Housing Overview and Scrutiny Committee, Tuesday 17 November 2020 at 7.00pm

Sheltered Housing Decommissioning - Alexandra Road and Dunlop Road

Noted Scrutiny 1 paper

Housing Overview and Scrutiny Committee noted this item on Tuesday 17 November 2020. Below is the council's own wording, with the papers it was decided on.

Item27

Resolved

Housing Overview and Scrutiny Committee noted and commented on: 1.1. the proposal to decommission the Sheltered Housing properties at Alexandra Road and Dunlop Road in Tilbury. 1.2. the proposal to implement a local lettings plan for the new housing development for older people at Calcutta Road which gives priority to tenants affected by the above proposed decommissioning.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Housing Overview and Scrutiny Committee

Executive summary

This report sets out the proposals for the future of the Alexandra Court Sheltered Housing complex in Tilbury, comprised of 36 properties at Alexandra Road and four properties at Dunlop Road.

The report outlines the options which were considered relating to accessibility to the communal blocks at this complex, as well as the opportunities which are available through one of the Council’s current new build schemes at Calcutta Road, Tilbury.

1. Recommendation(s)

Housing Overview and Scrutiny Committee are asked to note and comment on:

1.1the proposal to decommission the Sheltered Housing properties at Alexandra Road and Dunlop Road in Tilbury.

1.2the proposal to implement a local lettings plan for the new housing development for older people at Calcutta Road which gives priority to tenants affected by the above proposed decommissioning.

2. Introduction and Background

2.1In March 2019 a report was produced which considered the condition of communal entrance points in the Sheltered Housing complexes across the council’s housing stock. This review included the 36 properties at Alexandra Road and the four properties at Dunlop Road, which collectively form the 

‘Alexandra Court’ Sheltered Housing complex in the Tilbury Riverside and Thurrock Park ward.

Residents are being supported to live independently in Sheltered Housing properties for longer and later in life than they may have been able to historically. Whilst this is positive, as people age and their mobility reduces they may face additional challenges due to the condition of the communal access points for their homes, which subsequently impacts upon their quality of life and independence.

2.2The reviews which were carried out assessed the level of accessibility for each block and communal entrance point in the context of the Equality Act 2010 as well as against the ideal standards as set out in the Building Regulations 2010 Part M: Access to and use of Buildings; Volume 1: Dwellings; M4(2) Category 2: Accessible and adaptable dwellings.

In some cases, where dwelling or communal area accessibility is identified as being below the standard which the council is aiming to achieve across all its Sheltered Housing complexes, the work to rectify the issue is relatively straight-forward. In other instances there are significant constraints which hamper the identified remedial work, and this is the case at Alexandra Court.

2.3Approximately 400 metres from the Alexandra Court Sheltered Housing complex, construction is currently underway for a new development of 35 council-owned flats for older residents at Calcutta Road. The development, which will be called Beaconsfield Place, will have 31 one-bedroom flats and 4 two-bedroom duplex flats, and these are due to be completed in Summer 2021.

This development will have indoors communal spaces, private communal gardens for residents, ample parking and mobility scooter storage. The support of a sheltered housing officer will be provided at this new development.

3. Issues, Options and Analysis of Options

3.1The assessment of the access to the blocks at the Alexandra Court Sheltered Housing complex indicated that they do not currently meet the accessibility standards which the council is aiming to achieve. The options which have been considered include:

A. undertaking the identified work to bring the blocks in line with the standard

B. maintaining the current level of block accessibility below the required standard and retain the complex as a Sheltered Housing scheme

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sheltered Housing Decommissioning: Alexandra Road and Dunlop RoadReport 258 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 14 attended
LS
Councillor Luke SpillmanChair, present
CB
Councillor Chris BakerVice-Chair, present
QA
Councillor Qaisar AbbasCommittee Member, present
CC
Councillor Colin ChurchmanCommittee Member, apologies
JR
Councillor Joycelyn RedsellCommittee Member, present
LW
Councillor Lynn WorrallCommittee Member, present
LM
Lynn Mansfield, Housing Tenant RepresentativeCo-Optee, present
CH
Carol HinvestOfficer, in attendance
DM
David MooreOfficer, in attendance
DA
Dulal AhmedOfficer, in attendance
AD
Andrew DebnamOfficer, in attendance
RF
Ryan FarmerOfficer, in attendance

All 14 on the meeting page

On this subject at Thurrock

Search all
  1. Sheltered Housing Decommissioning - Alexandra Road and Dunlop RoadThis decision
  2. Sheltered Housing Decommissioning - Alexandra Road/Dunlop RoadApproved
  3. Out of Hours Procedures for Sheltered HousingDecided
  4. Sheltered Housing Changes to Service – UpdateNoted
  5. Sheltered Housing Decommissioning - Next stepsNoted

More from Thurrock Housing Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
5 Mar 2024 Findings of Stock Condition Survey of Housing PortfolioThe Housing Overview and Scrutiny Committee reviewed and provided comment and challenge as above with regard to; i.) ... Decided Open
5 Mar 2024 Update on Procurement of Strategic Delivery Partner for Housing Works1.1 Members noted the contents of the report. Noted Open
5 Mar 2024 Housing Revenue Account Review - to follow1.1 Members noted the contents of this report. Noted Open
5 Mar 2024 Teviot Avenue Nos - 158 - 228 (evens) - Demolition and Redevelopment - to followThe Committee commented above on the following: 1.1 The proposed site area for the redevelopment of numbers 158 – 228... Decided Open
15 Feb 2024 Update on Procurement of Strategic Delivery Partner for Housing Works1.1 Members are requested to note and comment on the contents of this report. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies