Resolved
RESOLVED that the recommendations made by the Resources and Services Overview & Scrutiny Committee be considered and that the response of the Assets Portfolio Holder thereto be endorsed.
Cabinet decided this item on Friday 23 June 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the recommendations made by the Resources and Services Overview & Scrutiny Committee be considered and that the response of the Assets Portfolio Holder thereto be endorsed.
CABINET
23 JUNE 2023
REFERENCE REPORT FROM THE RESOURCES AND SERVICES OVERVIEW & SCRUTINY COMMITTEE
A.2 SCRUTINY OF PROCURMENT & CONTRACT MANAGMENT (Report prepared by Keith Durran)
BACKGROUND On 13 March 2023 the Resources and Services Overview & Scrutiny Committee (“the Committee”) received a report that detailed the outcome of the informal review of procurement and contract management at the Council to ensure that it was functioning as it should and was fit for purpose.
The Members heard from Lisa Hastings, Deputy Chief Executive & Assistant Director for Governance and lead officer for the topic who presented her report. The report outlined that informal meetings of the Committee had been held on 17 October and 7 December 2022, when Members had received a range of information around the subject of Council Procurement and Contract Management. Senior Officers across the Council, involved in the subject area and the specific contracts referred to within the scope of the review had supported the first informal meeting in October.
Members also heard that Full Council, at its meeting held on 12th July 2022 agreed (Minute 29) had approved the Committee’s Work Programme for the 2022-23 Municipal Year, that had included, inter alia:
Council procurement and Contract Management – using potential exemplars from:
“The housing maintenance contract awarded to Rapid, its delivery of work and the management of it. The management of the previous cremator maintenance contract, the need to stop the use of those cremators and the process for securing replacement cremators given the sensitivity around this service and the budgetary implications for the Council while these cremators are out of action. The Leisure Centre Investment – specifications, securing contractors and delivery of those works and maintenance of the equipment at the Centres”.
It was reported to the Committee that the Procurement Team consisted of 2 FTE posts, both of which were currently vacant (that had been increased through the restructure in 2022 by 3 additional posts, all of which also remained vacant – see below). The budget for the service consisted of salaries and £22,670 for computer software. At its meeting held on 17th September 2021, Cabinet had considered in Section 2 of its Financial Performance Update 2021/22 a small number of in-year budget adjustments to the Portfolio Holder’s report, one of which had reflected a proposed service level agreement being entered into with Essex County Council (ECC) to enable this Council to ‘buy in’ procurement services from them.
The report had outlined that, following the last vacancy, discussions had commenced with ECC in terms of a shared service / collaborative approach as a way of providing a more comprehensive procurement service to the Council’s internal departments. This approach would involve the Council purchasing a range of procurement services from ECC on a proposed ‘hourly rate’ basis via a service level agreement. Appendix B to the Cabinet Report had set out a proposed adjustment, which would see budgets transferred from direct employee costs to ‘contract’ payments to ECC. That approach would also support the accelerated delivery programme whereby the Council would have access to specialist / expert advice along with additional procurement capacity e.g. supporting the procurement of replacement cremators. That arrangement would be kept under wider review as it could form part of a longer-term solution, whereby the Council could continue to have access to such advice as part of the future delivery of projects and activities along with the ‘usual’ operational requirements expected of a procurement function / service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Matters Referred to the Cabinet by a Committee: Reference from the Resources and Services Overview & Scrutiny Committee: A.2: Scrutiny of Procurement and Contract ManagementReport | 43 KB | DownloadRead as text |
Follow Cabinet at Tendring and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.