That (1) the results of the public engagement be noted; (2) the High Street scheme and the 20mph speed limit proposals be progressed to detailed design and implementation and construction programmed to commence in late July 2015; and (3) the Traffic Regulation Order to reduce the speed limit in the High Street area to 20mph be made as advertised.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
1.1.1 As reported to the Joint Transportation Board in September and December 2014, the outline design for the Tonbridge High Street scheme has been progressed and a public engagement carried out to gain views from the public regarding the proposal.
1.1.2 £2.65 million pounds of funding is available for the overall project made up of £2.4 million from the Government’s Single Local Growth Fund and £250,000 from capital receipts towards the aims of:
Boosting the local economy
Providing a more attractive environment
Reducing traffic congestion
Improving air quality
Providing improved pedestrian and cycle facilities
Improving bus journey times
1.1.3 A briefing was held for local County and Borough Members on 21st January 2015 to ensure they were informed prior to the start of the public engagement. The
JTB - Part 1 Public 30 March 2015 2
team taking forward the scheme were introduced and details of the proposed scheme were explained.
1.1.4 The scheme is being developed in partnership with Tonbridge and Malling Borough Council (TMBC), key elements of which are:
Widened footways and a raised speed table
Defined delivery areas level with the footways
A 20mph speed limit
Environmental improvements
Quality street furniture
1.1.5 As part of the briefing, Members were informed of the intended communications strategy to support the public engagement. The intention of which being to raise awareness locally to ensure as many could put forward their views on the proposed scheme. A summary of the public engagement follows below.
1.1.6 The proposed High Street scheme is shown in [Appendix 1] and the extent of the advertised 20mph speed limit is shown in [Appendix 2].
1.2Public Engagement
1.2.1 Media
1.2.2 Two advertisements were taken out in the Tonbridge Courier in the weeks prior to the engagement events to inform the public of the scheme and upcoming exhibitions.
1.2.3 The local Press also followed up with their own newspaper, web and radio articles.
1.2.4 Web Site
1.2.5 A web site was produced which detailed the public engagement events, hosted the scheme proposal drawings with artists’ impressions and providing a contact form for queries and comments.
1.2.6 Links to this site are hosted on both the TMBC and KCC websites.
1.2.7 Business Interviews
1.2.8 On 4th and 5th February, officers visited all the businesses on the High Street within the proposed scheme (approximately one hundred properties) as well as those in the Angel Walk and Pavilion shopping centres. This allowed officers to discuss the scheme directly with business owners and managers, obtain their
JTB - Part 1 Public 30 March 2015 3
contact details for futures updates and enquire about each business’s delivery and loading needs.
1.2.9 The proposals were well received by businesses, many of whom were enthusiastic about improvements for the High Street.
1.2.10 Public Engagement Event
1.2.11 An exhibition was held at Tonbridge Castle on 5th, 6th and 7th February where the public could view large scale drawings of the proposed scheme and see artists impressions.
1.2.12 The project team were on hand to meet the public, explain the proposals and answer queries.
1.2.13 All sessions were well attended and the advanced press releases had helped boost awareness and attendance at the exhibition.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Transportation Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
Parking Action Plan, Access Group 9That the decision of the Cabinet Member for Transformation and Infrastructure to set aside the objections attached at...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.