Housing Overview and Scrutiny Committee noted this item on Tuesday 10 January 2023. Below is the council's own wording, with the papers it was decided on.
1.1 The Housing Overview and Scrutiny Committee are invited to note and comment on the Council’s Voids Management Policy. 1.2 The Housing Overview and Scrutiny Committee are invited to note and comment on the Council’s Fit to Let standard. 1.3 The Housing Overview and Scrutiny Committee are invited to note and comment on the Council’s Voids Recharge Policy.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report is being presented to the Housing Overview and Scrutiny Committee to provide an update on the Council’s management of void properties within its housing stock.
The Current Voids Policy has been reviewed and updated from March 2022. The new policy and voids process has been implemented by the Housing Directorate.
1. Recommendation(s)
1.1The Housing Overview and Scrutiny Committee are invited to note and comment on the Council’s Voids Management Policy.
1.2The Housing Overview and Scrutiny Committee are invited to note and comment on the Council’s Fit to Let standard.
1.3The Housing Overview and Scrutiny Committee are invited to note and comment on the Council’s Voids Recharge Policy.
2. Introduction and Background
2.1Voids are unoccupied properties which often require repairs before being ready for let to new occupants. The Council’s objective is to make void properties available for letting as quickly as possible, minimising rent loss and maximising the housing available, whilst enabling our tenants to know that their home will be clean, safe, secure and comply with the Council’s fit to let standard. The policy applies to all properties held by the Council within its Housing Revenue Account and is triggered by a tenancy ending.
2.2The draft Void Policy ensures consistency of the standard of properties that we let to our tenants, working alongside the Housing Strategy and Asset Management Strategy. The policy will enable the Council to ensure its housing voids process, functions effectively by ensuring that all properties are available to our tenants at an acceptable standard, in line with the voids fit to let standard, by meeting the Council’s legal obligations and the terms of the Tenancy Agreement.
2.3The draft void policy had been drafted in accordance with the latest statutory and regulatory requirements and best practice. The policy confirms the aim of ‘delivering a clean, safe and secure property to incoming tenants, within our targets for turnaround times, standards and cost’. It therefore a high-level commitment to meeting resident expectations and the Council meeting challenging but realistic turnaround times between vacancies.
2.4As part of the void fit to let standard the Council carries out any essential routine repairs and/or health & safety checks that require completing prior to re-letting. The primary objective of the void process is to return the property for re-let in the shortest possible time with a “repair and safety check” process. In the past two years some additional elements have been added to the scope of works for the fit to let standard which include roof insulation, internal fire door replacement and installation of LD1 fire detection systems.
2.5Void properties with a history of damp and mould issues will have a specialist damp and mould survey undertaken. Any required repairs carried out to rectify, this could include damp treatment, building works or improvements made to the thermal efficiency of the property.
2.6The Council manages approximately 9840 rented homes of which an average of approximately 5.7% (558 properties) become vacant each year. The Council’s Void Team (CVT) re-let target for standard voids is currently set at 28 calendar days and 60 calendar days for major capital voids.
2.7Standard voids are generally carried out by the repairs and maintenance contractor (Mears) with major voids for the replacement of major elements within the property such as kitchens, bathrooms, roofing etc being undertaken by Wates.
2.8Sheltered Housing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.