Decision Notice D140135MEM The report provided an update on progress made on flood recovery within the Borough following the events over the Christmas/New Year period. Proposed measures to provide increased protection for local residents and businesses for the future were set out, with particular reference made to the partnership approach on the Leigh Flood Storage Area and the associated funding arrangements. Members expressed concern that the flood improvement measures would not be in place this winter and sought reassurance that the temporary solutions and contingency planning would be adequate in the event of a flood. In response, the Environment Agency’s (EA) commitment, at the highest possible level, to provide flood protection for Tonbridge and the surrounding area was reiterated. Officers were working closely with the EA on contingency planning but recognised the concerns of Members and residents. However, as the EA was the statutory body with overall responsibility the Borough Council recognised their expertise in dealing with flood improvement measures. RECOMMENDED : That (1) the position set out in the report, including a contribution of £100k from the Flood Recovery and Defence reserve towards an assessment of the options and the delivery of an outline design for the Leigh Flood Storage Area scheme, be noted and endorsed; and (2) Officers continue to liaise closely with the Environment Agency and put forward a clear representation of the Borough Council’s wish to pursue the most robust solutions in the case of all the proposed flood mitigation works.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report to Planning and Transportation Advisory Board
TONBRIDGE & MALLING BOROUGH COUNCIL
PLANNING and TRANSPORTATION ADVISORY BOARD
18 November 2014
Report of the Director of Planning, Housing and Environmental Health Part 1- Public
Matters for Recommendation to Cabinet - Non-Key Decision (Decision may be taken by the Cabinet Member)
1 FLOODING UPDATE
This is a progress report on flood recovery within our borough following the events over the Christmas/New Year period and presents the Newsletter prepared for residents of these affected communities.
1.1Introduction
1.1.1 This report provides an update on the aspects and issues relevant to our involvement in the flood recovery and attached to the report is the multi-agency Technical Group Newsletter which is being distributed to residents across the flood affected areas of the borough.
1.2Multi-Agency Recovery Strategy
1.2.1 Members will be aware that we have been participating in the county-wide Strategic and Tactical Recovery Coordinating Groups throughout the year which are chaired by Kent County Council. The aim of these groups is to work in partnership to support affected individuals, communities and organisations to recover from the floods and to return to a state of normality. Many of our residents are now back in their homes however at the start of this month there were still 32 properties where extensive repairs have been needed following the flood damage and are still not complete. These houses remain unoccupied.
1.3The Multi-Agency Technical Working Group
1.3.1 The Technical Working Group was set up in February following the various public engagement meetings across the Borough. It consists of representatives from the organisations with an involvement in flood risk management and has been working consistently throughout the year to ensure that existing flood defence systems are sound and the sewer systems and drains are as functioning as intended.
1.3.2 In addition to this the Environment Agency is working on some key flood defence projects and we have been liaison closely on a range of design matters with them.
P&TAB-NKD-Part 1 Public 18 November 2014 2
When implemented these measures will provide increased protection for local residents and businesses. The schemes are:
• Avebury Avenue, Tonbridge flood defence – this project is in the planning stages and the Environment Agency hope to start construction in early 2015
• Hildenborough flood defence – construction is planned to take place in the summer of 2015
• East Peckham and Little Mill – the Environment Agency hope to be able to progress this project in 2015/16
• Leigh Flood Storage Area – there will be a partnership approach to developing this project which will increase the capacity within the Leigh Flood Storage Area. This will be formed of the Environment Agency, KCC and TMBC. TMBC has agreed to contribute £100k from the “Flood Recovery and Defence” reserve we set up at the end of last year for an assessment of the options and the delivery of an outline design. Maidstone Borough Council will also participate in this project with a view to reducing flood risk at Yalding. We are working on a legal agreement to formalise this approach. The Borough Council will also be party to a bid to the Local Enterprise Partnership (LEP) for capital funding towards this project to ensure that it is constructed as soon as possible.
1.3.3 Further information relating to each of these projects can be found in the Technical Newsletter in Annex 1.
1.4Flood Wardens
1.4.1 A second training session for Flood Wardens was held at Kings Hill on 18 October. This has reinforced the Flood Warden numbers in Hildenborough and East Peckham and we now have six trained Flood Wardens in Tonbridge.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Transportation Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.