Decision Notice D140031MEM The report provided an update on progress and set out a programme for the implementation of the scheme. Members noted that a start date on site was now anticipated for July 2014, which allowed the majority of the work to be completed during the summer months when working conditions were most favourable. Completion of the project would be around October/November dependent upon the contractor’s approved construction programme. In addition, the Advisory Board had every confidence that the objectives of officers were the same as local Members in getting the Town Lock area reinvigorated. RECOMMENDED : That the progress made towards implementing the Town Lock capital project be noted and the programme as set out in the report be approved.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report to Planning and Transportation Advisory Board
Background
1.1.1 I last reported to members on the Town Lock project at the meeting of this Board on 4 June 2013. At that time the detailed design was being finalised so that the scheme could be costed prior to inviting tenders for construction. Members may recall that, in the context of a fixed scheme budget, I had highlighted the possibility that elements of the design would need to be reviewed if the estimated cost exceeded that budget.
1.1.2 In the event, the estimate did indeed exceed the budget and so I was prevented from proceeding to tender stage. This is frustrating, but not uncommon, particularly with schemes involving features such as engineering near the river which are often difficult to cost. There followed a period of working with the Environment Agency and Halcrow, the designers, to redesign various elements of the scheme such that the costs could be reduced to an affordable level. This process has been necessarily time consuming in order to retain the essential project requirements and function without significant loss of overall quality. The scheme has now reached the limits of what can be achieved by ‘value engineering’ and so it is appropriate to now continue to tender to determine the ‘real’ cost of building the revised scheme.
1.2What has been done?
1.2.1 The scheme ‘plan’ has not had any fundamental changes, although individual elements of the scheme have been critically scrutinised to see how they might be provided in a less expensive way.
1.2.2 The key focus of the value engineering has been upon lighting and upon the flood wall. The lighting has been simplified such that there will be a ‘lit way’ through the
P&TAB-NKD-Part 1 Public 11 March 2014 2
scheme rather than an attempt to provide lighting to all areas of open space. This takes account of reflected light from adjacent buildings and is better in environmental terms such as light pollution and power consumption.
1.2.3 The reinforced concrete flood wall has been replaced for a significant part of the scheme by a masonry wall/earth bund composite structure which will be equally as effective. The brick cladding and coping to the remaining concrete flood wall has been deleted. Some railings have been deleted consistent with the existing similar areas in Medway Wharf Road.
1.2.4 Elsewhere, small changes have been made to a number of other elements which cumulatively will all help in reducing cost.
1.3Programme for Implementation
1.3.1 The revised drawings and tender documents are programmed to be completed by the end of March which will allow tenders to be received and analysed during May.
1.3.2 A start on site is now anticipated for July 2014, which will allow the majority of construction work to be completed during the summer months when working conditions are most favourable. Completion will be around October/November dependent upon the contractor’s approved construction programme.
Legal implications
1.4.1 None arising from this report.
1.5Financial and Value for Money Considerations
1.5.1 The scheme budget is currently fixed at £791,600, funded from a variety of sources including contributions from nearby development, funds from the Environment Agency and the Council’s own capital plan funding.
1.6Risk Assessment
1.6.1 There is still a risk that a tender will not returned within the available budget and a further review might prove necessary in those circumstances.
Recommendations
1.7.1 That Members NOTE the update on progress towards implementing the Town Lock capital project and APPROVE the programme as outlined.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Transportation Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.