Resolved
RESOLVED that the recommendations made by the Resources and Services Overview & Scrutiny Committee be noted and that the response of the Leisure & Tourism Portfolio Holder thereto be endorsed.
Cabinet noted this item on Friday 12 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the recommendations made by the Resources and Services Overview & Scrutiny Committee be noted and that the response of the Leisure & Tourism Portfolio Holder thereto be endorsed.
CABINET
12 NOVEMBER 2021
REFERENCE REPORT FROM THE RESOURCES AND SERVICES OVERVIEW & SCRUTINY COMMITTEE
A.2 SCRUTINY OF THE COUNCIL’S SEAFRONTS SERVICES (Report prepared by Keith Durran)
BACKGROUND At its meeting held on 20 September 2021 (Minute 23 refers), the Resources and Services Overview & Scrutiny Committee (“the Committee”) scrutinised the Council’s Seafronts Services.
The Committee heard how in 2014 the Council had instigated a £36 million coastal defence project stretching from Clacton Pier to Holland-on-Sea in partnership with the Environment Agency. Not only had that protected the coastline, it had led to the creation of 23 new sand beaches which had provided a major opportunity for tourism development.
The Committee also heard that in 2016 the pre-construction phase had started to stabilise the cliff between Hazelmere Road and Queensway. This phase had consisted of ground investigations, numerous surveys, obtaining planning permission, producing detailed designs, producing tender documents, obtaining tenders, and appointing a contractor in line with the Council’s procurement policy. The construction of the project had commenced on 28 August 2018 and had been completed on 28 June 2019 at a cost of £4.3 million. The project had stabilised a 500m length of coastal slopes by temporarily removing 83 beach huts, excavating to construct a new piled slope retaining wall and new steel piled retaining wall at the base of the slope to provide a stable shelf for the beach huts to be returned. The scheme had also included new drainage and a Equality Act compliant ramp from the top promenade to the lower promenade.
The scheme had been first identified in the Clacton & Holland Geomorphological Assessment and Conceptual report 2015 produced by Mott MacDonald. The report had identified the areas that were most at risk of failure between Clacton Pier and Holland Haven. The report had also suggested a detailed slope stability study of the cliffs to be carried out at a cost of £225,000. Based on that estimate the suggested cost to carry out detailed slope stability studies on all of the cliffs the Council was responsible for would be approximately £700,000.
With the assistance of the Assistant Director (Building & Public Realm) and [name removed] of Hestur Limited (the Council’s contractor for the current cliff stabilisation works), the Committee considered the risk factors for the cliffs in the area and the measures to reduce the risks and otherwise undertake works to stabilise the cliffs for the future. The aim would be to achieve cliffs with a sustainable factor of safety of 1.0. [name removed] advised that neighbouring cliffs to those currently being stabilised could fail with a marginal deterioration of the factor of safety.
The works being undertaken used techniques to reduce vibration and therefore did not themselves cause the factor of safety to deterioate in those neighbouring cliffs. He also advised that the current stabilisation works could be completed by December 2021 (although it had provided for them to be completed by March 2022 to allow for adverse weather impacts). The Assistant Director (Building & Public Realm) referred to an initial visual overview of the slopes from the Pier to Holland Haven that had confirmed that some were at more risk of failure and the bowed railings and cracked promenade in places were some of the indicators of this. He further advised that the original pitch-fibre drainage system was still in place in the cliffs although its effectiveness had likely deteriorated.
RESOURCES AND SERVICES OVERVIEW & SCRUTINY COMMITTEE’S RECOMMENDATIONS TO CABINET After a detailed discussion the Committee had RECOMMENDED to Cabinet that:
a) where observation reveals cliff slippages, all communication with Beach Hut Licensees in respect of Cliff Stabilisation and safety, is consistently shared with the relevant District Ward Councillors; and
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Matters Referred to the Cabinet by a Committee: Reference from the Resources and Services Overview & Scrutiny Committee: A.2: Scrutiny of the Council's Seafront ServicesReport | 178 KB | DownloadRead as text |
Follow Cabinet at Tendring and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.