AI summaryThree Rivers District Council's Climate Change and Leisure Committee adopted a new five-year management plan for The Green & Stones Orchard in Croxley Green, running to March 2030, and delegated authority to the Director of Finance for contracts above £25,000 subject to external funding.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCovers The Green and Stones Orchard, Croxley Green, until March 2030
Money£25,000 contract thresholdDirector of Finance delegated authority above this, subject to external funding
What happens nextSeek external fundingOfficers to implement actions via existing budgets or external grants
Who it affectsCroxley Green community and visitorsPlus wildlife, biodiversity, and local stakeholders on the site
What was decided
The committee adopted the new five-year Management Plan for The Green & Stones Orchard, covering habitat, wildlife, public access and signage improvements. Report 2.2, 1.2
Delegated authority was given to the Director of Finance to enter into contracts or funding agreements above £25,000, subject to securing external funding. Report 2.3
Public access to the report was granted immediately. Report 2.4
Why
Officers recommended adoption so management actions for biodiversity and public access can begin, with works funded through existing budgets or external grants. Report 1.2, 5.1
The plan supports the Council's biodiversity duty under S40 of the Natural Environment and Rural Communities Act 2006 and the protection of common land under the Commons Act 2006. Report 7.5
It links to the Council's Sustainable Communities and Net Carbon Zero corporate objectives, and to performance indicators LNI04 and LNI05. Report 5.3, P58, P59, P55, P56
What happens next
Officers will implement actions using existing budgets, with other works dependent on securing external funding in advance. Report 1.2, 6.2
An internal annual review of the site risk assessment will take place, and the website will be kept updated with site changes. Report P33, 14.1
Good news stories on progress will be shared via the Communications team across social media channels. Report 14.2
The money
£25,000 Threshold above which delegated authority to the Director of Finance applies for contracts or funding agreements Report 2.3, 7.4
Options considered
Chosen: Adopt the five-year management plan as recommended. Allows officers to begin implementing biodiversity and public access improvements, subject to funding Report 2.2
Rejected: Do not approve the plan. Maintenance would continue at a base level only, with no additional biodiversity or access improvements Report 4.2
Implications
Financial: Recommendations are within the Council's agreed budgets; further actions depend on external funding being secured first. Report 5.1, 6.1, 6.2
Legal: Works and equipment will be tendered under the Council's Contract Procedure Rules; The Green is common land protected by the Commons Act 2006. Report 7.1, 7.5
Equalities: A Short Equality Impact Assessment found positive impacts through improved accessibility, site furniture, interpretation and community events, dependent on external funding. Report 8.1, 8.2, 8.3
Climate: A Climate and Sustainability Impact Assessment was completed, with an overall average score of 3.5. Report 10.1, P77
Risk: Risk register notes reputational risk if plan actions are not implemented due to a lack of resources, rated 4 and to be tolerated with monitoring. Report P92, P93, 15.2
Staffing: Delivery will be led by the Leisure and Natural Infrastructure Service within existing staff resource, supported by Croxley Green Parish Council and other Council services. Report 9.1, 9.2, 9.3
Other: Community Safety and Public Health outcomes are expected to be positive, including new preventative measures against unwanted vehicle incursion. Report 11.1, 12.1
Who and where
Local community and visitors to The Green and Stones Orchard, Croxley Green Report P39, P40
Croxley Green Parish Council, which supports grounds maintenance work at the sites Report P9, 6.1, 9.2
Local stakeholders consulted, including Croxley Green Residents Association, Croxley History Project, Croxley Revels, Three Rivers Museum, local allotments and Hertfordshire County Council's Countryside Management Service Report P21
Wildlife and habitats on the sites, including badger setts Report P43, P31
Timeline
4 November to 2 December 2024: Initial public consultation on the briefing document, hosted on the council's 'Have your Say' platform, receiving 16 responses Report P13
7 August to 30 September 2025: Public and stakeholder consultation on the draft management plan, receiving 88 responses Report P14
14 January 2026: Climate Change and Leisure Committee considers and adopts the management plan Report 2.2
From adoption until March 2030: Five-year period over which the management plan's actions are to be delivered Report 1.2
Plain English for the jargon
Have your Say: The council's online public consultation platform used for the two consultation stages
S40 of the Natural Environment and Rural Communities Act 2006: Statutory duty requiring the Council to have regard to conserving and enhancing biodiversity when exercising its functions
Commons Act 2006: Legislation under which The Green's common land status and associated rights are protected
LNI04 and LNI05: Performance indicators in the Leisure and Natural Infrastructure Service Plan 2025-2028 for external funding secured and biodiversity-managed land area
The Green: An area of common land in Croxley Green covered by the plan, alongside Stones Orchard
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item32
Resolved
That the Climate Change & Leisure Committee: i. Adopt the new five-year Management Plan for The Green & Stones Orchard. ii. Give delegated authority to the Director of Finance to enter into a contract or funding agreement above the value of £25,000, subject to securing external funding for actions relating to The Green & Stones Orchard Management Plan. iii. That public access to the report be immediate.
Word for word from the decision Three Rivers published for this meeting.Source: moderngov.threerivers.gov.uk
1.1A new five-year management plan has been developed for The Green & Stones Orchard in Croxley Green.
1.2The new plan contains proposed management actions over the next five years from adoption of the plan until March 2030. The detailed actions relate to habitat and wildlife improvements for biodiversity alongside improvements to public access and signage. Should the plans be approved, Officers will seek to implement the actions using existing budgets or where necessary actions will be subject to external funding being secured.
Recommendation
2.1That the Climate Change & Leisure Committee:
2.2Adopt the new five-year Management Plan for The Green & Stones Orchard.
2.3Give delegated authority to the Director of Finance to enter into a contract or funding agreement above the value of £25,000, subject to securing external funding for actions relating to The Green & Stones Orchard Management Plan.
2.4That public access to the report be immediate.
3 Details
3.1Plan Development Process
3.1.1 The plan was developed by officers from the Leisure & Natural Infrastructure team in partnership with officers from the Grounds Maintenance and Property Services & Facilities teams with support from Croxley Green Parish Council officers
3.1.2 The process commenced with the creation of a briefing document which outlined the process and purpose of the management plan. This was consulted upon with the public and local stakeholders. This process invited interested parties to share ideas and thoughts on the management of the sites for the coming five years.
3.1.3 Upon completion of the draft plan, a second period of consultation was held to enable stakeholders (detailed 3.2.2) to comment on draft versions of the plans. Minor amendments were made to the plans to produce the final version.
3.2Consultation Process
3.2.1 The initial consultation on the briefing document was held over four weeks between 4th November and 2nd December 2024.The consultation was hosted on the council’s “Have your Say” platform; publicised online and received 16 individual responses to the consultation. Appendix D overviews the responses submitted as part of the briefing document consultation process.
2 3.2.2 Public and stakeholder consultation, on the draft management plan, took place from 7th August to 30th September 2025. The consultation was hosted on the council’s “Have your Say” platform; publicised online, on-site through posters and local stakeholders were directly contacted notifying of the consultation. A total of 88 individuals responded.
3.2.3 Some of the key items raised included:
The future aspirational action “Pond / Wetland Creation on The Green”
Dislike of parking inhibitors on the Green
Concerns for future development on the sites
Opportunities to plant more trees
3.2.4 An overview of the consultation responses is included within the Appendix D with feedback and how this engagement has been incorporated into the management plan development process.
3.2.5 Direct contact with local Stakeholders included: local Councillors; Croxley Green Parish Council; Hertfordshire County Council’s Countryside Management Service; Three Rivers Museum; Croxley Green Residents Association; Croxley History Project; Croxley Revels and local allotments.
3.2.6 Following the consultation period, a series of amendments were made to the management plan draft. The more significant amendments were as follows (where applicable paragraph reference points have been included):
Addition of references throughout the document to direct information sources.
1.7: Addition of reference to the Hertfordshire Local Nature Recovery Strategy.
3.10: Additional information has been provided in relation to the Pond/Wetland Creation on the Green.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Climate Change and Leisure Committee at Three Rivers and we tell you when its next papers are published, before the meeting rather than after it.
Pond Wood Management Plan 2026-36That the Climate Change and Leisure Committee: Adopt the new 10-year Management Plan for Pond Wood Give delegated aut...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.