25/1943/FUL - Demolition of existing building and construction of a new three storey building to provide community centre at ground floor level and 8 residential units to the two upper floors with associated landscaping, access, and parking
AgreedPlanning3 papers
AI summaryThree Rivers planners approve demolition of the British Red Cross building in Croxley Green and a replacement three storey building with a community centre and 8 affordable flats, subject to conditions.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedApplication 25/1943/FUL, item PC106/25, on 2026-02-26
MoneyNo direct sum statedLHA caps given as £218.63/week and £287.67/week
What happens nextCommencement within 2 yearsStandard 3 year time limit reduced to 2 years to speed affordable delivery
Who it affectsBritish Red Cross site, Croxley GreenCommunity Way, Croxley Green, Herts WD3 3HB
What was decided
Planning permission was approved subject to conditions, with officers adding an informative drawing the applicant's attention to the council's Housing Allocations Policy. A note confirmed that properties on the council's Housing Register are allocated across the district, with no preferential treatment for any one area.
Why
The scheme provides 100 percent affordable housing on site, all as affordable rent capped at Local Housing Allowance rates, which meets an acute local need and outweighs the absence of social rented units, the lack of which the committee accepted as a technical departure from Policy CP4. Report P47, P48, P135, P136, P137, P138
The design, height and massing were considered acceptable for this prominent corner site within the primary shopping area, with materials, landscaping and energy measures secured by condition. Highways and fire consultees raised no objections, subject to conditions and a Section 278 agreement. Report P121, P122, P123, P124, P125, P40, P41, P42, P166, P167
What happens next
Conditions require detailed designs and implementation of offsite highway works on Barton Way and Community Way, a Construction Management Plan, materials and landscaping details, swift brick installation, and a community use opening hours plan. The applicant must enter into a Section 278 agreement with Hertfordshire County Council. Report P8, P9, P10, P11, P12, P13, P14, P15, P17, P164, P156
The money
£218.63 per week Current LHA rate for a 1 bed unit in this postcode Report P136
£287.67 per week Current LHA rate for a 2 bed unit in this postcode Report P136
Options considered
Chosen: Approve planning permission subject to conditions (officer recommendation). 100% affordable housing, policy compliant community use, acceptable design and highways impact; social rent shortfall offset by LHA cap and faster 2 year commencement Report P129, P130, P137, P138
Implications
Legal: The community use must remain in F2(b) (halls or meeting places) and the office in Class E(g)(i); a Section 278 agreement with the Highway Authority is required for the crossovers and crossing point. Report P105, P17, P8, P9, P10, P11
Equalities: Three of the eight residential parking spaces are designed to be M4(2) compliant, and the building is in a sustainable location close to bus and rail links and Public Open Space. Report P177, P31, P154
Climate: The development is required to deliver 59% carbon savings against Building Regulations Part L (2013), using Air Source Heat Pumps and Solar PV panels, with details reserved by condition. Swift bricks must be installed to a specified standard. Report P185, P164
Risk: There is a parking shortfall of 6.5 residential spaces and up to 16 community spaces against Appendix 5 standards; officers judged this acceptable given the sustainable location, parking restrictions and secured cycle parking. Report P174, P177, P178, P179
Other: Seventy one objections were received on grounds including scale, overlooking, noise, parking, loss of community facility and construction impact; a petition request to treat the existing building as an asset of community value only to facilitate demolition was among them. Report P55, P57, P58, P59, P60, P61, P62, P63, P64, P65, P66, P67, P68, P69
Who and where
Future residents of 8 affordable rented flats (2 one-bed and 6 two-bed) capped at Local Housing Allowance rates Report P129, P136, P151, P152
Users of the new Croxley Green community centre and library, with a 264sqm community floor and 320sqm previously Report P102, P103
Neighbours on New Road and Barton Way, with 12m and 20m separation distances considered acceptable Report P146, P147
Hertfordshire County Council as Highway Authority, requiring a Section 278 agreement for new crossovers and a crossing point on Barton Way Report P8, P9, P10, P11, P17, P26
The applicant (British Red Cross site owner/developer)
Timeline
05.09.2025: Site notice posted Report P56
13.09.2025: Press notice published Report P56
2026-02-26: Planning Committee resolved to approve with conditions
Within 2 years of permission: Development must commence (reduced from standard 3 year time limit) Report P137
Plain English for the jargon
LHA: Local Housing Allowance, the rate used to calculate housing support for private renters; the affordable rents here are capped at these rates.
Section 278 agreement: A legal agreement under the Highways Act 1980 between a developer and the Highway Authority for works to be carried out within the public highway.
F2(b) use: Planning use class for halls or meeting places for the principal use of the local community.
ASHP: Air Source Heat Pump, a low carbon heating technology.
Biodiversity Net Gain: A planning requirement that development delivers a measurable net improvement for biodiversity.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPC106/25
Resolved
It was agreed that officers would add an informative to draw this to the applicant’s attention. (Note: subsequent to the meeting the Council’s Housing Team advised that properties advertised via the Council’s Housing Register are allocated strictly in accordance with the Council’s Housing Allocations Policy. Preferential treatment to residents from any particular area could not be offered / specified, as the local connection test applies district wide). Councillor Drury moved, and Councillor Lloyd seconded, ... view the full minutes text for item PC106/25
Word for word from the decision Three Rivers published for this meeting.Source: moderngov.threerivers.gov.uk
25/1943/FUL - Demolition of existing building and construction of a new three storey building to provide community centre at ground floor level and 8 residential units to the two upper floors with associated landscaping, access, and parking alterations at BRITISH RED CROSS, COMMUNITY WAY, CROXLEY GREEN, HERTS, WD3 3HB
Parish: Croxley Green Parish Council Ward: Dickinsons Expiry of Statutory Period: 13.02.2026 (EOT Case Officer: Lauren Edwards agreed 02.03.2026)
Recommendation: That Planning Permission be approved subject to conditions
Reason for consideration by the Committee: The applicant is Three Rivers Homes Ltd, a joint venture between Three Rivers District Council and Watford Community Housing.
Development type: Minor Dwellings
To view all documents forming part of this application please go to the following website:
25/1943/FUL - Demolition of existing building and construction of a new three storey building to provide community centre at ground floor level and 8 residential units to the two upper floors with associated landscaping, access, and parking alterations at BRITISH RED CROSS, COMMUNITY WAY, CROXLEY GREEN, HERTS, WD3 3HB
1 Relevant Planning History
1.1No relevant planning history.
2 Description of Application Site
2.1The application site is located on the corner of Barton Way and Community Way in Croxley Green. The site is currently occupied by a single storey flat roofed building that is currently in a community use. The building adjoins the Library to the south, the Library being sited on the corner of Barton Way and New Road. There is an existing car park to the west of the building, accessed from Community Way.
2.2This part of Croxley Green is characterised by a mixture of residential, commercial and retail uses.
2.3To the south of the site there are shops on New Road. Barton Way is characterised predominantly by pairs of semi-detached two storey dwellings. Community Way provides access to a public car park, there are also allotments to the north of Community Way. There are a number buildings (to the rear of properties in New Road) that have access directly onto Community Way including houses and flatted properties. Barton Way Recreation Ground is to the east of the site.
2.4Development within the area is predominantly two-storeys in height, however, there are existing single storey buildings (including the application building) and three-storey buildings within the vicinity fronting New Road, including opposite the junction with Barton Way.
3 Description of Proposed Development
3.1This application seeks planning permission for the demolition of existing building and construction of a new three storey building to provide a community centre at ground floor level and 8 residential units to the two upper floors with associated landscaping, access, and parking alterations. 3.2 The proposed residential units comprise of 2 x 1 bed flats and 6 x 2 bed flats with a community use retained at ground floor level. This would comprise of a community hall in an F2 use and also a Class E (g) (i) office use (which is intended to be occupied by Croxley Green Parish Council).
3.3The proposed building would have a square footprint (17.7 x 17.7m). The building would be three storeys in height with two mono pitched roofs at stepped heights. It would have a maximum height of 12m. A single storey side projection is also proposed to the north which would house the refuse store. This element would face Community Way and would have a depth of 3.5m and width of 6.8m (in line with the western flank). It would have a mono pitched roof with a maximum height of 3.5m.
3.4The proposal would provide 100% on site affordable housing in Affordable Rented tenure.
3.5The building would be finished in white render and buff brickwork with green windows, facias and rainwater goods to reflect the existing adjacent Library.
3.6The entrance to the community use would front Barton Way with the access to the residential units via Community Way.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
25/1943/FUL: Demolition of existing building and construction of a new three storey building to provide community centre at ground floor level and 8 residential units to the two upper floors with associated landscaping, access, and parking alterations at British Red Cross, Community Way, Croxley GrReport
PC106/2525/1943/FUL - Demolition of existing building and construction of a new three storey building to provide community centre at ground floor level and 8 residential units to the two upper floors with associated landscaping, access, and parkingThis decision
25/1943/FUL - Demolition of existing building and construction of a new three storey building to provide community centre at ground floor level and 8 residential units to the two upper floors with associated landscaping, access, and parkingThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.