TRDC SIAS Progress Report Against the 2024-25 Audit Plan for 26 September 2024

Noted Finance 1 paper

Audit Committee noted this item on Thursday 26 September 2024. Below is the council's own wording, with the papers it was decided on.

ItemAC21/23

Resolved

i. to NOTE the Internal Audit Progress Report for the period to 13 September 2024. ii. to APPROVE amendments to the Audit Plan as at 13 September 2024. iii. to AGREE changes to the implementation date for 5 audit recommendations (paragraph 2.5) for the reason set out in appendices 3 to 6. iv. to AGREE removal of implemented audit recommendations (appendices 3 to 6).
Word for word from the decision Three Rivers published for this meeting. Source: moderngov.threerivers.gov.uk

Follow this further

Built from Three Rivers's papers

What the report saysPro

Report to Audit Committee

Recommendation

Members are recommended to:  Note the Internal Audit Progress Report for the period to 13 September 2024  Approve amendments to the Audit Plan as at 13 September 2024  Agree changes to the implementation date for 5 audit recommendations (paragraph 2.5) for the reason set out in Appendices 3 to 6  Agree removal of implemented audit recommendations (Appendices 3 to 6) Contents

1 Introduction and Background 1.1 Purpose of Report 1.2 Background

2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 Audit Recommendations 2.6 Proposed Audit Plan Amendments 2.7 Audit Plan Delivery Progress

Appendices 1 Progress against the 2024/25 Audit Plan 2 2024/25 Audit Plan Projected Start Dates 3-6 Progress against Outstanding Internal Audit Recommendations 7 Assurance and Priority Levels 8 Global Internal Audit Standards – Briefing Paper

1 1. Introduction and Background Purpose of Report

1.1This report details:

a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s annual audit plan for 2024/25 as at 13 September 2024. b) Proposed amendments to the approved 2024/25 Annual Audit Plan. c) Implementation status of all previously agreed audit recommendations from 2019/20 onwards. d) An update on performance management information as at 13 September 2024.

Background

1.2The work of internal audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.

1.3The 2024/25 Annual Audit Plan was approved by Audit Committee on 21 March 2024.

1.4The Audit Committee receives periodic updates on progress against the Annual Audit Plan from SIAS, the most recent of which was brought to this Committee on 25 July 2024.

2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings

2.1At 13 September 2024, 34% of the 2024/25 Audit Plan days had been delivered (calculation excludes unused ‘To Be Allocated’). Appendix A provides a status update on each individual deliverable within the audit plan.

2.2The following 2023/24 has not yet been finalised and is awaiting management response.

Audit Title Date of Assurance Number and Draft Level Priority of Report Recommendations 2 Medium Sundry Debtors 09/05/24 Reasonable 3 Low

The following 2024/25 final report has been issued since July 2024 Audit Committee. 2 Audit Title Date of Assurance Number and Issue Level Priority of Recommendations Homelessness Sept ‘24 Substantial None

All Priority Audit Recommendations

2.3Members will be aware that a Final Audit Report is issued when agreed by Management. This includes an agreement to implement the recommendations made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of recommendations; it is the responsibility of officers to implement the recommendations by the agreed date.

2.4The table below summarises progress in implementation of all outstanding internal audit recommendations as at 12 July 2024, with full details given in appendices 3 to 6:

Year Number of Implemented Not Outstanding % Recommendations yet & request implemented due made for extended time or no update provided 2019/20 37 36 1 0 97% 2020/21 25 25 0 0 100% 2022/23 44 43 1 0 98% 2023/24 36 26 5 5 72%

2.5Since July 2024 Audit Committee, extension to implementation dates have been requested by action owners for 5 recommendations as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TRDC SIAS Progress Report Against the 2024-25 Audit Plan for 26 September 2024Report 1.3 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 14 attended
TH
Councillor Tony HumphreysChair, present
KM
Councillor Keith MartinVice-Chair, present
LH
Councillor Lisa HudsonCommittee Member, present
SB
Councillor Sara BedfordCommittee Member, apologies
KH
Councillor Khalid HussainCommittee Member, present
DM
Councillor David MajorCommittee Member, apologies
IM
Councillor Ian MorrisCommittee Member, present
CR
Councillor Ciaran ReedCommittee Member, present
MS
Councillor Mike SimsCommittee Member, present
HD
Hannah DoneyOfficer, expected
AH
Anita HibbsClerk, expected
RT
Robert ThurlowOfficer, expected

All 14 on the meeting page

On this subject at Three Rivers

Search all
  1. TRDC SIAS Progress Report Against the 2024-25 Audit Plan for 26 September 2024This decision
  2. TRDC SIAS Progress Report Against the 2025-2026 Audit PlanNoted
  3. Trdc sias annual assurance statement and internal audit report 2024-2025Noted
  4. Trdc sias progress report against the 2023/24 audit planNoted
  5. Trdc sias progress against the 2022/23 audit planNoted

More from Three Rivers Audit Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Annual Fraud Report 2025/26To note the contents of this report. Noted Open
25 Jun 2026 Audit plan updateMembers are recommended to: Note the position of the 2026/27 Audit Plan delivery Noted Open
28 May 2026 Internal Audit Annual Report 2025/26Recommendation Members are recommended to: Note the Annual Assurance Statement and Note the results of the self-asses... Noted Open
28 May 2026 Statement of Accounts Update 2025/26Recommendation To note the update in relation to the 2025/26 Statement of Accounts timeframes. To review the draft Ac... Noted Open
24 Mar 2026 Statement of Accounts Update 2025/26To note the update in relation to the 2025/26 Statement of Accounts timeframes. To review the draft Accounting Polici... Noted Open