AI summaryThree Rivers District Council's Policy and Resources Committee recommended that Full Council allocate £165,000 in capital funds for Aquadrome match funding if the Community Infrastructure Levy application fails, with Footpath 65 improvements at risk without the allocation [D] [1.6].
Written from the decision and the officer reportPDF Pro
OutcomeDecidedAllocation is conditional on levy failure [D]
Money£165,000 capital funds [D]Only needed if levy application fails [D]
What happens nextFull Council referral [D]Committee recommendation is referred onward [D]
Who it affectsAquadrome Project delivery [D]Footpath 65 improvements may otherwise be dropped [1.6]
What was decided
The Policy and Resources Committee recommended that Full Council allocate £165,000 of capital funds as match funding towards the Aquadrome Project if the Community Infrastructure Levy application is unsuccessful. Report 2.1
The recommendation would place £165,000 in the council's medium term financial plan for National Lottery Heritage Fund match funding if the Community Infrastructure Levy application fails. Report 1.5, 3.10
Public access to the report and the decision was agreed to be immediate. Report P8
Why
The National Lottery Heritage Fund expected the grant and match funding ratio to remain close to the original 75% and 25% split, while refined costs had moved it to 76% and 24%. Report 3.8, 3.9
The Lottery asked the council to provide direct match funding to demonstrate its support for the project. Report 3.7
Without direct match funding, Lottery support would be less likely, the delivery bid could be seriously jeopardised, and Footpath 65 was likely to be replaced with a more sustainable solution. Report P22, P23, P24
What happens next
Full Council will consider the recommended £165,000 capital allocation if the Community Infrastructure Levy application is unsuccessful. Report 2.1
Officers will apply to the Community Infrastructure Levy and continue seeking other match funding to reduce the requested capital amount. Report 3.10, 4.2
The council is preparing the Stage 3 Delivery Phase application, with staffing identified as a core funding element. Report 3.4, 9.2
The money
£165,000 Requested capital funding for Aquadrome match funding, conditional on levy application failure Report 2.1, 6.4
circa £5.6 million Total project cost Report 6.1
approximately £5 million Lottery grant request Report 6.1
approximately £1.5 million Total match funding required Report 6.1
just under: £1.4 million Total of other match funding applied for or secured Report 6.2, 6.3
circa £5 million Potential National Lottery Heritage Fund investment Report 1.2
Options considered
Chosen: Add £165,000 of council capital funding for Aquadrome match funding if the Community Infrastructure Levy bid fails.. It would strengthen the council's bid and positively affect the Lottery funding outcome, while officers continue seeking other match funding to reduce the request. Report 4.1, 4.2, 4.4
Rejected: Do not add £165,000 of council capital funding.. This would likely mean the loss of Footpath 65 and would jeopardise the successful funding bid. Report 4.3
Implications
Financial: The £165,000 request is outside the council's agreed budgets and is required only if the Community Infrastructure Levy application is unsuccessful. Report 5.4, 6.4
Financial: The project costs circa £5.6 million, with an approximately £5 million Lottery grant request and approximately £1.5 million in match funding required. Report 6.1
Risk: Without direct match funding, Lottery decision makers may be less supportive, the delivery application could be seriously jeopardised, and Footpath 65 is likely to be replaced with a more sustainable solution. Report P22, P23, P24
Legal: Proposed works and equipment will be tendered under council procedures, required permissions will be obtained, and the council must consider action that can further the general biodiversity objective. Report P51, 7.2
Equalities: Positive equal opportunities impacts depend on securing external funding, and accessibility features depend on the outcome of the Chilterns National Landscape Access for All grant programme. Report 8.1, 8.2
Climate: The climate change and sustainability impact assessment scored 3.7 out of 4, indicating a strong positive impact. Report P62
Staffing: Staffing will be a core part of the Delivery Phase funding application, following project specific posts funded during the Development Phase. Report 9.2
Other: Subject to securing Delivery Phase funding, activities will support health and wellbeing and local environmental education, while officers will seek to design out crime where possible. Report P66, P64
Who and where
Visitors to the Rickmansworth Aquadrome Report P39, P40
Community organisations and businesses operating from the Aquadrome Report P39
Leisure participants, including vulnerable participants Report P35, P40
Council staff delivering the programme Report 9.1, 9.3
Habitats and species at the Aquadrome Report 7.2, 7.3, P41
Timeline
Development Phase: Three Rivers was funded for Stage 2, passed the development review and was invited to develop the delivery submission. Report 3.4, 3.5, 3.6
Delivery Phase: The council is preparing a Stage 3 application that would deliver physical capital works on site. Report 3.4
Plain English for the jargon
Aquadrome: The council's Rickmansworth visitor site and improvement programme [3.1] [P39].
National Lottery Heritage Fund: The heritage funder for the project, whose three stage process ends with physical works in Stage 3 [3.4].
Community Infrastructure Levy: A funding pot to which officers will apply for Aquadrome match funding [3.10].
Match funding: The share of project funding provided alongside the Lottery grant, originally 25% and currently 24% [3.8] [3.9].
Development Phase: Stage 2 of the Lottery process, including detailed cost refinement and the review that confirmed continued support [3.4] [3.5] [3.6].
Delivery Phase: Stage 3 of the Lottery process, covering the funding application and physical works [3.4].
Footpath 65: The Causeway between Bury Lake and Stockers Lake, likely to be replaced with a more sustainable solution if match funding is not increased [P24].
Medium term financial plan: The council plan in which the £165,000 is proposed if the Community Infrastructure Levy application fails [1.5] [3.10].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPR824
Resolved
That: · The Policy and Resources Committee recommends to Full Council that £165,000 of capital funds be allocated to be used as match funding towards the Aquadrome Project as detailed at point 1.5 and between points 3.7 and 3.10, should a funding application to the Community Infrastructure Levy be unsuccessful. · That public access to the report be immediate. · That public access to the decision be immediate.
Word for word from the decision Three Rivers published for this meeting.Source: moderngov.threerivers.gov.uk
1.1During the Development Phase review with the National Lottery Heritage Fund, the account managers informed Officers that whilst they expect project costs for Delivery Phase to increase due to detailed design work, they would also expect to see income/match funding increase.
1.2Particularly of note, as the Lottery are potentially investing a significant amount of money into the project (circa £5 million), they would expect to see Three Rivers District Council contributing capital towards the total project cost.
1.3The percentage of funding between the Lottery and match funding must remain similar to that which was submitted as part of the Development Phase budget. This was 75% from the Lottery and 25% from match funding. As costs have increased, these percentages have changed and the level of match funding required also needs to increase to balance the percentages.
1.4Officers have explored all avenues of funding available for the project, including securing funds from Affinity Water, the HS2 Colne Valley Additional Mitigation Panel (AMP) and the Chilterns National Landscape – Access for All funding. There remains, however, a shortfall
1.5Officers will also be applying to the Community Infrastructure Levy funding pot, however, should this be unsuccessful it is recommended that £165,000 is included in the Medium-Term Financial Plan for use as match funding towards the National Lottery Heritage Fund.
1.6Should additional income not be secured, delivery costs will need to be reduced, which means key aspects of the project (Improvements to Footpath 65 – the Causeway between Bury and Stockers Lakes) will not be delivered.
Recommendation
2.1That the Policy and Resources Committee recommends to Full Council that £165,000 of capital funds be allocated to be used as match funding towards the Aquadrome Project as detailed at point 1.5 and between points 3.7 and 3.10, should a funding application to the Community Infrastructure Levy be unsuccessful.
That public access to the report be immediate. That public access to the decision be immediate.
Report prepared by: Charlotte Gomes, Head of Leisure and Natural Infrastructure
2 3 Details
3.1The Rickmansworth Aquadrome Management Plan 2022 – 2027 is an ambitious and far-reaching plan. As a result of the Plan, the Rickmansworth Aquadrome Programme was established to support its delivery.
3.2The council have been exploring funding opportunities and have so far secured match funding from the HS2 Colne Valley Additional Mitigation Plan and from Affinity Water. Chilterns National Landscape have also provided a letter of support, outlining their commitment to support funding from the Access for All funding stream for the Changing Places Toilet, Tactile Site Map and a 360- degree tour of the site – all in place to improve the accessibility for visitors with additional needs.
3.3The council has also been successful in securing and engaging with the National Lottery Heritage Fund (NLHF) as part of their Heritage Fund.
3.4The NLHF is a 3-stage process. Three Rivers has successfully progressed through Stage 1, the initial Expression of Interest, has been accepted and funded by NLHF for Stage 2, the Development Phase, and is preparing to bid for funding under Stage 3, the Delivery Phase. The final, third, phase is when capital works (physical improvements on site) will be delivered.
3.5As part of the Development Phase period, a key milestone is the Development Phase Review – this is when the Lottery will determine whether or not the project remains viable and if there continues to be support for the council to progress towards the next stage, which is submission of the Delivery Phase funding application.
3.6Positively the council passed this review and have been invited to continue to develop the delivery round submission.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Monitoring Report to 30 June 2026· That the revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4. 1. 4 be approved and in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.