Three Rivers District Council
Audit Committee, Thursday 27 November 2025 at 7.30pm

INTERNAL AUDIT PROGRESS REPORT

Noted Finance 1 paper

AI summaryThree Rivers Audit Committee noted the Internal Audit Progress Report to 14 November 2025, approved plan amendments using all remaining contingency, and agreed to extend recommendation deadlines. Plan delivery is below target at 48% of days.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedExtensions and removals of recommendations agreed
MoneyNot stated
What happens nextService update to followHeads of Service update via Interim Head of Finance
Who it affectsCouncil services being auditedOfficers responsible for open recommendations

What was decided

The committee noted the Internal Audit Progress Report covering the period to 14 November 2025. Report P1

Members approved amendments to the 2025/26 Audit Plan, allocating all 11 remaining contingency days (6 to Financial Billing, 5 to the Agency audit). Report P1, 2.6

The committee agreed changes to implementation dates for audit recommendations and removal of implemented recommendations listed in Appendices 3 to 5. Report P1

Why

48% of the 2025/26 Audit Plan days had been delivered as at 14 November 2025, below the 60% profile target, with 32% of projects at draft stage against a 42% target. Report 2.1, 2.8, P26, P27

Action owners requested extensions to seven recommendation deadlines from the Sundry Debtors, Public Health Funerals, Council Tax, Procurement Act and Business Rates audits. Report 2.5, P20

Officers reported no risks to the annual assurance opinion, with delivery expected to recover in quarters 3 and 4 once vacant trainee posts were filled. Report 2.10, 2.12, P36

What happens next

The Interim Head of Finance is to circulate a more detailed update from Heads of Service to the Committee.

Plan delivery is to be brought back to the 95% days and 90% draft report KPIs by 31 March 2026. Report 2.2

Outstanding recommendations carry revised target dates including 31 March 2026, 29 June 2026, 28 February 2026 and 31 January 2026. Report P20, P67, P83, P86, P105, P116, P120, P122

Options considered

  • Chosen: Note the Internal Audit Progress Report to 14 November 2025. Standard committee oversight of internal audit delivery Report P1
  • Chosen: Approve amendments to the 2025/26 Audit Plan. Allocated all remaining contingency days to Financial Billing and Agency audits Report 2.6
  • Chosen: Agree changes to implementation dates for audit recommendations. Action owners requested extensions, set out in Appendices 3 to 5 Report 2.5, P20
  • Chosen: Agree removal of implemented audit recommendations. Recommendations had been completed and signed off Report P75, P103, P112

Implications

  • Risk: Plan delivery is currently below the agreed profile, though officers report no risk to the annual assurance opinion. Report 2.10, 2.12
  • Staffing: Two previously vacant trainee auditor posts have been filled, with new staff in post during quarter 2. Report P36
  • Other: Delays from the external co-sourced partner and senior staff capacity issues linked to local government reorganisation have affected delivery timing. Report P36
  • Other: No Critical or High priority audit recommendations have been made in 2025/26 to date. Report P29

Who and where

  • Three Rivers District Council services subject to 2025/26 internal audits Report P39, P40, P42, P44
  • Officers responsible for open audit recommendations across Sundry Debtors, Council Tax, Business Rates, Procurement, Public Health Funerals, Asset Management, Cyber Security and Housing Benefits overpayments Report P20, P67, P75, P83, P86, P91, P104, P116, P120, P61
  • Heads of Service, who are to provide a more detailed update to the Committee via the Interim Head of Finance

Timeline

  • 25 March 2025: 2025/26 Annual Audit Plan approved by Audit Committee Report 1.3
  • 14 November 2025: Cut-off date for progress, recommendations and performance figures in this report Report 1.1, 2.1
  • 27 November 2025: Audit Committee meeting considering this report
  • 31 January 2026: Revised target date for Business Rates recommendations Report P20, P120, P122
  • 28 February 2026: Revised target date for Procurement Act recommendation Report P20, P116
  • 31 March 2026: KPIs for billable days and draft reports to be met Report 2.2
  • 31 March 2026: Revised target date for Sundry Debtors, Council Tax and Asset Management recommendations Report P20, P67, P105, P91
  • 29 June 2026: Revised target date for Public Health Funerals recommendations Report P20, P83, P86

Plain English for the jargon

  • SIAS: Shared Internal Audit Service, the council's internal audit provider
  • KPI: Key Performance Indicator used to measure audit plan delivery
  • TRAMPS: Three Rivers Asset Management Property System used to record lease events
  • LGR: Local Government Reorganisation, cited as a cause of capacity issues
  • CMT: Corporate Management Team
  • JLT: Joint Leadership Team
  • SIRO: Senior Information Risk Owner responsible for information risk
  • PHF: Public Health Funerals, the council's service for arranging funerals where no one else will
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAC28/25

Resolved

For Members to: Note the Internal Audit Progress Report for the period to 14 November 2025 Approve amendments to the Audit Plan as at 14 November 2025 Agree changes to the implementation date for 8 audit recommendations (paragraph 2.5) for the reason set out in Appendices 3 to 5 Agree removal of implemented audit recommendations (Appendices 3 to 5) A more detailed update from Heads of Service to be circulated to the Committee by the Interim Head of Finance.
Word for word from the decision Three Rivers published for this meeting. Source: moderngov.threerivers.gov.uk

Follow this further

Built from Three Rivers's papers

What the report saysPro

Report to Audit Committee

Recommendation

Members are recommended to:  Note the Internal Audit Progress Report for the period to 14 November 2025  Approve amendments to the Audit Plan as at 14 November 2025  Agree changes to the implementation date for 8 audit recommendations (paragraph 2.5) for the reason set out in Appendices 3 to 5  Agree removal of implemented audit recommendations (Appendices 3 to 5) Contents

1 Introduction and Background 1.1 Purpose of Report 1.2 Background

2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 All Priority Audit Recommendations 2.7 Proposed Audit Plan Amendments 2.8 Audit Plan Delivery Progress

Appendices 1 Progress against the 2025/26 Audit Plan 2 2025/26 Audit Plan Projected Start Dates 3-5 Progress against Outstanding Internal Audit Recommendations 6 Assurance and Priority Levels

1 1. Introduction and Background Purpose of Report

1.1This report details:

a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s annual audit plan for 2025/26 as at 14 November 2025. b) Proposed amendments to the approved 2025/26 Annual Audit Plan. c) Implementation status of all previously agreed audit recommendations from 2019/20 onwards. d) An update on performance management information as at 14 November 2025.

Background

1.2The work of internal audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.

1.3The 2025/26 Annual Audit Plan was approved by Audit Committee on 25 March 2025.

1.4The Audit Committee receives periodic updates on progress against the Annual Audit Plan from SIAS. This is the second report giving an update on the delivery of the 2025/26 Internal Audit Plan.

2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings

2.1At 14 November 2025, 48% of the 2025/26 Audit Plan days had been delivered. Appendix 1 provides a status update on each individual deliverable within the audit plan.

2.2There have not been any final reports issued since the September meeting of the Audit Committee. However, the position is not dissimilar to progress in the November 2024 report, and all audits have been allocated resource to ensure that the agreed KPIs for deliverable days (95%) and draft reports issued (90%) are met before 31 March 2026.

All Priority Audit Recommendations

2.3Audit Committee Members will be aware that a Final Audit Report is issued when agreed by Management. This includes an agreement to implement the recommendations made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of

2 recommendations; it is the responsibility of officers to implement the recommendations by the agreed date.

2.4The table below summarises progress in implementation of all outstanding internal audit recommendations as at 14 November 2025, with full details given in appendices 3 to 5:

Year Number of Total Not Overdue No Percent Recommendatio Number of yet & a revised update age ns made Outstanding due implementation receive implem Recommend date provided d ented ations % 2023/24 39 2 1 1 0 95% 2024/25 35 8 4 4 0 77%

2.5Since the September 2025 Audit Committee, extension to implementation dates have been requested by action owners for seven recommendations (some were not due at the time of the extension request) as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT PROGRESS REPORTReport 473 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
TH
Councillor Tony HumphreysChair, present
KM
Councillor Keith MartinVice-Chair, apologies, sent representative
HD
Councillor Harry DaviesCommittee Member, present
LH
Councillor Lisa HudsonCommittee Member, present
SK
Councillor Stephen KingCommittee Member, present
DM
Councillor David MajorCommittee Member, present
CR
Councillor Ciaran ReedCommittee Member, present
MS
Councillor Mike SimsCommittee Member, present
CS
Councillor Cheryl StungoCommittee Member, absent
RK
Councillor Raj KhiroyaCommittee Member, present as substitute
MH
Michelle HowellCouncil Staff, in attendance
AH
Anita HibbsOfficer, in attendance

All 16 on the meeting page

On this subject at Three Rivers

Search all
  1. INTERNAL AUDIT PROGRESS REPORTThis decision
  2. Internal Audit Annual Report 2025/26Noted
  3. TRDC Internal Audit Plan report 2026/27Approved
  4. Trdc sias annual assurance statement and internal audit report 2024-2025Noted
  5. SIAS Internal Audit Plan Report 2025-26Approved
  6. Shared Internal Audit Service (SIAS) Board Annual ReportNoted

More from Three Rivers Audit Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Annual Fraud Report 2025/26To note the contents of this report. Noted Open
25 Jun 2026 Audit plan updateMembers are recommended to: Note the position of the 2026/27 Audit Plan delivery Noted Open
28 May 2026 Internal Audit Annual Report 2025/26Recommendation Members are recommended to: Note the Annual Assurance Statement and Note the results of the self-asses... Noted Open
28 May 2026 Statement of Accounts Update 2025/26Recommendation To note the update in relation to the 2025/26 Statement of Accounts timeframes. To review the draft Ac... Noted Open