Tilbury-Gravesend Ferry Task and Finish Group

Agreed Scrutiny 3 papers

AI summaryThurrock Place Overview and Scrutiny Committee agrees to set up a 10-week Task and Finish Group from early 2026 to examine the future of the Tilbury-Gravesend Ferry, with four councillors and a report due by March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed10-week review of Tilbury-Gravesend Ferry closure
MoneyNot stated
What happens nextInaugural meeting on 3rd December 2025Final report due to Place O&S on 26th March 2026
Who it affectsTilbury-Gravesend ferry users and operatorsLocal residents, businesses and community groups

What was decided

The Committee agreed to launch a 10-week time-limited Tilbury-Gravesend Ferry Task and Finish Group starting in the new year (2026), with members invited to comment on and suggest amendments to the draft Terms of Reference and Scoping Document.

Members of the Committee agreed the size and membership of the Task and Finish Group, set at four elected members drawn from the Conservative, Labour and Independent groups. Report P4

Why

The Group will look into the background and rationale for the previous closure of the ferry service and analyse the 2024 consultation responses on the impact of that closure. Report P2

It will also seek the views of internal and external stakeholders and explore potential options for a ferry service, including their financial and strategic viability. Report P2

What happens next

The Group is expected to complete its tasks by 20th February 2026, with a final report presented to the Place Overview and Scrutiny Committee on 26th March 2026. Report P6

An inaugural meeting on 3rd December 2025 will be used to identify key questions and agree a project plan, followed by a site visit to the ferry terminals between 15th and 19th December 2025 and 5th to 9th January 2026. Report P7, P11

Between 12th and 30th January 2026 the Group will hold a witness or information-gathering session with local residents, community groups and businesses, and meet with Kent County Council and potential partners or operators. Report P11

Options considered

  • Rejected: Reinstatement under previous model with revised subsidy Report P7, P11
  • Rejected: Partnership operations Report P7, P11
  • Rejected: Private operations Report P7, P11
  • Rejected: Replacement with enhanced bus or active travel links Report P7, P11

Implications

  • Governance: The Task and Finish Group has no executive power; all findings and recommendations will be referred directly to the Place Overview and Scrutiny Committee. Report P9
  • Other: The Group will consider cost implications, funding sources (including central government, levelling-up funds and green transport initiatives), legal implications and long-term sustainability, using RAG or SWOT analysis to evaluate each option. Report P7, P11

Who and where

  • Local residents, community groups and businesses affected by the closure of the Tilbury-Gravesend ferry Report P2, P7
  • Commuters, tourists and other users who previously relied on the ferry Report P11
  • Kent County Council and potential future partners or operators of the ferry Report P7, P11
  • Thurrock Council directorates covering transport, finance, regeneration and legal Report P7

Timeline

  • 3rd December 2025: First meeting of the Task and Finish Group to look at the overview of the Group and draft and scope themes and key areas to be discussed. Report P7
  • 1st to 12th December 2025: Inaugural meeting, agree project plan, review existing documents and receive written briefings from relevant directorates. Report P11
  • 15th to 19th December 2025 and 5th to 9th January 2026: Site visit to Tilbury and Gravesend ferry terminals and analysis of the 2024 consultation and 2025 consultant's report. Report P11
  • 12th to 30th January 2026: Witness or information-gathering session with residents, community groups and businesses, and meeting with Kent County Council and potential partners or operators. Report P11
  • 2nd to 13th February 2026: Compare alternative options and models for a future ferry service, assess cost implications, funding sources, sustainability goals and alignment with transport strategies. Report P11
  • 16th to 20th February 2026: Draft findings and recommendations and final report outlining the Group's recommended option for the future of the ferry service or alternative transport connectivity. Report P11
  • 20th February 2026: Expected completion date for the work of the Task and Finish Group. Report P6
  • 26th March 2026: Final report to be presented to the Place Overview and Scrutiny Committee. Report P6

Plain English for the jargon

  • Task and Finish Group: A short-term scrutiny group set up to investigate a specific issue and report back with findings and recommendations.
  • Place Overview and Scrutiny Committee: A Thurrock Council committee that reviews decisions and policies relating to place-based services such as transport, environment and regeneration.
  • RAG analysis: Red, Amber, Green rating tool used to assess the status or risk of options or actions.
  • SWOT analysis: A framework for evaluating the Strengths, Weaknesses, Opportunities and Threats of an option or proposal.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26

Resolved

Agreed to commence a 10-week time limited in the new year (2026). Comment and suggest relevant amendments to the draft Terms of Reference (Appendix 1) and Scoping Document (Appendix 2), in accordance with the updated Overview and Scrutiny Protocol and Thurrock Council’s Constitution. Members of the Committee agreed the size and membership of the Tilbury-Gravesend Ferry Task and Finish Group.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Place Overview and Scrutiny Committee

Terms of Reference Place O&S Task & Finish Group –Tilbury-Gravesend Ferry Task and Finish Group.

Purpose: • To seek to establish the background context and rationale for the previous closure of the ferry service. • To analyse the 2024 consultation responses regarding the impact of the closure of the ferry service on local residents, community groups, and businesses. • To review and understand the views and perspectives of relevant [internal and external] stakeholders. • To explore potential options for a ferry service, including considering the financial and strategic viability of any options identified. • Report the output of the above actions by the Group to the Place O&S Committee as to the Task and Finish Group’s preferred options for the future of the ferry service. The findings and recommendations of the Group to also be shared with other contributing stakeholders.

The outcome of the Task & Finish Group will be to provide a final report detailing the evidence gathered and upon which its recommendations are based for presentation to the Place Overview Scrutiny Committee.

Membership: 4 elected members (X Conservative, X Labour, X Independent)

Chair: The Chair and Vice-Chair will be elected by the membership of the Task & Finish Group at its first meeting. The appointment will last until the work of the Task & Finish Group is complete.

Duration: The Task & Finish Group will be established with the expectation to complete its tasks by 20th February 2026. A report will be presented to the Place Overview and Scrutiny Committee on the 26th March 2026.

Meeting Schedule: The Task & Finish Group will meet on an ad-hoc basis, in line with the key dates proposed in the below table. The first meeting on 3rd December will look at the overview of the Group and draft / scope themes / key areas to be discussed. Activities: The Task & Finish Group will undertake all but not exclusively the following activities: • Hold an inaugural meeting to identify key questions to ask and agree the project plan. • Review existing documents such as Council/Cabinet/O&S reports and minutes, ferry operation contracts, performance reports from the operator, and any relevant transport strategies. • Receive written or verbal briefings from relevant directorates across the Council e.g. transport, finance, regeneration or legal. • Undertake a site visit to Tilbury-Gravesend ferry terminals to observe conditions and local connectivity. • Evaluate and analyse the 2024 consultation and consultants report to understand the impact of the ferry closure on residents, businesses and other external stakeholders. • Hold an information gathering or witness session inviting stakeholders such as local residents, community groups, or local businesses to feedback their perspectives of the ferry and impact of its closure. • Hold a meeting with representatives from Kent County Council and potential partners or operators to discuss options for the future of the ferry service. • Compare alternative scenarios for the future of the ferry service, such as reinstatement under existing model with revised subsidy, partnership operations, private operations, or replacement with enhanced bus or active travel links. • Assess the cost implications and funding sources, sustainability goals, and alignment with transport strategies. Use RAG or SWOT analysis to evaluate each option. • Draft findings and recommendations to Committee based on evidence, including the Task and Finish Group’s recommended option, for the future of the Gravesend-Tilbury ferry service or alternate transport connectivity.

These meetings and activities can be held during the day / evening, and Members will be required to attend as many meetings/activities as possible.

Decision-Making: The Task and Finish Group has no executive power, and all findings and recommendations will be referred directly to the Place Overview and Scrutiny Committee.

Timeline: As outlined within the below table.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Tilbury-Gravesend Ferry Task and Finish GroupReport 110 KB DownloadRead as text
PDF
Enc. 2 for Tilbury-Gravesend Ferry Task and Finish GroupReport 149 KB Download
PDF
Tilbury-Gravesend Ferry Task and Finish GroupReport 123 KB Download

At this meeting

Whole meeting

Who was there

7 of 10 attended
RJ
Councillor Roy JonesChair, present
JM
Councillor Jacqui ManeyVice-Chair, present
JC
Councillor John CecilCommittee Member, present
RC
Councillor Russell CherryCommittee Member, apologies
TK
Councillor Tom KellyCommittee Member, present
SL
Councillor Steve LiddiardCommittee Member, present
CM
Councillor Cici ManwaCommittee Member, present
SP
Councillor Srikanth PanjalaCommittee Member, apologies
CS
Councillor Cathy SistersonCommittee Member, present
SH
Sue Hodgson, Housing Tenant RepresentativeCo-Optee, expected

More from Thurrock Place Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
26 Mar 2026 Briefing Note - Update on Tilbury Dust IssuesThat the Place Overview and Scrutiny Committee noted the update received. Noted Open
6 Jan 2026 Call-in to Cabinet Decision: LGA Social Housing Peer Review (HRA Landlord Services)The Place Overview and Scrutiny Committee reject the call-in allowing the Cabinet decision to proceed. 2. The Place O... Refused Open
6 Jan 2026 Verbal Update - Brisbane HouseThe Place Overview and Scrutiny Committee noted the verbal update. Noted Open
6 Jan 2026 Housing Fire Safety Policy and Building Safety PolicyReview and note the updated Housing Fire Safety Policy (Appendix 1) to take effect immediately for a period of three ... Noted Open
6 Jan 2026 Approach to Tackling Damp and Mould in Social HousingThe Committee noted and commented on the contents of this report. Noted Open