Decision Notice D140076MEM The joint report of the Director of Street Scene and Leisure and Cabinet Member for Leisure, Youth and Arts outlined progress in relation to the refurbishment of the Health Suite and the provision of LED lighting in the sports hall at Larkfield Leisure Centre. Details were given of the procurement process in respect of the former together with a proposed procedure for award of the contract in view of the timescale for the project. RECOMMENDED: That due to the construction timescale, authority for the award of the Health Suite Refurbishment Contract at Larkfield Leisure Centre be delegated to the Directors of Street Scene and Leisure and Central Services in consultation with the Cabinet Member for Leisure, Youth and Arts and the Chairman and Vice Chairman of the Leisure and Arts Advisory Board.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
1.1.1 Members will be aware that there are currently two schemes for Larkfield Leisure Centre funded within List A of the Capital Plan in the current financial year. The schemes are the refurbishment of the existing Health Suite (£240,000) and the installation of LED lights in the sports hall (£40,000).
1.2Health Suite Refurbishment
1.2.1 The original Capital Plan evaluation of the Health Suite refurbishment at [Annex 1] reported to Finance, Innovation & Property Advisory Board on 8 January 2014, identified the benefits of the scheme as maintaining Lifestyles membership and income levels, reducing maintenance costs and increasing customer satisfaction.
1.2.2 The Health Suite is currently in a poor condition with deterioration of the walls and floors, primarily due to the aggressive environment. Proposals to refurbish the health suite have been brought forward in liaison with the Tonbridge & Malling Leisure Trust and the Council’s Building & Facilities Manager. The proposals involve significant building works to restore the fabric of the facility to a fit condition, including stripping walls and floors back to the structure. Improvements to the ventilation system are also included within the refurbishment scheme and it is felt essential to protect the integrity of the health suite over the longer term.
1.2.3 The above works, together with the like for like replacement of existing features (sauna, steam room, spa baths) have been estimated to cost in the region of £220,000 plus fees and other associated costs (including contingency) of £20,000.
Leisure.ArtsAB-NKD-Part 1 Public 10 June 2014 2
1.2.4 Since the initial proposals were developed it has been identified from consultation with the customer panel and representatives from the Leisure Trust, that a better balance of features would be achieved by installing an ice room in place of the existing aromatherapy room.
1.2.5 The Building & Facilities Manager is progressing the procurement of the work on a design and build basis. Selection of the successful contractor will be based on the most economically advantageous tender using a price:quality ratio of 30:70 considering the following principal factors:
Criteria Weighting Price 30% Quality Design Experience 10% Proposed Layout and Design 30% Proposed Features 30%
1.2.6 The procurement process is being managed electronically through Dartford Borough Council. Following evaluation of prequalification questionnaires submitted by 17 companies the scheme is currently out to tender to the following seven companies:
1) Ash
2) Cosmur
3) Createability
4) Cablesheer
5) ITC Concepts
6) John Graham Construction
7) Coleman & James
1.2.7 The closing date for the return of tenders is Friday 13 June 2014 with initial evaluation taking place by Council Officers and representatives from the Leisure Trust.
1.2.8 It is currently anticipated that the contract will begin late June with a construction phase anticipated to finish by the end of September, allowing completion in advance of the winter months which are historically a busier time.
1.2.9 The Chief Executive of the Trust previously confirmed that the Trust would bear the loss of income associated with the originally predicted construction period of six weeks (circa £2-3,000) over the summer months of 2014. Now that detailed
Leisure.ArtsAB-NKD-Part 1 Public 10 June 2014 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Leisure and Arts Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.