Tendring District Council
Cabinet, Friday 26 June 2026 at 10.30am

Cabinet Members' Items - Report of the Economic Growth, Regeneration and Tourism Portfolio Holder - A.3 - Local Regeneration Fund (LRF) - Milton Road and Victoria Street: Progress Update

Agreed Executive 1 paper

AI summaryTendring District Council Cabinet noted progress on the Homes for Dovercourt scheme, confirming a preferred bidder for the £3.798m project to refurbish Milton Road car park and build eight affordable homes on Victoria Street, with a Pre-Construction Services Agreement to be signed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet notes progress, supports PCSA progression
Money£3.798mTotal approved Homes for Dovercourt budget
What happens nextPCSA award July 2026Final contract sum expected September 2026
Who it affectsHarwich & Kingsway WardDovercourt residents, future housing tenants

What was decided

Cabinet noted and welcomed progress on the second procurement exercise, which identified a preferred bidder, applying lessons from the earlier unsuccessful tender. Report P12

Cabinet confirmed Milton Road will stay as public car parking and the Victoria Street sites will stay as housing within the Housing Revenue Account, with no current intention to appropriate or dispose of any of the sites. Report P13

Cabinet supported moving to the next stage by entering a Pre-Construction Services Agreement with the preferred bidder under existing delegated authority. Report P14

Why

The PCSA lets the Council and contractor refine the design, test buildability, manage risk and develop a robust contract sum before main works award. Report P15, P7

The preferred bidder's price sits within the £3.798m budget with a 10 per cent contingency, and the initial 2025 tender was not viable. Report P10, P15, P35

All MHCLG funding must be spent by the end of March 2028, so the Council needs to keep the programme moving. Report P27, P80

What happens next

The Corporate Director for Place and Wellbeing will sign the PCSA using delegated authority, in consultation with Portfolio Holders. Report P6

A final construction price is expected in September 2026 and, if within budget, will go to a further officer decision in consultation with Portfolio Holders. Report P7, P55

Milton Road car park is due to reopen in June 2027, Victoria Street housing to complete in October 2027, and first residents to move in by December 2027. Report P55

The money

  • £3,798,751 Total approved project budget for Homes for Dovercourt Report P38, P41
  • £3,332,251 Total request to Capital Regeneration Project (CRP) Report P36
  • £466,500 Match funding contribution provided by Tendring District Council Report P37
  • £2,148,421 Combined funding allocated by Cabinet in 2023 to commission the project team and design work Report P39
  • £2.79m Targeted main contract sum (excluding VAT) Report P29
  • £69,300 Fixed cost of the Pre-Construction Services Agreement stage (excluding VAT) Report P9, P29
  • £69,291.87 Cost of entering into the PCSA, funded from the approved project budget Report P42
  • £600,859 Amount spent to date as at June 2026 Report P41
  • £102,538 Additional capitalisation forecast to completion Report P41
  • £3.095m Remaining budget against the total project budget Report P41
  • £1.04m Estimated nominal social value of the contractor's offer Report P4, P64
  • c.£970,000 Commitment to local supply chain spend, including £89,000 with SMEs Report P4, P63
  • £40,000 MHCLG salary contribution to the Council's internal project manager, administered by the Improvement and Development Agency Report P41

Options considered

  • Rejected: Do nothing. Would risk loss of MHCLG funding and delivery failure Report P16
  • Rejected: Do not award the contract. Would delay or prevent delivery Report P16
  • Rejected: Do not award the contract at this time. Would risk the funding because all Local Regeneration Fund must be spent by March 2028 Report P16
  • Rejected: Undertake a further procurement exercise. Unlikely to improve outcome given current market response and would risk programme delay Report P16

Implications

  • Financial: PCSA cost of £69,291.87 will be funded from the approved £3.798m project budget, with a 10 per cent contingency held within the budget as a buffer. Report P10, P42
  • Financial: One remaining risk is that the contract value is relatively high compared with the preferred bidder's last reported turnover, which will be monitored through the PCSA stage. Report P45
  • Legal: Both works and services fall under the thresholds in the Procurement Act 2023, so Part 6 PA23 applies; procurement has been carried out in line with Part 2 and Part 6 of the Act and the Council's Procurement Procedure Rules. Report P29, P20
  • Legal: A formal application has been lodged at the Land Registry seeking registration of title in the Council's favour for 20 Victoria Street; correspondence continues and the position is unchanged from previous reports. Report P28
  • Legal: Subsidy Control: a compliant competitive procurement exercise has been undertaken under the Subsidy Control Act 2022. Report P73
  • Climate: The scheme supports the Council's Net Zero by 2050 aim, with electric vehicle charging at Milton Road, low carbon housing design and sustainable materials to be developed during the PCSA stage. Report P69, P70
  • Risk: Top risks include cost escalation from inflation, unknown ground conditions, programme delays, planning variations, coordination with other projects and Network Rail delays; mitigations are tracked monthly through the Regeneration Capital Delivery Board. Report P57, P58
  • Other: Contractual provisions including assignment and novation clauses will be incorporated to enable transfer of contractual responsibilities to any successor authority under Local Government Reorganisation. Report P65, P66, P67

Who and where

  • Residents of Harwich and Kingsway Ward, Dovercourt Report P74
  • Future tenants of eight new affordable social rented homes on Victoria Street, to be managed within the Housing Revenue Account Report P3, P32
  • Users of Milton Road public car park once it reopens Report P3, P13
  • Local supply chain, including SMEs, with c.£970,000 of committed local spend Report P4, P63
  • People taking up four local employment opportunities and 52 apprenticeship weeks plus student placements Report P4, P63
  • Neighbouring properties of 20 Victoria Street affected by Rights of Light survey and party wall works Report P60

Timeline

  • February to April 2025: RIBA Stage 3 design completed and planning permission secured for both sites Report P5, P76
  • August 2025: Portfolio Holder approved revised procurement strategy, switching to a two-stage approach Report P78, P82
  • September 2025 to January 2026: Initial tender exercise returned no viable outcome Report P35
  • March 2026: Cabinet approved revised procurement approach and next steps Report P82
  • 28 April 2026: Proposed decision published in the Notice of forthcoming decisions Report P27
  • April to May 2026: Second procurement exercise: 13 submissions received, 12 compliant, preferred bidder identified Report P5, P23
  • 26 June 2026: Cabinet considered the progress update and supported the PCSA
  • July 2026: PCSA award expected Report P55
  • September 2026: Final contract sum agreed, main works contract awarded, mobilisation and site setup begin Report P7, P55
  • June 2027: Milton Road car park completes and reopens to the public Report P55
  • October 2027: Practical completion of Victoria Street housing and the overall scheme Report P55
  • December 2027: First residents move into the new homes (eight weeks after practical completion) Report P55
  • by March 2028: Final account agreed and all MHCLG funding must be spent Report P27, P55

Plain English for the jargon

  • PCSA: Pre-Construction Services Agreement, an early contractor appointment to develop design, cost and programme before the main works contract is signed.
  • LRF: Local Regeneration Fund, formerly the Levelling Up Fund, the central government funding stream being used here.
  • CRP: Capital Regeneration Project, the funding programme covering the Dovercourt scheme.
  • MHCLG: Ministry of Housing, Communities and Local Government, the government department providing the grant, which must be spent by March 2028.
  • HRA: Housing Revenue Account, the ring-fenced account that will hold and manage the new social rented homes.
  • RIBA stages: Royal Institute of British Architects work stages that structure design and construction; the project is moving from Stage 3 into Stage 4 during the PCSA.
  • LGR: Local Government Reorganisation, the restructuring of councils that may affect long-term ownership and management of the assets.
  • PA23: Procurement Act 2023; the procurement has been run under Part 2 and Part 6 of this Act.
  • TOMS: Themes, Outcomes and Measures, the social value framework used by Essex County Council against which social value is scored.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

RESOLVED that Cabinet - (a) notes and welcomes the progress on the second procurement exercise in securing a high level of interest from the market and a Preferred Bidder, and enacting the lessons learned from the previous exercise; (b) reinforces its ongoing commitment relating to the use and management of the Milton Road and Victoria Street sites, with Milton Road retained for public car parking provision, and the Victoria Street sites retained for housing purposes and being retained within the Housing Revenue Account (together with associated car parking provision), with no current intention to appropriate or dispose of any of the sites; and (c) notes and supports the progression of the project to the next stage, including entry into a Pre-Construction Services Agreement (PCSA) with the preferred bidder, in accordance with the existing operational delegated authority.
Word for word from the decision Tendring published for this meeting. Source: tdcdemocracy.tendringdc.gov.uk

Follow this further

Built from Tendring's papers

What the report saysPro

Report to Cabinet

Executive summary

The Homes for Dovercourt scheme is one part of the regeneration of Harwich town centre along the peninsula corridor from Dovercourt seafront to the Dovercourt station. A refurbished library with new accessible skills centre is already complete; upgrades to the town centre’s public realm and connection to the seafront are underway, and with this scheme, new social housing and improved car parking is planned. This suite of regeneration projects is expected to revitalise the the town, improve outcomes for residents and encourage private sector investment ahead of the planned arrival of the Freeport East Green Energy Hub at Bathside Bay.

The Homes for Dovercourt scheme will see two disused and derelict sites in Dovercourt transformed by the Council, building on the Dovercourt Revisited masterplan:

• At Milton Road, a derelict car park will be refurbished to provide a modern, fit-for- purpose at grade parking provision, with EV charging, cycle storage, soft landscaping and decorative railings celebrating local heritage; • At Victoria Street, the site of the historic Victoria Hotel will be rebuilt, echoing the history of the site’s design and Conservation Area, to provide eight new affordable homes and amenity space.

The project will deliver an estimated £1.04m in Social Value, including four local employment opportunities, 52 apprenticeship weeks and student placement opportunities, c.£970,000 of local supply chain spend, alongside wider community and environmental benefits

A summary of progress made to date, including design, planning and procurement milestones and recent updates following the March 2026 Cabinet report, is as follows: • RIBA Stage 3 design completed, and planning permission secured (Feb–Apr 2025); • An initial tender exercise undertaken in 2025 did not achieve a viable outcome; • The procurement strategy was revised to a two-stage approach to improve cost certainty, supported by a pre-market engagement exercise; • Second procurement (Apr–May 2026) attracted strong interest (13 submissions, 12 compliant); • The tender evaluation has now been completed and a preferred contractor identified; and • Project funding is confirmed within the Council’s Capital Programme within April 2026 Cabinet Report.

The Corporate Director for Place & Wellbeing is using delegated authority to enter into a Pre- Construction Services Agreement (PCSA) with the preferred contractor, in consultation with Portfolio Holders.

Through the PCSA, the contractor will work with the Council to finalise the design, delivery approach and cost. This will help manage risks early and improve cost certainty. A final construction price is expected in September 2026 and, if within budget, will be subject to a further officer decision in consultation with Portfolio Holders.

The procurement process has identified a preferred bidder and includes:

• A fixed cost of the PCSA stage of £69,300 (excluding of VAT); • An estimate of the main works cost which will be refined during the PCSA period; • A programme for completion of the works, which falls well within the funding envelope, and aligns with the above forecast for agreement of the main contract sum. The programme includes the early completion of Milton Road Car Park.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet Members' Items: Report of the Economic Growth, Regeneration and Tourism Portfolio Holder: A.3: Local Regeneration Fund (LRF): Milton Road and Victoria Street: Progress UpdateReport 285 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 28 attended
MS
Councillor Mark StephensonChairman, apologies (on leave)
IH
Councillor Ivan HendersonCommittee Member, present
AB
Councillor Andy BakerCommittee Member, present
MB
Councillor Mick BarryCommittee Member, present
PK
Councillor Peter KotzCommittee Member, present
GP
Councillor Gina PlaceyCommittee Member, present
GS
Councillor Gary ScottCommittee Member, present
AS
Councillor Adrian SmithCommittee Member, present
JB
Councillor Jeff BraySpokesperson, apologies (other personal or family responsibilities)
JC
Councillor Jayne Chapman BEMSpokesperson, in attendance
PH
Councillor Paul HoneywoodSpokesperson, apologies (unspecified)
ID
Ian DavidsonOfficer, in attendance

All 28 on the meeting page

On this subject at Tendring

Search all
  1. Cabinet Members' Items - Report of the Economic Growth, Regeneration and Tourism Portfolio Holder - A.3 - Local Regeneration Fund (LRF) - Milton Road and Victoria Street: Progress UpdateThis decision
  2. Cabinet Members' Items - Report of the Portfolio Holder for Corporate Finance & Governance - A.1 - Financial Performance Report 2026/27 - General Update at the end of September 2026Approved
  3. Cabinet Members' Items - Report of the Corporate Finance & Governance Portfolio Holder - A.2 - The Local Council Tax Support Scheme, Discretionary Council Tax Exemptions / Discounts / Premiums for 2027/28 and Annual Minimum Revenue Provision Policy Statement 2027/28Agreed
  4. Cabinet Members' Items - Report of the Housing & Planning Portfolio Holder - A.3 - Annual Housing Improvement, Performance & Assurance Report 2025/26Decided
  5. Cabinet Members' Items - Report of the Housing & Planning Portfolio Holder - A.4 - Adoption of the Conservation Area Character Appraisals and Management Plans for St Osyth and Manningtree & MistleyNoted
  6. Cabinet Members' Items - Report of the Portfolio Holder for Corporate Finance & Governance Portfolio Holder - A.1 - Financial Performance Report 2026/27 - General Update at the end of June 2026Approved

More from Tendring Cabinet

All decisions
MeetingDecisionOutcome
13 Nov 2026 Minutes of the Last MeetingRESOLVED that the minutes of the meeting of the Cabinet, held on Friday 23 October 2026, be approved as a correct rec... Approved Open
13 Nov 2026 Cabinet Members' Items - Report of the Portfolio Holder for Corporate Finance & Governance - A.1 - Financial Performance Report 2026/27 - General Update at the end of September 2026RESOLVED that Cabinet – (a) notes the Council’s in-year financial position as at the end of September 2026; (b) appro... Approved Open
13 Nov 2026 Cabinet Members' Items - Report of the Corporate Finance & Governance Portfolio Holder - A.2 - The Local Council Tax Support Scheme, Discretionary Council Tax Exemptions / Discounts / Premiums for 2027/28 and Annual Minimum Revenue Provision Policy Statement 2027/28RESOLVED that Cabinet – a) agrees that the underlying LCTS scheme for 2027/28 remains the same as the current year, a... Agreed Open
13 Nov 2026 Cabinet Members' Items - Report of the Housing & Planning Portfolio Holder - A.3 - Annual Housing Improvement, Performance & Assurance Report 2025/26RESOLVED that Cabinet – (a) notes the contents of the Annual Housing Improvement, Performance & Assurance Report 2025... Decided Open
13 Nov 2026 Cabinet Members' Items - Report of the Housing & Planning Portfolio Holder - A.4 - Adoption of the Conservation Area Character Appraisals and Management Plans for St Osyth and Manningtree & MistleyRESOLVED that – (a) the outcome of the public consultation exercises summarised in this report (A.4) be noted; and (b... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies