Cabinet Members' Items - Joint Report of the Business & Economic Growth Portfolio Holder and the Housing Portfolio Holder - A.6 - Jaywick Sands Covered Market and Managed Workspace
AgreedExecutive2 papers
Cabinet agreed this item on Friday 28 January 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED that, in the event that this Council (TDC) is successful in its pursuit of external funding to meet the shortfall in the Jaywick Workspace and Covered Market project, Cabinet - (1) authorises the Chief Executive, in consultation with the Portfolio Holder for Housing and the Portfolio Holder for Business and Economic Growth and the Council’s Section 151 Officer and the Monitoring Officer, to enter into the necessary Funding Agreement; (2) agrees that the Housing Revenue Account Capital Programme be increased by £1,934,647 to £4,407,000 to be funded by a TDC contribution of £254,465 from the 2022/23 New Homes Bonus and external funding of £1,680,182; and (3) notes that, in that eventuality, the Council will proceed to award the contract to construct the Jaywick Workspace and Covered Market project.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
Key Decision Required: Yes In the Forward Plan: Yes
CABINET
28 JANUARY 2022
JOINT REPORT OF THE PORTFOLIO HOLDER FOR BUSINESS & ECONOMIC GROWTH AND THE PORTFOLIO HOLDER FOR HOUSING
A.6 JAYWICK SANDS COVERED MARKET AND MANAGED WORKSPACE (Report prepared by Lee Heley, Interim Corporate Director (Project Delivery)
PART 1 – KEY INFORMATION
PURPOSE OF THE REPORT For Cabinet to allocate a further £254,465 from Tendring District Council New Homes Bonus to the Jaywick Sands Covered Market and Managed Workspace Project given the recent significant increase in construction costs demonstrated by tender returns.
To seek further external funding from partners and enter into agreement with them to meet the remaining gap in funding for the project. Depending on the success of the effort to source sufficient funds, the Council will enter into contract with a construction firm to deliver the project.
EXECUTIVE SUMMARY Cabinet last received an update on the Jaywick Sands Covered Market and Workspace at its meeting in October 2021, and agreed to grant an exemption to the Council’s procurement rules to allow a direct award of a service contract for management of the facility and business support service to the Council’s’ operating partner, agreeing that that a licence to occupy would enable the most effective project delivery.
The October 2021 Cabinet report noted that construction material costs have been seen to increase as the country unlocks and once tender prices come in for construction there is a potential risk that this budget is insufficient to deliver the project as planned. Cabinet was informed it would be updated with options if the increase in prices occurs, seeking any necessary approvals.
Since that date the tender process for the construction of the facility has been undertaken by the Council with its Professional Team: HAT Projects (Architects), Potter Raper (Cost Consultants) and Daniel Connal Partnership (Construction, Design and Management Consultants). On 3 December 2021 the Council’s cost consultants Potter Raper produced a revised cost appraisal based on the Council’s tender pack and the latest market information on the cost of materials. This work indicated that the total construction cost of the scheme had likely increased from £2.1m to at least £2.7m.
On 6 December 2021 the Council received tenders from building contractors as part of the Council’s procurement exercise, which came in significantly above the budget, with the lowest tender after value engineering at £3,877,239, over £1.1m greater than the cost consultant’s recent estimate. This gives a total scheme value of £4,407,182, which is £1.98m over the total budget currently allocated of £2,427,000 to secure delivery. As part of the evaluation process, Potter Raper were asked to examine and comment on the large discrepancy between their latest cost advice and the prices quoted in the three submitted tenders. It is considered likely that contractors have sought to reduce their risk by cushioning current volatile market prices against materials cost inflation during the nine month delivery phase. It is noted that while the three tenders are significantly higher than the most recent cost estimates, the three returns all fell within about seven percent of each other, demonstrating that this range is the price necessary to complete the work in current market conditions.
One option would be to end the project at this point and not draw down the funding. However the economic benefits of the project for Jaywick Sands would not be realised, with the jobs and businesses not attracted to the location. In addition, the wider regeneration of Jaywick Sands linked to the Place Plan would be stalled, and sunk costs in the project of around £300,000 would need to be covered, with no output.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Cabinet Members' Items: Joint Report of the Business & Economic Growth Portfolio Holder and the Housing Portfolio Holder: A.6: Jaywick Sands Covered Market and Managed WorkspaceReport
121Cabinet Members' Items - Joint Report of the Business & Economic Growth Portfolio Holder and the Housing Portfolio Holder - A.6 - Jaywick Sands Covered Market and Managed WorkspaceThis decision
Cabinet Members' Items - Joint Report of the Business & Economic Growth Portfolio Holder and the Housing Portfolio Holder - A.6 - Jaywick Sands Covered Market and Managed WorkspaceThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.