Place Overview and Scrutiny Committee decided this item on Thursday 26 June 2025. Below is the council's own wording, with the papers it was decided on.
RESOLVED That the Place Overview and Scrutiny Committee: Support the council’s engagement with National Grid in preparation for the submission of the Norwich to Tilbury Development Consent Order application. Councillor Cherry returned to the Chamber at 7.20pm
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report details the council’s engagement so far with National Grid on the project titled Norwich to Tilbury. The report details the plan for future engagement. The O&S Committee is sought to recognise this work and agree the need to continue engagement with the project.
Recommendations
For the reasons set out in this report, the O&S Committee is recommended to:
2.1Support the council’s engagement with National Grid in preparation for the submission of the Norwich to Tilbury Development Consent Order application.
3. Commissioner’s Comments
3.1There have been no commissioner’s comments received for this report.
4. Proposals – the rationale and evidence for the recommendations
Background and drivers
4.1National Grid is proposing, under the project titled Norwich to Tilbury, to construct new high voltage power lines to increase the grid’s capacity to transfer electricity from the east coast, where a large increase in renewable energy production is expected over the next five years, to Tilbury, where it can connect to the existing infrastructure. 4.2 In Thurrock, this is likely to include: i) The construction of new pylons and overhead 400kV cabling, entering in the north of the borough, east of Bulphan, passing to the west of Horndon on the Hill, and finishing north of Linford. ii) The construction of a new substation just north of Linford. iii) The installation of underground cabling near the new substation to replace some existing overhead cabling, to avoid crossing with the new overhead cables coming out of the substation. iv) The modification of a section of existing overhead cabling around Chadwell St Mary and Linford, to increase capacity, and the temporary installation of a separate overhead line to facilitate this modification. A map of the proposals in Thurrock is included in Appendix 1, and a map showing the intersection with the order limits for the Lower Thames Crossing is included in Appendix 2. 4.3 The scale and national significance of the project mean National Grid must apply for a Developmental Consent Order (DCO) which will be judged by the Planning Inspectorate. Thurrock Council, as a local planning authority, will be asked by the Planning Inspectorate to provide an evaluation of the impacts of the proposed scheme to the borough, to be considered in the examination.
4.4National Grid is aiming to submit the DCO in August 2025, and to finish construction of the project in 2031.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.