It was recommended that Housing Overview and Scrutiny Committee receive this report for information and comment. The Committee raised concerns over the recommendations of reports and felt that many were still for ‘noting’ following on from the Scrutiny Review Project of last year. They felt that recommendations needed to show actions and outcomes as discussed in the project’s workshop. They stated that comments from scrutiny committees were not added into Cabinet reports. Grace Le answered that she would look into this with her team.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report identifies and updates on the main focuses of the Garage Service developments and improvements over the last year.
Recommendation
1.1It is recommended that Housing Overview and Scrutiny Committee receive this report for information and comment.
2. Introduction and Background
2.1Thurrock Council holds a stock of 2275 garages and 290 garage plots located across the borough. The garages are brick or concrete purpose-built structures which are located in a number of settings varying from standalone blocks in large sites, to small isolated buildings on small sections of land, to garages located under town houses and blocks of flats. The garage plots are individual hard standings or section of land on which tenants construct their own garages structures or use the space for allocated parking. There are garage plots located on 27 sites across the borough.
2.2At the end of second quarter of 2021/22, there are 1936 garages let and 339 are void. Of these void garages, there were 86 are free to let and 201 are being held for major works such as structural repairs and roof replacements or are being considered for redevelopment. The remaining 36 are currently being repaired or awaiting clearance. An additional 17 lettings have been carried out in the first week of October.
2.3There are 252 garage plots let and 38 are void. Of these void plots, 6 are free to let and the other 32 are awaiting clearance.
2.4The scheduled programme of works set up to clear the historic backlog of void garages is largely completed. Since the last report in September 2020, 462 garages have been made void, checked, repaired, cleared and made ready for re-let. 376 of these garages have now been let and 86 are free to let. This has also involved carrying out more than 900 void inspections and post- repairs inspections. Figure 1 shows a breakdown of these 462 garages by status.
2.5We have been reviewing long term regeneration and development opportunities across the borough. As part of this process, the Council are currently in the process of procuring a professional consultancy practice to undertake a stock condition survey of the garage portfolio. This survey including a structural appraisal is anticipated to commence in early 2022 with a view of receiving the report around May 2022.
The detailed survey and appraisal will allow the Council to firstly ensure that the garage portfolio is being managed and maintained appropriately to ensure all of these assets are in a safe and secure condition. Additionally, the survey will allow the service to fully inform the housing service to take a holistic view of the garage portfolio and inform a longer term investment and management strategy. This strategy will also include a long-term view in regards to what assets can receive the appropriate level of long term investment, but also potentially identify garage sites that are not suitable for significant investment and can be considered for other uses that would better serve the community and the wider Thurrock borough.
3. Garage updates
3.1From the start of the garage repairs contract with Mears in April 2019, repairs and capital works has increased significantly. The table below indicates 2020/21 spend and 2021/22 forecast spend on capital works (i.e. roof replacements, new doors) and repairs (i.e. lock changes, door overhauls):
2020/21 2021/22 Forecast Year-end Budget Budget Year-end Budget Type spend spend £’000 £’000 £’000 £’000 Capital 212 205 507 507
Repairs & 75 93.81 75.75 75.75 Maintenance
In addition, the garages income generation in 2020/21 and 2021/22 is as set out in the table below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.