Quarter 2 Forecast Revenue and Capital Outturn Report

Noted Scrutiny 7 papers

Place Overview and Scrutiny Committee noted this item on Wednesday 8 January 2025. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

Note and comment on the council’s Service position and forecast overspend position as at quarter 2 of £2.722m, representing a reduction of £0.348m on the position presented at quarter 1. Note and comment on the council’s overall position and forecast overspend position at quarter 2 of £1.896m, representing a reduction of £0.209m on the position presented at quarter 1. Note the approval of the transfer of £1.381m reserves to a MTFS Delivery Reserve and £1.5m to an Adult Social Care & Children’s Social Care Demographic Risk Reserve (as per section 14 of Appendix 1 and 4.7 below) approved at Cabinet 11th December 2024. Note and comment on the progress made on delivery against the savings target for 2024/25 and the remaining red (unachievable) rated savings. Further to an in-depth review and re-profiling of the General fund capital projects, to note and comment on the capital programme, and the anticipated General Fund Capital Programme slippage of £30.627m and £10.157m HRA Capital Programme slippage projected in the report. Note the approval of the addition of the DEFRA grant funding in the capital programme (as per section 16 of Appendix 1 and 4.12 below) approved at Cabinet 11th December 2024.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Place Overview and Scrutiny Committee

8 January 2025 ITEM: 8

Place Overview and Scrutiny Committee

Q2 Forecast Revenue and Capital Outturn Report

Wards and communities affected: Key Decision:

All Wards Key

Report of: Sima Khiroya, Assistant Director Financial Management & Procurement

Corporate Director: Chief Financial Officer S151

Lead Cabinet Member(s): Cabinet Member for Resources

This report is Public.

Final Version

1. Executive Summary 1.1 This report sets out the estimated forecast revenue outturn position for 2024-25 for the General Fund, Housing Revenue Account (HRA) and Dedicated Schools Grant (DSG) and provides an update on delivery against the savings target for 2024-25 at quarter 2.

1.2The total service position is showing a £2.722m net overspend position against a general fund budget of £172.398m at the end of quarter 2 (Period 6) for 2024/25. The overall position is showing significant pressures in Place (£1.919m overspend) and Corporate Services (£1.181m overspend). The movement between quarter 1 and quarter 2 is a reduction in net service expenditure of £0.348m.

1.3The actual reduction in gross expenditure for services between quarter 1 and quarter 2 is £0.741m, however, there has also been a reduction in the projected transfer from reserves by £0.393m, resulting in the net position reducing by £0.348m.

1.4The 2024/25 budget was set assuming exceptional financial support being required from central government in the amount of £68.570m. The position at quarter 2 shows a forecast additional pressure of £1.896m against this funding. There is an imperative that this pressure is managed by the end of the financial year.

1.5Services have been asked to take action to mitigate their pressures within the current financial year, where possible. Pressures that are ongoing into the next financial year, will be reflected in the MTFS Budget Setting process for 2025/26. 1.6 For the financial year 2020/21, the government introduced a one-off income loss scheme, the Covid Sales, Fees and Charges Scheme (SFC). This was intended to compensate local authorities for irrecoverable and unavoidable losses from sales, fees and charging income, generated in the delivery of services, that was impacted due to the Covid-19 pandemic. This covered loss of income in areas such as the registrars service, Grangewaters outdoor education centre, nurseries, parking charges etc. The compensation for income loss claims during the financial year 2020/21 were based on what was happening at the time, and as the financial year progressed, other corresponding reductions in expenditure and the impact of other funding released by the Government to compensate for loss of income and expenditure (such as the cultural grant for the Theatre and funding for staff on Furlough), meant we were in a position where we had overclaimed. The total value of claims that had been submitted during the financial year, based on the estimated income losses made at the time of the claims, amounted to £2.270m. After a full reconciliation as part of the financial year-end accounts, the total income loss that should have been claimed was calculated as £1.069m, resulting in an overclaimed amount of £1.202m. This amount has been provided for within available funding.

1.7The budget forecast at this stage in the financial year projects a total transfer from reserves to services of £12.024m (including £5.246m Transformation funding). In addition, an amount of £0.965m from previously received Contain Outbreak Management Fund Grant is being held in reserves and will be utilised to offset the overspend on Homelessness Services in the Place Directorate.

1.8Of the £19.866m savings target for 2024-25, £0.823m (4%) has been identified as unachievable at quarter 2 (red rating), following directorate deep dive reviews on all savings. At quarter 2, there has been a reduction on at amber savings (at risk) from 19% to 10% (£3.863m at quarter 1 to £2.008m at quarter 2). The values for savings on track and mitigated have increased between quarters 1 and 2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 2 Budget Monitoring Report 2024-25Appendix 1 1.2 MB Download
PDF
.1 GF Earmarked Reserves Quarter 2Appendix 2 174 KB Download
PDF
.2 HRA Earmarked Reserves Quarter 2Appendix 2 118 KB Download
PDF
MTFS Savings Tracker Quarter 2Appendix 3 203 KB Download
PDF
.1 GF Capital Monitoring Report Quarter 2Appendix 4 441 KB Download
PDF
.2 HRA Capital Monitoring Report Quarter 2Appendix 4 89 KB Download
PDF
Quarter 2 Forecast Revenue and Capital Outturn ReportReport 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 13 attended
GB
Councillor Gary ByrneChair, present
RJ
Councillor Roy JonesVice-Chair, present
PA
Councillor Paul ArnoldCommittee Member, present
DC
Councillor Daniel ChukwuCommittee Member, present
DD
Councillor David DayCommittee Member, present
AG
Councillor Aaron GreenCommittee Member, apologies, sent representative
MH
Councillor Mark HurrellCommittee Member, present
TK
Councillor Tom KellyCommittee Member, present
SL
Councillor Steve LiddiardCommittee Member, present
SS
Councillor Sue ShinnickCommittee Member, present
CS
Councillor Cathy SistersonCommittee Member, present
SH
Sue Hodgson, Housing Tenant RepresentativeCo-Optee, present

All 13 on the meeting page

On this subject at Thurrock

Search all
  1. Quarter 2 Forecast Revenue and Capital Outturn ReportThis decision
  2. 2023/24 Quarter 2 Forecast Revenue and Capital Outturn (Decision: 110685)Noted
  3. 2023/24 Quarter 1 Forecast Revenue and Capital Outturn (Decision: 110666)Noted

More from Thurrock Place Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
26 Mar 2026 Briefing Note - Update on Tilbury Dust IssuesThat the Place Overview and Scrutiny Committee noted the update received. Noted Open
6 Jan 2026 Call-in to Cabinet Decision: LGA Social Housing Peer Review (HRA Landlord Services)The Place Overview and Scrutiny Committee reject the call-in allowing the Cabinet decision to proceed. 2. The Place O... Refused Open
6 Jan 2026 Verbal Update - Brisbane HouseThe Place Overview and Scrutiny Committee noted the verbal update. Noted Open
6 Jan 2026 Housing Fire Safety Policy and Building Safety PolicyReview and note the updated Housing Fire Safety Policy (Appendix 1) to take effect immediately for a period of three ... Noted Open
6 Jan 2026 Approach to Tackling Damp and Mould in Social HousingThe Committee noted and commented on the contents of this report. Noted Open