CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tonbridge and Malling Borough Council
Leisure and Arts Advisory Board, Monday 15 September 2014 at 7.30pm

Indoor Leisure - Capital Plan Projects

Noted Committee 1 paper

Leisure and Arts Advisory Board noted this item on Monday 15 September 2014. Below is the council's own wording, with the papers it was decided on.

ItemLAA 14/34

Resolved

Decision Notice D140102MEM The joint report of the Director of Street Scene and Leisure and Cabinet Member for Leisure, Youth and Arts outlined progress in relation to the refurbishment of the Health Suite and the provision of LED lighting in the sports hall at Larkfield Leisure Centre. It was noted that since tenders received in respect of the Health Suite Refurbishment project were significantly above the pre-tender estimate, a fundamental review was being undertaken and options on the proposed way forward considered. However, the LED lighting project would be delivered within the approved budget with the Leisure Trust agreeing to reduce the annual service fee payable by the Council. RECOMMENDED: That a review of the Health Suite Refurbishment project at Larkfield Leisure Centre be considered by the Finance, Innovation and Property Advisory Board on 7 January 2015 as part of the Capital Plan Review process.
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Leisure and Arts Advisory Board

Background

1.1.1 Members will be aware that there are currently two schemes for Larkfield Leisure Centre funded within List A of the Capital Plan in the current financial year. The schemes are the refurbishment of the existing Health Suite (£240,000) and the installation of LED lights in the sports hall (£40,000).

1.2Health Suite Refurbishment

1.2.1 The original Capital Plan evaluation of the Health Suite refurbishment was reported to Finance, Innovation & Property Advisory Board on 8 January 2014, identifying the benefits of the scheme as maintaining Lifestyles membership and income levels, reducing maintenance costs and increasing customer satisfaction.

1.2.2 The Health Suite is currently in a relatively poor condition compared to other areas of the Centre with deterioration of the walls and floors. The works (excluding fees and contingencies), together with the like for like replacement of existing features (sauna, steam room, spa baths) were estimated to cost in the region of £220,000.

1.2.3 Further to the report on procurement of the works to this Board on 10 June 2014, tenders have now been received. Unfortunately, the lowest tender was £299,592, significantly above the pre-tender estimate.

1.2.4 Taking this into consideration a fundamental review of the project is now being undertaken in liaison with the Council’s Building & Facilities Manager and the Leisure Trust and options on the proposed way forward are being considered. The outcome of the review will be will be considered by the Finance, Innovation &

Leisure.ArtsAB-NKD-Part 1 Public 15 September 2014 2

Property Advisory Board on the 7 January 2015 as part of the Capital Plan Review process.

1.3LED lighting

1.3.1 A scheme to replace the existing light fittings in the Sports Hall at the Leisure Centre with LED fittings was identified as an “invest to save” scheme that will reduce energy consumption and lower costs. There are currently 120 fluorescent lamps in 60 fittings and the proposal is to reduce this to approximately 38 new LED high bay fittings.

1.3.2 The Sports Hall is in use for up to 16 hours per day, seven days a week and is consequently lit for over 5,000 hours per annum. The current lamps have a life expectancy of around 10,000 hours and are, therefore, generally replaced every two years with ad hoc replacements in between. Replacement of individual fittings is an onerous and time consuming task requiring a scaffold tower to be erected. The proposed LED fittings have a life expectancy of 50,000 hours.

1.3.3 The replacement will result in increased energy efficiency and extended life expectancy reducing maintenance costs. It is also planned to amend the wiring of the circuits to allow switching of individual courts and activation by motion sensor, which is not currently possible.

1.3.4 The Buildings & Facilities Manager has placed an order with the LASER energy group (a trading arm of Kent County Council) to procure and install the fittings and amend the circuits through a procurement framework, with installation expected to take place in September 2014. A verbal update on progress will be given at the Board.

1.3.5 The project will be delivered within the approved budget of £40,000. The Leisure Trust Board has agreed to reduce the annual Service Fee payable by the Council by £1,800 per annum upon completion. This saving will be reflected in revised revenue budgets.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Indoor Leisure: Capital Plan ProjectsReport 41 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 24 attended
MJ
Councillor Mrs Jeannett BellamyChairman, present
ME
Councillor Mrs Elizabeth HollandVice-Chair, present
TB
Councillor Timothy BishopCommittee Member, apologies
PB
Councillor Peter BoltCommittee Member, absent
MB
Councillor Mrs Barbara BrownCommittee Member, absent
TE
Councillor Tom Edmondston-Low BA (Hons)Committee Member, apologies
MJ
Councillor Miss Jessica ElksCommittee Member, absent
SJ
Councillor Simon JesselCommittee Member, present
DK
Councillor David KeeleyCommittee Member, present
RL
Councillor Russell Lancaster BA (Hons)Committee Member, present
MS
Councillor Miss Sophie ShrubsoleCommittee Member, absent
RT
Councillor Russ Taylor CEng, MIMarEST, Eur IngCommittee Member, present

All 24 on the meeting page

More from Tonbridge and Malling Leisure and Arts Advisory Board

All decisions
MeetingDecisionOutcome
24 Feb 2015 MinutesThat the notes of the meeting of the Leisure and Arts Advisory Board held on 8 December 2014 be approved as a correct... Approved Open
24 Feb 2015 Leisure Trust - Review of Core Charges and Annual Service Delivery PlanDecision Notice D150018MEM The joint report of the Director of Street Scene and Leisure and Cabinet Member for Leisur... Approved Open
24 Feb 2015 Leisure Facilities - Leisure Trust UpdateDecision Notice D150019MEM The joint report of the Director of Street Scene and Leisure and Cabinet Member for Leisur... Noted Open
24 Feb 2015 Tonbridge Farm Sportsground - User SurveyDecision Notice D150020MEM The joint report of the Director of Street Scene and Leisure and Cabinet Member for Leisur... Noted Open
24 Feb 2015 Capital Projects - Post Implementation ReviewsDecision Notice D150021MEM A Capital Plan Post Implementation Review was brought forward for consideration in respect... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies