Resolved
That: The Climate Change and Leisure Committee recommend officers seek contractor quotations and then recommend the Outline Business Case to the Policy & Resources Committee.
Climate Change and Leisure Committee decided this item on Wednesday 2 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That: The Climate Change and Leisure Committee recommend officers seek contractor quotations and then recommend the Outline Business Case to the Policy & Resources Committee.
1.1This report proposes that rooftop solar PV is installed at South Oxhey Leisure Centre, funded by council capital budget and repaid through a Power Purchase Agreement1 with Sports and Leisure Management Ltd (SLM).
1.2This report recommends that the Outline Business Case (OBC) is recommended to Policy & Resources Committee. This report provides background context and a high-level overview of the OBC, which can be found in Appendix 1.
2 Details
2.1Three Rivers District Council are committed to achieving net zero by 2030 for our own emissions and to inspire and enable a net zero district by 2045. Achieving net carbon zero and being climate resilient is one of four core pillars of the corporate framework. Residents endorsed this as a priority in the recent resident survey conducted in February-March 2024 when environment/climate change ranked as the 3rd biggest concern for households.
2.2Most of the council’s carbon emissions are emitted from two main sources 1) council buildings (including leisure centres) and 2) council vehicle fleet. To achieve net zero, the council must reduce carbon emissions from its vehicle fleet by ~850 tonnes per year by 2030 and reduce carbon emissions from its “core buildings” (excluding small buildings like pavilions) by ~838 tonnes per year by 2030.
2.3In 2022, the Association for Public Service Excellence (APSE) conducted a survey of the council’s core buildings to establish a baseline of emissions. The survey revealed that the core buildings emitted 942 tons (t) of carbon dioxide (CO2) in the 2019/20 fiscal year. APSE also projected a trajectory towards net- zero based on the completion of a suite of building decarbonisation projects. One of the projects recommended by APSE was the installation of rooftop solar PV at South Oxhey Leisure Centre (SOLC).
2.4Since then, several decarbonisation projects have been implemented (or planned) across the council estate, which are expected to result in savings of 104 tCO2. Most recently, a 500-panel rooftop solar PV system was installed at William Penn Leisure Centre which by June 17th 2025 over this calendar year has saved over £15,000 and 41 tonnes of CO2 and is performing 10% ahead of forecast at the end of May. See Figure 1.
1 A power purchase agreement (PPA) is a long-term contract between an electricity generator and a buyer. In this agreement, the buyer agrees to purchase electricity at a pre-negotiated price for a specified duration, usually ranging from 5 to 20 years. The PPA outlines the terms of energy delivery and pricing, ensuring a stable revenue stream for the energy supplier. 2.5 The rooftop solar PV at William Penn Leisure Centre was funded by a grant from the Swimming Pool Support Fund and Sport England. The council also applied to Sport England for a grant for rooftop solar PV at SOLC, but our application was unsuccessful.
2.6SOLC consumes 153,594 kWh of electricity per year and is one of the biggest electricity consuming buildings in the council estate.2 Therefore, the installation of rooftop solar PV would have a big impact on the council’s efforts to become net zero by 2030.
2.7As such, council officers have been working to 1) confirm the feasibility of installing rooftop solar PV at SOLC and 2) exploring alternative potential fundings sources.
2.8One potential funding source officers have explored is using council capital budget to fund the solar PV, repaid through a Power Purchase Agreement (PPA).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
South Oxhey Leisure Centre Solar Panels Business CaseReport | 269 KB | DownloadRead as text |
Follow Climate Change and Leisure Committee at Three Rivers and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | Pond Wood Management Plan 2026-36That the Climate Change and Leisure Committee: Adopt the new 10-year Management Plan for Pond Wood Give delegated aut... | Approved | Open |
| 24 Jun 2026 | Revocation of an Air Quality Management Area (AQMA) at junction 18 of M25, ChorleywoodThat the report and its recommendations are discussed and noted with the agreed Officer recommendations progressed: T... | Noted | Open |
| 11 Mar 2026 | Budget Management Report P10 - CC<hat members note and comment on the contents of the report. | Decided | Open |
| 11 Mar 2026 | Prestwick Road Meadows Management Plan 2026-2036That the Climate Change and Leisure Committee: i. Adopt the new ten-year Management Plan for Prestwick Road Meadows. ... | Approved | Open |
| 11 Mar 2026 | Work programmeTo receive the Committee’s work programme. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.