1.1 Note the progress to 11 January 2024 against the Audit Plan 2023/24 as documented in Appendix 1. 1.2 Consider the Key Findings from the assignment, Embedded Risk Management Culture (INT2324-02) as documented in Appendix 1. 1.3 Consider the Key Findings from the assignment, Stock and Security Assurance (INT2324-03) as documented in Appendix 1. 1.4 Note Internal Audit’s quality checking of its earlier verification work associated with the Supporting Families Programme. (See paragraph 3.2.4) 1.5 Note and agree the revised scope for audit INT2324-17 – Governance Recovery Board , which is now retitled INT2324-17 – Change Board . (See paragraph 3.4.1) 1.6 Note and agree the deferral of the audits INT2324-22 – Talent Management and Retention , and INT2324-30 – Waste – Compliance with ISO requirements . (See paragraphs 3.4.2 and 3.4.3) 1.7 Note the inclusion of additional engagements (See section 3.5) 1.8 Note the verification of management actions associated with recommendations from 2018/19 and 2019/20 audit reports. (See paragraph 3.6.2 and Appendix 1) 1.9 Internal Audit are to provide a list of management actions from audit reports from 2020/21 engagements for the Committee to consider. (See paragraph 3.6.3) 1.10 Note Internal Audit’s depleted level of resources and its reliance on support from Mazars. (See section 3.7) 1.11 Note that Internal Audit expects to have completed or substantially completed 21 of its 33 ... view the full minutes text for item 77.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
The 6-month Internal Audit Plan 2023/24 was discussed and agreed by the Standards & Audit Committee at their meeting of 19th July 2023. This is the second progress report since that meeting and covers final reports issued, draft reports issued and work in progress.
Commissioner Comment:
Internal Audit received confirmation that the Commissioners were content with this paper.
1. Recommendation(s)
1.1Note the progress to 11 January 2024 against the Audit Plan 2023/24 as documented in Appendix 1.
1.2Consider the Key Findings from the assignment, Embedded Risk Management Culture (INT2324-02) as documented in Appendix 1.
1.3Consider the Key Findings from the assignment, Stock and Security Assurance (INT2324-03) as documented in Appendix 1.
1.4Note Internal Audit’s quality checking of its earlier verification work associated with the Supporting Families Programme. (See paragraph 3.2.4)
1.5Note and agree the revised scope for audit INT2324-17 – Governance Recovery Board, which is now retitled INT2324-17 – Change Board. (See paragraph 3.4.1) Version Control Version Committee – Final ready for submission to public committee 1.6 Note and agree the deferral of the audits INT2324-22 – Talent Management and Retention, and INT2324-30 – Waste – Compliance with ISO requirements. (See paragraphs 3.4.2 and 3.4.3)
1.7Note the inclusion of additional engagements (See section 3.5)
1.8Note the verification of management actions associated with recommendations from 2018/19 and 2019/20 audit reports. (See paragraph 3.6.2 and Appendix 1)
1.9Consider and accept, or otherwise, Internal Audit’s proposal not to verify implementation of management actions from audit reports from 2020/21 engagements. (See paragraph 3.6.3)
1.10Note Internal Audit’s depleted level of resources and its reliance on support from Mazars. (See section 3.7)
1.11Note that Internal Audit expects to have completed or substantially completed 21 of its 33 engagements by the end of March 2024. There are requests to defer two audits (see recommendation 1.6). The remaining ten audits will still be in their respective planning stages at the end of the financial year. (See section 3.8)
2. Introduction and Background
2.1The Accounts and Audit Regulations 2015 require that the Council, as a relevant authority, must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes taking into account public sector internal auditing standards or guidance.
2.2The Internal Audit Service carries out the work to satisfy this legislative requirement and part of this is reporting the outcome of its work to the Standards & Audit Committee.
2.3The Standards & Audit Committee has a responsibility for reviewing the Council’s corporate governance arrangements, including internal control, and formally approving the Annual Governance Statement. The audit work carried out by the Internal Audit Service is a key source of assurance to the Standards & Audit Committee about the operation of the internal control environment.
2.4The audits contained in the Internal Audit Plan 2023/24 are based on an assessment of risk for each system or operational area. The assessment of risk includes elements such as the level of corporate importance, materiality, service delivery/importance and sensitivity.
3. Issues, Options and Analysis of Options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal Audit Protocol- Item to follow1.1 That the Standards and Audit Committee agree that the Internal Audit Protocol provides the Council and the Intern...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.