully fund the proposed cliff stabilisation scheme;
d) instructs officers to seek ways to generate external funding to offset cliff stabilisation costs; and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Cabinet Members' Items: Report of the Corporate Finance and Governance Portfolio Holder: A.2: Clacton and Holland-on-Sea Cliff Stabilisation: Phase 2Report
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.