Charlton Lakes Circular Path

Approved Executive 2 papers

AI summaryCabinet approved a £310,000 project to build an all-user access route around the playing fields at Charlton Leisure Centre, adding the cost to the 2026/27 Capital Programme.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedAll-user route around playing fields perimeter
Money£310,000Added to Capital Programme for 2026/27
What happens nextConstruct the routeDirector of Community and Leisure to deliver, minor design delegated
Who it affectsCharlton Leisure Centre playing fieldsAll-user access route around perimeter

What was decided

Cabinet approved the project to construct an all-user access route around the perimeter of the playing fields at Charlton Leisure Centre.

£310,000 was added to the Council's Capital Programme for the construction and delivery of the route.

The Director of Community and Leisure was given delegated authority to make minor changes to the final design and layout, including hard and soft landscaping.

Why

The project is listed in the Council's Corporate Action Plan for year four of the Corporate Plan.

What happens next

Construction of the all-user access route will go ahead using the £310,000 capital allocation in 2026/27.

The Director of Community and Leisure will oversee delivery and finalise design, with delegated authority for minor changes including hard and soft landscaping.

The money

  • £310,000 Added to Capital Programme for construction and delivery of the all-user access route

Implications

  • Financial: £310,000 added to the Council's Capital Programme in 2026/27 for construction and delivery.
  • Other: The project is part of year four of the Council's Corporate Plan through the Corporate Action Plan.

Who and where

  • Users of Charlton Leisure Centre and its playing fields

Timeline

  • 2026/27: Funding to be added to Capital Programme for construction and delivery

Plain English for the jargon

  • Capital Programme: The Council's planned spending on major projects and fixed assets.
  • All-user access route: A path designed for use by a range of users.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

That the project to construct an all-user access route around the perimeter of playing fields at Charlton Leisure Centre, listed in the Council’s Corporate Action Plan for year four of the Corporate Plan and as described in this report, be approved. 2. That £310,000 be added to the Council’s Capital Programme for construction and delivery of the route. 3. That the Director of Community and Leisure be given delegated authority to make changes of a minor nature to the final design and layout of the route, including hard and soft landscaping. 1. That the project to construct an all-user access route around the perimeter of playing fields at Charlton Leisure Centre, listed in the Council’s Corporate Action Plan for year four of the Corporate Plan and as described in this report, be approved. 2. That £310,000 be added to the Council’s Capital Programme for construction and delivery of the route. 3. That the Director of Community and Leisure be given delegated authority to make changes of a minor nature to the final design and layout of the route, including hard and soft landscaping.
Word for word from the decision Test Valley published for this meeting. Source: democracy.testvalley.gov.uk

Follow this further

Built from Test Valley's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Charlton Lakes: AnnexAppendix 117 KB Copy on its way
PDF
Charlton Lakes Circular PathReport 100 KB Copy on its way

At this meeting

Whole meeting

More from Test Valley Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Recommendations of the Overview and Scrutiny CommitteeThat Cabinet considers the recommendations of the Overview and Scrutiny Committee resulting from the Digital Inclusio... Approved Open
23 Sep 2026 Scheme of Delegations to OfficersThat the Scheme of Officer Delegations, as set out in the Annex to the report, insofar as it applies to the powers an... Approved Open
23 Sep 2026 Quarterly Revenue Budget Monitoring 2026/27That the financial position for each Service and the key revenue areas contained in the Annex is noted. 2. That the T... Noted Open
23 Sep 2026 Test Valley Borough Council Playing Pitch and Sport Facilities StrategiesThat the Test Valley Borough Playing Pitch and Sport Facilities Strategies, annexed to the report, be adopted and pub... Approved Open