Written from the decision and the officer reportPDF Pro
OutcomeApprovedAuthorise Head of Planning to grant permission
MoneyNo S106 requirements
What happens nextPermission to be issuedSubject to conditions including lighting scheme
Who it affectsClacton Leisure Centre site usersLocal sports groups and community
What was decided
The Head of Planning and Building Control was authorised to grant planning permission for the construction of a floodlit Football Foundation Playzone on part of the redundant games courts at Clacton Leisure Centre. Report 1.1, 9.1
An additional condition was added requiring a lighting scheme to be approved and thereafter maintained, on top of the conditions set out at paragraph 9.2 of the officer report.
No Section 106 planning obligations were required as part of the approval. Report 9.1
Why
The proposal is considered an improvement over the existing rundown sports court, expanding accessible sports and recreation facilities, with no significant harmful impacts identified on character, residential amenity, highways, trees, or ecology. Report 1.1, 7.8, 7.14, 7.20, 8.1
Sport England raised no objection, finding the proposal meets Exception 5 of its Playing Fields Policy and paragraph 104 of the NPPF, providing sports development benefits on redundant games courts. Report P28, 7.9
Essex County Council Highways and the Council's Environmental Protection team raised no objection, subject to conditions on construction hours, lighting design, and on-site loading arrangements. Report P24, P25, P34, 7.22
What happens next
The Head of Planning and Building Control will issue the planning permission with the conditions listed in paragraph 9.2, as varied for enforceability, plus the added lighting scheme condition. Report 9.1, P91
The development must commence within three years of the date of permission, with construction vehicle movements restricted to 07:30 to 19:00 and working hours limited to 08:00 to 18:00 weekdays and Saturdays. Report P94, P109
The approved floodlights may only operate between 8am and 10pm, and must be designed and directed to avoid light pollution, residential intrusion, and traffic hazards. Report P112
Options considered
Chosen: Approve the application subject to conditions, including an added lighting scheme condition. Proposal acceptable in principle and detail, with no significant harmful impacts and no objections from statutory consultees. Report 1.1, 8.1, 9.1
Rejected: Refuse the application. Officers found no material harm to character, amenity, highways, trees, or ecology, and both Sport England and ECC Highways raised no objection. Report 7.14, 7.20, P24, P28, 8.1
Implications
Equalities: Officers assessed the public sector equality duty and found no disproportionate adverse impacts on protected characteristics; the proposal is expected to be neutral across all groups assessed. Report 10.3, P130
Legal: Officers considered the Human Rights Act 1998 and concluded the recommendation to grant is a proportionate response that does not interfere with residents' Article 8 or Article 14 rights. Report 10.4, 10.5, 10.6
Environmental: An informative encourages biodiversity enhancements through additional planting and wildlife friendly features, though statutory Biodiversity Net Gain does not apply as the proposal replaces an existing structure. Report P82, P117, P118
Other: A group of poor-quality self-sown Sycamore and Ash trees will be removed, with minor works to a Norway Maple; no other trees will be adversely affected. Report P39, P40, P42
Who and where
Users of Clacton Leisure Centre and the local community, including lower socio-economic groups, women and girls, disabled people, ethnically diverse communities, and people with long-term health conditions prioritised by the Football Foundation Report P30
Residents of nearby properties to the south and west of the site Report 7.20, 7.21
Users of Public Footpath No. 23 (Great Clacton) running to the west of the site Report 7.12, P26, P121
Local football and basketball clubs and groups seeking evening bookable access Report P30
Timeline
06.02.2025: Application 24/01596/FUL approved for CCTV columns and cameras under the Clacton on Sea Safer Streets Scheme Report P19
09.03.2026: Sport England consulted and raised no objection Report P28
12.03.2026: Advertisement consent 26/00074/ADV approved for 13 signs for the Football Foundation Playzone Report P20
16.03.2026: Essex County Council Highways consulted and raised no objection subject to conditions Report P24
26.03.2026: Environmental Protection team consulted and recommended construction hours and lighting conditions Report P34
30.03.2026: Tree and Landscape Officer consulted and raised no objection Report P38
Within three years of the date of permission: Development must commence or the permission will lapse Report P94
Daily 08:30 to 22:00 Monday to Friday and 08:30 to 18:00 Saturday and Sunday: Playzone opening hours once operational
Daily 08:00 to 22:00: Permitted operating hours for the approved floodlights Report P112
Plain English for the jargon
Playzone: A Football Foundation multi-use sports facility, in this case designed principally for football and basketball with floodlighting and perimeter fencing.
MUGA: Multi-Use Games Area, a fenced outdoor court surfaced for several sports.
BNG (Biodiversity Net Gain): An approach requiring development to leave the natural environment in a measurably better state; not applicable here as the proposal replaces an existing structure.
S106: A Section 106 legal agreement under the Town and Country Planning Act 1990 used to secure planning obligations; none required for this application.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item79
Resolved
RESOLVED that:- 1) the Head of Planning and Building Control be authorised to grant planning permission subject to the conditions as stated at paragraph 9.2 of the Officer report (A.3), with an added condition requiring a lighting scheme to be approved and thereafter maintained, or varied as is necessary to ensure the wording is enforceable, precise, and reasonable in all other respects, including appropriate updates, so long as the principle of the conditions as referenced is retained; and 2) the sending to the applicant of the informative notes as may be deemed necessary. </AI7>
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
1.1The proposal seeks permission for a new floodlit Football Foundation Playzone on part of the redundant games courts at Clacton Leisure Centre. The development is considered acceptable in principle and detail, representing a visual and functional improvement to existing facilities with no significant harmful impacts identified.
2. Status of the Local Plan
Planning Policy Context
2.1Planning law requires that decisions on applications must be taken in accordance with the development plan unless there are material considerations that indicate otherwise (Section 70(2) of the 1990 Town and Country Planning Act and Section 38(6) of the Planning and Compulsory Purchase Act 2004). This is set out in Paragraph 2 of the National Planning Policy Framework (the Framework). The ‘development plan’ for Tendring comprises, in part, Sections 1 and 2 of the Tendring District Local Plan 2013-33 and Beyond (adopted January 2021 and January 2022, respectively), supported by our suite of evidence base core documents (https://www.tendringdc.uk/content/evidence-base) together with any Neighbourhood Plans that have been made and the Minerals and Waste Local Plans adopted by Essex County Council.
Neighbourhood Plans
2.2At the time of writing, there are no draft or adopted neighbourhood plans relevant to this site.
3. Planning Policy
3.1The following Local and National Planning Policies are relevant to this planning application.
National: National Planning Policy Framework 2024 (NPPF) National Planning Practice Guidance (NPPG)
Local: Tendring District Local Plan 2013-2033 and Beyond North Essex Authorities' Shared Strategic Section 1 (adopted January 2021) SP 1 Presumption in Favour of Sustainable Development SP 3 Spatial Strategy for North Essex SP 7 Place Shaping Principles
Tendring District Local Plan 2013-2033 and Beyond Section 2 (adopted January 2022) SPL1 Managing Growth SPL2 Settlement Development Boundaries SPL3 Sustainable Design HP1 Improving Health and Wellbeing HP2 Community Facilities HP3 Green Infrastructure HP4 Safeguarded Open Space PPL4 Biodiversity and Geodiversity PPL5 Water Conservation, Drainage and Sewerage PPL10 Renewable Energy Generation and Energy efficiency Measures CP1 Sustainable Transport and Accessibility
79Report of the Corporate Director (Planning & Community) - A.3 - 26-00075-FUL – Clacton Leisure Centre, Vista Road, Clacton-on-Sea, CO15 6DBThis decision
Report of the Corporate Director (Planning & Community) - A.3 - 26-00075-FUL – Clacton Leisure Centre, Vista Road, Clacton-on-Sea, CO15 6DBThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.