CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tendring District Council
Cabinet, Friday 23 June 2023 at 10.30am

Matters Referred to the Cabinet by a Committee - Reference from the Resources and Services Overview & Scrutiny Committee - A.2 - Scrutiny of Procurement and Contract Management

Decided Executive 1 paper

Cabinet decided this item on Friday 23 June 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED that the recommendations made by the Resources and Services Overview & Scrutiny Committee be considered and that the response of the Assets Portfolio Holder thereto be endorsed.
Word for word from the decision Tendring published for this meeting. Source: tdcdemocracy.tendringdc.gov.uk

Follow this further

Built from Tendring's papers

What the report saysPro

Report to Cabinet

CABINET

23 JUNE 2023

REFERENCE REPORT FROM THE RESOURCES AND SERVICES OVERVIEW & SCRUTINY COMMITTEE

A.2 SCRUTINY OF PROCURMENT & CONTRACT MANAGMENT (Report prepared by Keith Durran)

BACKGROUND On 13 March 2023 the Resources and Services Overview & Scrutiny Committee (“the Committee”) received a report that detailed the outcome of the informal review of procurement and contract management at the Council to ensure that it was functioning as it should and was fit for purpose.

The Members heard from Lisa Hastings, Deputy Chief Executive & Assistant Director for Governance and lead officer for the topic who presented her report. The report outlined that informal meetings of the Committee had been held on 17 October and 7 December 2022, when Members had received a range of information around the subject of Council Procurement and Contract Management. Senior Officers across the Council, involved in the subject area and the specific contracts referred to within the scope of the review had supported the first informal meeting in October.

Members also heard that Full Council, at its meeting held on 12th July 2022 agreed (Minute 29) had approved the Committee’s Work Programme for the 2022-23 Municipal Year, that had included, inter alia:

Council procurement and Contract Management – using potential exemplars from:

 “The housing maintenance contract awarded to Rapid, its delivery of work and the management of it.  The management of the previous cremator maintenance contract, the need to stop the use of those cremators and the process for securing replacement cremators given the sensitivity around this service and the budgetary implications for the Council while these cremators are out of action.  The Leisure Centre Investment – specifications, securing contractors and delivery of those works and maintenance of the equipment at the Centres”.

It was reported to the Committee that the Procurement Team consisted of 2 FTE posts, both of which were currently vacant (that had been increased through the restructure in 2022 by 3 additional posts, all of which also remained vacant – see below). The budget for the service consisted of salaries and £22,670 for computer software. At its meeting held on 17th September 2021, Cabinet had considered in Section 2 of its Financial Performance Update 2021/22 a small number of in-year budget adjustments to the Portfolio Holder’s report, one of which had reflected a proposed service level agreement being entered into with Essex County Council (ECC) to enable this Council to ‘buy in’ procurement services from them.

The report had outlined that, following the last vacancy, discussions had commenced with ECC in terms of a shared service / collaborative approach as a way of providing a more comprehensive procurement service to the Council’s internal departments. This approach would involve the Council purchasing a range of procurement services from ECC on a proposed ‘hourly rate’ basis via a service level agreement. Appendix B to the Cabinet Report had set out a proposed adjustment, which would see budgets transferred from direct employee costs to ‘contract’ payments to ECC. That approach would also support the accelerated delivery programme whereby the Council would have access to specialist / expert advice along with additional procurement capacity e.g. supporting the procurement of replacement cremators. That arrangement would be kept under wider review as it could form part of a longer-term solution, whereby the Council could continue to have access to such advice as part of the future delivery of projects and activities along with the ‘usual’ operational requirements expected of a procurement function / service.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Matters Referred to the Cabinet by a Committee: Reference from the Resources and Services Overview & Scrutiny Committee: A.2: Scrutiny of Procurement and Contract ManagementReport 43 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 24 attended
MS
Councillor Mark StephensonChairman, present
IH
Councillor Ivan HendersonCommittee Member, present
AB
Councillor Andy BakerCommittee Member, present
MB
Councillor Mick BarryCommittee Member, present
MB
Councillor Michael BushCommittee Member, present
PK
Councillor Peter KotzCommittee Member, present
GP
Councillor Gina PlaceyCommittee Member, present
JC
Councillor Jayne Chapman BEMSpokesperson, apologies, sent representative (business duties)
CG
Councillor Carlo GuglielmiSpokesperson, apologies, sent representative (council duties)
PH
Councillor Paul HoneywoodSpokesperson, in attendance
GS
Councillor Gary ScottSpokesperson, in attendance
GS
Councillor Graham SteadySpokesperson, in attendance

All 24 on the meeting page

On this subject at Tendring

Search all
  1. Matters Referred to the Cabinet by a Committee - Reference from the Resources and Services Overview & Scrutiny Committee - A.2 - Scrutiny of Procurement and Contract ManagementThis decision
  2. Matters Referred to the Cabinet by a Committee - Reference from the Planning Policy & Local Plan Committee - A.1 - Adoption of the Revised Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS)Approved
  3. Matters Referred to the Cabinet by a Committee - Reference from the Community Leadership Overview & Scrutiny Committee - A.1 - Grant Funding by the Council and others and its appropriateness given the needs of the DistrictNoted
  4. Matters Referred to the Cabinet by a Committee - Reference from the Community Leadership Overview & Scrutiny Committee - A.2 - The Council's Youth Provision for School Aged Children Task & Finish Group - Their Final Report and Committee Recommendations to CabinetNoted
  5. Matters Referred to the Cabinet by a Committee - Reference from the Community Leadership Overview & Scrutiny Committee - A.3 - Konectbus Attendance at the Community Leadership Overview and Scrutiny Committee MeetingNoted
  6. Matters Referred to the Cabinet by a Committee - Reference from the Licensing and Registration Committee - A.4 - Charitable Collections PolicyApproved

More from Tendring Cabinet

All decisions
MeetingDecisionOutcome
13 Nov 2026 Minutes of the Last MeetingRESOLVED that the minutes of the meeting of the Cabinet, held on Friday 23 October 2026, be approved as a correct rec... Approved Open
13 Nov 2026 Cabinet Members' Items - Report of the Portfolio Holder for Corporate Finance & Governance - A.1 - Financial Performance Report 2026/27 - General Update at the end of September 2026RESOLVED that Cabinet – (a) notes the Council’s in-year financial position as at the end of September 2026; (b) appro... Approved Open
13 Nov 2026 Cabinet Members' Items - Report of the Corporate Finance & Governance Portfolio Holder - A.2 - The Local Council Tax Support Scheme, Discretionary Council Tax Exemptions / Discounts / Premiums for 2027/28 and Annual Minimum Revenue Provision Policy Statement 2027/28RESOLVED that Cabinet – a) agrees that the underlying LCTS scheme for 2027/28 remains the same as the current year, a... Agreed Open
13 Nov 2026 Cabinet Members' Items - Report of the Housing & Planning Portfolio Holder - A.3 - Annual Housing Improvement, Performance & Assurance Report 2025/26RESOLVED that Cabinet – (a) notes the contents of the Annual Housing Improvement, Performance & Assurance Report 2025... Decided Open
13 Nov 2026 Cabinet Members' Items - Report of the Housing & Planning Portfolio Holder - A.4 - Adoption of the Conservation Area Character Appraisals and Management Plans for St Osyth and Manningtree & MistleyRESOLVED that – (a) the outcome of the public consultation exercises summarised in this report (A.4) be noted; and (b... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies