Resolved
That the work to date on the High Street Improvements and the next steps, as set out in the report, be noted.
Joint Transportation Board noted this item on Monday 9 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the work to date on the High Street Improvements and the next steps, as set out in the report, be noted.
1.1.1 It was agreed by the Joint Transportation Board (JTB) in December that Kent County Council (KCC) would advance the agreed streetscape and traffic management improvements for the lower High Street to the detailed design and costing stage in the new year. This work is progressing well and the scheme has been included in the South East Local Enterprise Partnership (SELEP)’s Single Local Growth Fund submission to Government.
1.2Progress to Date
High Street improvements
1.2.1 In terms of the proposed physical improvement works, KCC commissioned its consultant, Amey, to progress the necessary detailed design and costing work for the lower High Street improvement scheme in January. To date, baseline traffic counts and pedestrian crossing surveys have been undertaken, which will inform the type and location of future crossing facilities and speed limits. A full drainage survey has recently been completed and an Environmental Scoping Assessment produced; the outcomes of which will feed in to the design process as appropriate. Amey’s detailed design commission will continue throughout the summer and the outcome of this work will be reported to the JTB later in the year, prior to local consultation taking place.
1.2.2 The High Street scheme formed part of the SELEP’s Strategic Economic Plan (SEP), which was submitted to Government at the end of March. The Plan outlines the region’s principal economic challenges and opportunities, together
JTB - Part 1 Public 9 June 2014 2
with its corresponding bid for a share of the Government’s Single Local Growth Fund (SLGF), which will be worth a total of £2 billion a year from 2015. It is expected that funding awards will be made to each of England’s 39 LEPs during Autumn 2014, which will enable the delivery of successful schemes to commence from April 2015.
1.2.3 Projects stand a significantly greater chance of securing SLGF funding if they are also able to attract financial contributions from local sources. With this in mind, discussions have been held with KCC’s Road Works Team, and it has been confirmed that the High Street scheme would be eligible to receive contributions arising from Lane Rental income. So, although there remains some uncertainty about the overall funding position, we are generally optimistic that the scheme will attract sufficient finance to enable implementation in due course.
1.3.1 None at this stage.
1.4Financial and Value for Money Considerations
1.4.1 None at this stage.
1.5Risk Assessment
1.5.1 Not required.
1.6Equality Impact Assessment
1.6.1 See 'Screening for equality impacts' table at end of report
1.7.1 The Board NOTES the work to date on the High Street Improvements and the next steps as set out in the report.
Background papers: contact: Chad Nwanosike/ Mike O’Brien Nil
Tim Read Head of Transportation
Steve Humphrey Director of Planning, Housing and Environmental Health
JTB - Part 1 Public 9 June 2014 3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tonbridge Town Centre Transport Strategy: UpdateReport | 35 KB | DownloadRead as text |
Follow Joint Transportation Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Dec 2024 | Parking UpdateThat the current progress and approach to the Parking Team’s work programme, be noted. | Noted | Open |
| 2 Dec 2024 | Parking Action Plan, Access Group 9That the decision of the Cabinet Member for Transformation and Infrastructure to set aside the objections attached at... | Noted | Open |
| 17 Jun 2024 | Scope of the Joint Transportation Board and local/public transportThat consideration be given to the scope of the Joint Transportation Board at the next meeting. | Decided | Open |
| 21 Nov 2022 | Proposed Single Yellow Line Waiting Restrictions - Oldbury LaneThat the Traffic Regulation Order for double yellow lines be implemented on Old Lane Only, as shown in the plan at Ap... | Decided | Open |
| 6 Jun 2022 | Proposed 40mph Speed Limit - B2016 Seven Mile Lane, MereworthThat the 40mph speed limit on the B2016, Seven Mile Lane, be implemented as shown on the plan at Appendix D to the re... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.